Parke v. Pence Springs Co.

118 S.E. 508, 94 W. Va. 382, 1923 W. Va. LEXIS 149
CourtWest Virginia Supreme Court
DecidedJune 27, 1923
StatusPublished
Cited by1 cases

This text of 118 S.E. 508 (Parke v. Pence Springs Co.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parke v. Pence Springs Co., 118 S.E. 508, 94 W. Va. 382, 1923 W. Va. LEXIS 149 (W. Va. 1923).

Opinion

McGinnis, Judge:

This is a writ of error to a judgment of the Circuit Court of Summers County, in an action of assumpsit, brought by the plaintiff, John Parke as surviving- partner of Parke-Grimes & Company, a partnership, against the Pence Springs Company, a corporation.

The object of this action was to recover from the defendant, the sum of $4735.94 represented by the plaintiff-to be the unpaid balance on the contract price for the construction of the Pence Springs Hotel at Pence Spring, West Virginia, by which the plaintiff agreed to provide all materials, and perform all the work, and complete the building on or before July 1, 1917 for $33553.00, which amount, as claimed by the ■plaintiff, includes $609.99, charged by the plaintiff for hauling 225,000 brick.

At the March term of. said court, the defendant demurred to the declaration filed in the case, and the demurrer was overruled, thereupon the defendant filed a special plea of payment, which plea sets forth that the defendant had paid to the plaintiff at various times before the institution of this suit the aggregate sum of $37,282.17. There is no controversy about this payment, the plaintiff claims that by reason of extra work done and materials furnished, that the defendant, notwithstanding the payment aforesaid, still is indebted to him the said sum of $4735.94. There was also a plea of non assumpsit filed, and a notice of recoupment. The case was tried on these -issues on January 10th and 11th 1921 and, at the conclusion of the evidence, the court, on motion of counsel for the defendant, gave to the jury a peremptory instruction to find for the defendant, and a verdict was accordingly rendered; a motion was made to set aside said-verdict, which was overruled and judgment was thereon accordingly entered.

It appears from the record, that Parke-Grimes & Company, a partnership, of which the Plaintiff John Parke is the surviving partner, was, in the year 1916, engaged in business as building contractors with principal offices at Chattanooga, Tennessee; that on or about December 20, 1916, this partner[385]*385ship entered into a written contract with, the defendant, Pence Springs Company, a corporation, for the construction of a hotel building at Pence Springs, West Virginia, to be known as the Pence Springs Hotel; which building was to be built and completed in accordance with the plans and specifications prepared by Meanor and Sweeney, architects of Huntington, West Virginia, and was to be ready for occupancy as a hotel, on or before July 1, 1917. The building was not completed within the time specified, in fact was pot completed until June 4, 1918, In defendant’s notice of re-coupment it claims, under article VI of the "contract, that it is entitled to be allowed $25.00 per day from July 1, 1917, to June 4, 1918, as liquidated damages. However, on the trial, the defendant waived all claim for liquidated damages accruing after February 19, 1918, at which time the defendant took Over the work and completed the building on June 4, 1918, and the main questions of . dispute in this ease arose from the construction and application of articles VI and VII of the contract. Article VI of the contract is as follows:

“Art. VI. The contractors shall complete the several portions, and the whole of the work comprehended in this agreement by and at the time hereinafter stated, to wit: The contractors agree to complete the building and have it ready for occupancy as a hotel by the first, day of July, 1917. A bonus of $25.00 per day will be paid the contractors for each and every day remaining after the building is' completed as herein provided before July 1st, 1917, and the contractors will pay to the owners $25.00 per day for each and every day the building remains uncompleted after July 1st, 1917.”

Article VII of the contract is as follows:

“Art. VII. Should the contractors be delayed in the prosecution or completion of the work by the act, neglect or default of the owner, of the architects, or of any other contractors employed by the owners upon the work, or by any damages caused by fire or other casualties for which the contractors are not responsible, or by combined action of workmen in no wise caused by or resulting from default or collusion on the part of the contractors, then the time herein [386]*386fixed for tbe completion of the work shall be extended for a period equivalent to tbe time lost by reason of any or all the causes aforesaid, which extended period, shall- be, determined and fixed by the architects; but no such allowance shall be made unless a claim therefor is presented in writing to the architects within forty-eight hours .of the occui-rence of such delay.”

The plaintiff insists that the clause in the contract requiring the contractors to pay the owners $25.00 per day for each and every day the building remains incomplete after July 1, 1917, is a penalty and not liquidated damages, and cannot, for that reason, be set up against the plaintiff’s claim, and the plaintiff has correctly stated the law in the brief of his counsel, in which 'he says:

“It is, of course, elementary that if the provision is a stipulation for liquidated damages, it can be set up against the demand of the plaintiff, but if it is a penalty provision it cannot be set up.”

To support the contention of the plaintiff on this question the plaintiff’s counsel cited, Wheeling Mould and Foundry Company v. Wheeling Steel and Iron Company, 58 W. Va. 62; and Charleston Lumber Company v. Friedman, 64 W. Va. 152, and particular attention is called to the latter case. The defendant also relies on the cases cited above to support its theory that the $25.00 referred to in said article of the contract is for liquidated damages. ■ ■

In the first ease referred to, the defendant entered into a written contract with the plaintiff by which the plaintiff was to manufacture, and deliver, to the defendant certain Pipe Mill Machinery. The contract recited that the contractor had full knowledge of the owner’s requirements in regard to the machinery and full knowledge that the building of the machinery was to be begun forthwith and that it was necessary that it should be delivered at Benwood, W. Va., on or before January 14, 1902:

“Among other things, the contract provided, in effect, that the contractors should not further engage its capacities so as to militate against the manu[387]*387facturer and deliery of the machinery at Benwood, W. Va., by noon of January 14, 1902, that neither party should be liable to the other in damages for delays due to wars, strikes, fires or accidents beyond their control; that in case of delay from any of said causes a certificate for the time lost should be required; that all drawings furnished the contractor should remain the property of the owner and be returned to it on completion of the work; that the owner should, furnish certain materials including motors to be used in, and in connection with the manufacture of the machinery to be manufactured and delivered by the contractor; that all the foundation should be prepared By the owner; that in consideration of the faithful carrying out.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gillioz v. State Highway Commission
153 S.W.2d 18 (Supreme Court of Missouri, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
118 S.E. 508, 94 W. Va. 382, 1923 W. Va. LEXIS 149, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parke-v-pence-springs-co-wva-1923.