Wheeling Mold & Foundry Co. v. Wheeling Steel & Iron Co.

57 S.E. 826, 62 W. Va. 288, 1907 W. Va. LEXIS 37
West Virginia Supreme Court·Decided June 14, 1907·Published·Cited by 18 cases

Opinion

Miller, Judge:

The verdict and judgment on the new trial awarded by this Court (58 W. Va. 62) were, as on the first, for the identical sum sued foi — $12,298.98. On the former hearing, the judgment of the circuit court overruling the demurrer to the amended declaration and each count thereof was not challenged, but is now assigned as error. On the last trial, on motion of the defendant to strike out the several counts, the court struck out the first but overruled the motion as to the others. ' The argument of counsel relate to the second and third counts, and we need notice them only. The former opinion recites the substantial provisions of the contract declared on, and they need not be here repeated.

The second count avers that, after the contract was made and the drawings furnished, the plaintiff proceeded with due diligence to do the work, which it is averred was of such a character and magnitude as to' require in its completion for a long period the entire time and capacity of plaintiff’s manufacturing establishment; that shortly after making the contract the defendant procured the plaintiff to agree that the drawings furnished' should be modified, and the work done in accordance with other drawings thereafter to be furnished by the defendant; that, pursuant to said last arrangement, the original drawings were surrendered, after which the defendant furnished the plaintiff a small number of the substituted drawings; that the plaintiff proceeded to do the work and manufacture the machinery so far as it could with the new drawings received, the starting of the work according thereto involving considerable change in all succeeding work and in all portions of the articles thereafter to be manufactured, so that it was impracticable to proceed further until the residue of the new drawings should also be furnished, which, by way of assigning breach of contract, it is further averred the defendant failed to furnish until long after January 14, 1902, by reason whereof the plaintiff was prevented from completing. the work within the time provided, and which but for such delay of the defendant it alleges it would have done. It is further averred that as soon as practicable [291] after the said new drawings were subsequently furnished (the time when not alleged) the plaintiff proceeded with the utmost diligence to manufacture the machinery, but was unable to complete the same until. September 24, 1902; that on the day last named it had fully performed all the work and manufactured all the machinery, which was on the same day delivered to and accepted by the defendant; that the delay therein was not due in any respect to any fault or dereliction of the plaintiff, but wholl3>- to the fault of the defendant in the failure to perform those things which under the said agreement and the subsequently made arrangement it was to perform; that by reason of the premises the defendant became and was liable to pay the plaintiff thirty days after the said 24th day of September, 1902, when there was a complete erection and acceptance of the whole machinery, the said sum of $58,526, which, though often requested, the defendant has failed and neglected to do, etc.

The third count is substantially the same as the second, except it avers more specifically the duty of the defendant under the contract to provide foundations and motors, and introduces as additional excuse for delay the failure of the defendant to provide these foundations and motors. As a breach of its duty to provide motors, the plaintiff alleges that the defendant did not, though often requested by plaintiff, furnish and deliver them; either at its place of business, the place of erection or elsewhere, until long after the time when according to the said contract it should have delivered the same, and until long after January 14,1902, by reason whereof the plaintiff alleges it was further delayed in the manufacture of said machinery and completion of the work; but that subsequently, when after long and unreasonable delay the defendant did deliver said motors, it.promptly upon receipt thereof (date and place not averred), as soon as practicable and with the utmost diligence, proceeded to do the work and manufacture the machinery. It is also averred that the improper construction of said foundations necessitated their reconstruction; that the plaintiff could not finish the work until the foundations had been reconstructed; and that the improper construction and consequent reconstruction of the foundations was the cause of further delay in the completion of the work and the manufacture of the machinery by the plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Wheeling Mold & Foundry Co. v. Wheeling Steel & Iron Co., 57 S.E. 826, 62 W. Va. 288, 1907 W. Va. LEXIS 37 (W. Va. 1907).

57 S.E. 826 (Wheeling Mold & Foundry Co. v. Wheeling Steel & Iron Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State Ex Rel. Allstate Insurance v. Union Public Service District
151 S.E.2d 102 (West Virginia Supreme Court, 1966)
Preston County Coke Co. v. Preston County Light & Power Co.
119 S.E.2d 420 (West Virginia Supreme Court, 1961)
Payne v. Ace House Movers, Inc.
112 S.E.2d 449 (West Virginia Supreme Court, 1960)
Wright v. Standard Ultramarine and Color Co.
90 S.E.2d 459 (West Virginia Supreme Court, 1955)
Clark v. Douglas
81 S.E.2d 112 (West Virginia Supreme Court, 1954)
State v. Evans
66 S.E.2d 545 (West Virginia Supreme Court, 1951)
Williams v. Zimmerman
20 S.E.2d 785 (West Virginia Supreme Court, 1942)
State v. Stone
130 S.E. 124 (West Virginia Supreme Court, 1925)
State v. Andy Scurlock
130 S.E. 263 (West Virginia Supreme Court, 1925)
Hill v. Ansted National Bank
123 S.E. 417 (West Virginia Supreme Court, 1924)
State v. White
94 S.E. 972 (West Virginia Supreme Court, 1918)
Paull v. Pittsburgh, Wheeling & Kentucky Railroad
78 S.E. 100 (West Virginia Supreme Court, 1913)
Bannister v. Victoria Coal & Coke Co.
61 S.E. 338 (West Virginia Supreme Court, 1908)