Clark v. Moore

3 Mich. 55
CourtMichigan Supreme Court
DecidedJanuary 15, 1853
StatusPublished
Cited by22 cases

This text of 3 Mich. 55 (Clark v. Moore) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clark v. Moore, 3 Mich. 55 (Mich. 1853).

Opinion

By the Court,

Douglass, J.

'Indebitatus assumpsit brought by Moore & Co. for goods sold and delivered in pursuance of the following agreement:

“ E. Moore & Co. hereby contract and agree to furnish Mr. J. P. Clark all the tarred and Manilla cordage, spun yarn, and hamline necessary to rig a vessel said Clark is now building at Truago, at ten and a half cents per pound, (except bolt ropes for making sails,) to be delivered on or before the first day of September next. It is agreed that the said Clark shall [57]*57pay one balf in cash on delivery, and the balance in six months. E. Moore & Co..
J. E. Clark-
“ Detroit, July 9th, 1846.”

On the trial the plaintiffs proved the delivery of materials called for by this contract at sundry times between August 1st and October 29th, 1846, amounting at the contract prices to 1437 93.

The defendant proved that this was less than the quantity required to rig the vessel, and that the plaintiffs refused on demand to furnish the residue.

Under a stipulation entered into' between the parties that any legal claim for damages arising out of the plaintiffs’ nonperformance of the contract might be shown in defence, the defendant offered to prove that when the plaintiffs refused to furnish the balance of the materials they had agreed to deliver, the same could not be procured in the Detroit market, but had to be procured elsewhere; that in consequence, considerable delay necessarily accrued in getting said' vessel ready for sea, during which time the -defendant lost the use of her, and was wholly deprived of the profits which she might have earned, and was thus damaged to a large.amount.

But the Court rejected this evidence as. inadmissible; t® which ruling the defendant excepted.

It does not appear that there was any evidence tending to prove that the defendant had ever returned or offered to return the goods which had been delivered under the contract, or that the. plaintiffs had demanded a return of them. Nor was there any evidence except the contract as to their value.

The evidence being closed, the Court instructed the jury that although the plaintiffs might have failed to complete the performance of their agreement, yet they were entitled to recover the contract price for such portion of the materials as had been delivered under it.

To which charge the defendant’s counsel' excepted, and the [58]*58jury having found a verdict for the plaintiffs in conformity with the charge of the Court, the cause was removed to this Court by writ of error and bill of exceptions.

First, as to the instruction of the Court below that Moore & Co. were entitled to recover. Clark was not bound to accept any of the materials contracted for unless the whole were delivered. When after furnishing a portion of them,. Moore-& Co. refused to deliver the residue, he was at liberty to decline the portion he had received. But there was no evidence that he did so, and the jury were bound to presume that he retained them in silence. This was an acceptance, and the law implies an engagement on his part to pay for them.

The case comes directly within the- principle- that though a contract of sale be entire, and the seller deliver only a part of the goods bargained for, yet if the vendee retain such part; the vendor may recover the value of the part retained in an- action for goods sold and delivered. (Oxendale vs. Wetherell, 9 Barn. & Cress. 386; Shipton vs. Casson, 5 Id. 378; Bragg vs. Cole, 6 J. B. Moore, 114; Champion vs. Short, 1 Camp. 53; Bowker vs. Hoyt, 18 Pick. 555; Roberts vs. Beatty, 2 Penn. R. 63; Shaw vs. Badger, 12 Serg. & R. 275; Chitty on Contr. 430; Story on Sales, §§ 424, 439.) We-are aware that a contrary doctrine may be considered as established in New York by Champlin vs. Rowley, 13 Wend. 258; S. C., 18 Id. 187, and Mead vs. Degolyer, 16 Id. 632, which .cases have been recently followed in Ohio in Witherow vs. Witherow, 16 Ohio R. 238, but not without-the protest of -Justice Read in an able dissenting opinion.

In the two first cases it distinctly appeared, and in the last "there was ground for the presumption, that the plaintiff had willfully refused to complete the performance of his contract with the view of profiting by the rise in the'market of articles to be delivered. But they go upon the broad ground that 'the deliverymi all the goods was a condition précedentto the payment of the price or value of any part of- them, though [59]*59such- part may have been accepted and retained by the vendee. Such a doctrine may have enabled the Courts of New York and Ohio to inflict a salutary though somewhat severe punishment upon the bad faith of the vendor, in each of the cases referred to, but in a majority of the cases actually arising. to which, it is equally applicable, it would lead to .monstrous injustice. Suppose A contracted to deliver to 33 1000 bushels of wheat by a certain day, B agreeing to pay therefor so much per bushel on or after the day of delivery. A from time to time delivers wheat to the amount of 900 bushels, but is prevented by bankruptcy or any other of the ordinary accidents or casualties4>f business from delivering the residue. According to this doctrine, A’s failure to deliver B 100 bushels works a complete forfeiture to B of,the 900 delivered. It was stated by Lord Tenterden, in Oxendale vs. Wetherell, and admitted by Cowen, J., in Mead vs. Degolyer, that this must be the result. It was apparently the manifest hardship of such a case which induced the Supreme Court of Ohio to hint that where an excuse was shown for the vendor’s failure to complete the performance, he might maintain an action for the goods delivered. But if the delivery of the entire quantity be a condition precedent to his right of action, I imagine that nothing less than the act of God, of the law, or of the vendee, could excuse his non-performance of it

It would occupy too much space to examine the reasoning of these cases at length. All that need* be said of them is, that they are contrary to the well-settled law of England, Massachusetts and Pennsylvania, and that the application of the rule they assert to a majority of the cases which would fall within it, must shock the moral sense of every man. The law is best administered when it enforces equity and disables fraud.

Secondly, as to the charge of the Court that the plaintiffs were entitled to recover the con tract price of the goods delivered. There is much authority for saying that in cases like [60]*60the present, the vendor is entitled to recover the contract price,, deducting any damage which the vendee may show, he has sustained in consequence of the non-delivery of all the goods. But whether this is so it is not now necessary to determine. In this' case there was no evidence before the jury as to the value of the goods, except the contract. This was some evidence, and in the absence of any other the jury were bound by it; and even if the charge of the Court on this point was incorrect as the statement of the rule of law, it is no ground of error, because a different charge could have had no influ: ence upon the verdict.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kewin v. Massachusetts Mutual Life Insurance Company
295 N.W.2d 50 (Michigan Supreme Court, 1980)
Stanback v. Stanback
254 S.E.2d 611 (Supreme Court of North Carolina, 1979)
Stewart v. Rudner
84 N.W.2d 816 (Michigan Supreme Court, 1957)
Vance v. Forty-Eight Star Mill
215 P.2d 1016 (New Mexico Supreme Court, 1949)
American National Bank v. Barley
189 N.W. 22 (Michigan Supreme Court, 1922)
Randall v. Detroit & Mackinac Railway Co.
180 N.W. 361 (Michigan Supreme Court, 1920)
Avgikos v. Lowry
179 P. 988 (Utah Supreme Court, 1919)
Frederick v. Hillebrand
165 N.W. 810 (Michigan Supreme Court, 1917)
Lardie v. Manistee & Northeastern Railroad
158 N.W. 31 (Michigan Supreme Court, 1916)
Galinski v. Thomas
146 N.W. 191 (Michigan Supreme Court, 1914)
Henry v. Hobbs
130 N.W. 616 (Michigan Supreme Court, 1911)
David v. William Whitmer & Sons, Inc.
46 Pa. Super. 307 (Superior Court of Pennsylvania, 1911)
C. W. Hunt Co. v. Boston Elevated Railway Co.
85 N.E. 446 (Massachusetts Supreme Judicial Court, 1908)
Michigan Yacht & Power Co. v. Busch
143 F. 929 (Sixth Circuit, 1906)
Carnegie, Phipps & Co. v. Holt
58 N.W. 623 (Michigan Supreme Court, 1894)
Shouse v. Neiswaanger
18 Mo. App. 236 (Missouri Court of Appeals, 1885)
People's Ice Co. v. The Steamer "Excelsior."
6 N.W. 636 (Michigan Supreme Court, 1880)
Michigan Central Railroad v. Burrows
33 Mich. 6 (Michigan Supreme Court, 1875)
Wilson v. Wagar
26 Mich. 452 (Michigan Supreme Court, 1873)

Cite This Page — Counsel Stack

Bluebook (online)
3 Mich. 55, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clark-v-moore-mich-1853.