Rowland Lumber Co. v. Ross

40 S.E. 922, 100 Va. 275, 1902 Va. LEXIS 25
CourtSupreme Court of Virginia
DecidedMarch 13, 1902
StatusPublished
Cited by9 cases

This text of 40 S.E. 922 (Rowland Lumber Co. v. Ross) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rowland Lumber Co. v. Ross, 40 S.E. 922, 100 Va. 275, 1902 Va. LEXIS 25 (Va. 1902).

Opinion

Keith, P.,

delivered the opinion of the court.

P. Sanford Ross sued the Rowland Lumber Company in assumpsit and obtained a judgment against it for the sum .of $4,244.99, with interest at the rate of 6 per cent., and the case is before us upon exceptions taken to the rulings and judgment in the trial court.

The Rowland Lumber Co., desiring to have a channel dredged from a point in Scott’s Creek, Norfolk harbor, to the áte of its proposed lumber shed, received a letter from P. Sanford Ross Company of date November 3, 1899, addressed to Gr. M. Serpell, Esq., as follows:

“Dear Sir,—We will agree to do what dreclging you have to do at your terminal at Pinner’s Point for eleven three quarters (Ilf) per cubic yard, scow measurement. Material to be put in scows and scowed away, work to be done in >a first-class and thorough manner, and subjected to your approval. Hoping the above figure is a satisfactory one to you, and you will feel so disposed to let us do the work, we remain,
Yery truly yours,
P. SANFORD ROSS (Inc.),
Per Ely.”

On January 23, 1900, Serpell, acting for the Rowland Lumber Co., replied as follows:

“Mr. P. Sanford Ross, Norfolk, Ya.:
Dear Sir,—I have your bid of eleven 'and three-quarter (Ilf) cents per cubic yard for digging a channel about 600 feet long [277]*277and forty feet' wide, and about thirteen feet at low water in Scott’s creek, Norfolk harbor, to the site of the proposed lumber shed of Rowland Lumber Company, with following condition: Quantities to be paid for by scow measurement, deductions to be made for all dredging over thirteen feet in depth at mean low water, and for greater width than forty feet. An allowance of six inches will be made for back filling.
Tours truly,
Gk M. SERPELL,
Eor Rowland Lumber Co.
Accepted: P. Saneord Ross.
Per Ely, for Sanford P. Ross.”

These letters are the evidence of the written contract between the plaintiff and defendant. In the latter part of January the Sanford Ross 'Dredging Company commenced operations. It claims that it found the work more difficult than was expected; that it had been misled by the representations of the Lumber Company as to the place where the channel was to be dredged; that it ran further into the shore than was anticipated; the dredging being thereby rendered more difficult, and, the depth of water proving insufficient to float the scows by which the material excavated was to be removed, necessitated the handling of material more than once, diminished the load which the scows were able to take to the dumping ground, and greatly increased the cost.

The contention of the Dredging Company in the court below was that very soon after it commenced work and found itself confronted with these adverse conditions, it represented the situation to Serpell, through whom the contract with the Lumber Company had been made, and demanded a modification of it as to the rate 'of compensation to be paid, and the manner in which the material to be removed was to be estimated.

It cannot be denied that there is evidence which tends to [278]*278prove its contentions in these respects. On the other hand, it seems plain that the verdict and judgment are for a sum greater than is authorized hy the written contract, though we are not prepared to state in precise terms the amount of the excess. If, then, the defendant in error recovered a larger sum from the plaintiff in error than was justly due from it under its written contract the judgment must be reversed, unless the evidence shows a modified or substituted verbal contract under which the recovery may be maintained. As we have said, the Dredging Company claims that it -made its complaint, and was promised relief very soon after it commenced work. This is denied by the Lumber Company, and the court is asked to consider, in determining the issue thus made, not only the testimony of witnesses, but certain documentary evidence.

On the 16th day of [February, 1900, the following letter was addressed hy the Sanford Ross Company to G-. M. Serpell:

“Dear Sir,—¥e would resp. ask of you that you would allow us a higher price for this hard digging, that we have found for about 150 in the forty-foot cut, as the material is such that it is all our machine can do to dig it, as it is composed of hard clay and sand, and an average in same when seowed away would be very small, so much so, that after we had paid the charter of two tug boats in connection with the machine (also the working machine) would amount to $125 per day, withtout wear and tear to machine. When we g'ave you our figure of Ilf cents per cubic yard scow measurement for this work, we had no idea that you expected to go in so far in shore (which has caused the hard digging). If we had known this ait first, we would have gone higher in our price to allow for this ■hard material. We have also been handicapped on the work from the beginning by having low tides, which delayed us on our work. We could not get enough water to float our scows full. We feel that our figure was an exceedingly lew one for such a small job, but we were in hopes that we would come out [279]*279on top 'by giving you a No. 1 job on this work. S'o far we have not cleared expenses, as we have had bad weather to contend with, and now, with this hard material that we have struck in the forty-foot cut about 150 feet in that you wish us to scow away, we would respectfully ask of you to give us a price for same that we could clear expenses on. "We conscientiously feel and would ask that you give us eighteen cents per cubic yard scow measurement for this 150 by forty cut in, as in this material we could not average 800 cubic yards per day. If we could have thrown this material over on each side of the cut and let it lay we would have finished this work at Ilf cents, but when we come to scow it away, this necessitates two tug boats, one to wait on machine to put scows in and take same out, and the other to take tow to dump and back. This puts the cost on us for tug charter of eighty dollars per day. And to run a machine is an actual cost of forty-five dollars per day. This makes the total expense per day one hundred and twenty-five dollars. We would like to go ahead on this work and finish it up in good shape so that you would be perfectly satisfied with same, but to do this Ilf cents and scow material away, we would lose from thirty to thirty-five dollars per day in this hard material.
Hoping that you may grant the above request of eighteen cents per cubic yard, scow measurement, so that we may continue with the work, we remain,
Yery truly yours,
P. SANFORD ROSS (S. M. E.)”

On February 20th, Serpell sent the following reply:

“Mr. P. Saneord Ross, Norfolk, Ya.:
Bear Sir,—I am in receipt of your letter requesting an advance price over your contract for a part of the dredging you are doing at Pinner’s Point for the Rowland Lumber 'Company, [280]*280and have referred the letter to Mr. O. S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pro Football Inc. v. Paul
569 S.E.2d 66 (Court of Appeals of Virginia, 2002)
Ferk, Ltd. v. Turner Enterprises, Ltd.
43 Va. Cir. 238 (Charlottesville County Circuit Court, 1997)
Hammond Hotel & Improvement Co. v. Williams
176 N.E. 154 (Indiana Court of Appeals, 1931)
Virginia Hardwood Lumber Co. v. Hughes
124 S.E. 283 (Supreme Court of Virginia, 1924)
Atlantic Coast Realty Co. v. Townsend
98 S.E. 684 (Supreme Court of Virginia, 1919)
Roach v. Harty Coal Co.
92 S.E. 458 (West Virginia Supreme Court, 1917)
Charleston Lumber Co. v. Friedman
61 S.E. 815 (West Virginia Supreme Court, 1908)
Wheeling Mold & Foundry Co. v. Wheeling Steel & Iron Co.
57 S.E. 826 (West Virginia Supreme Court, 1907)
Hurxthal v. Boom Co.
44 S.E. 520 (West Virginia Supreme Court, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
40 S.E. 922, 100 Va. 275, 1902 Va. LEXIS 25, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rowland-lumber-co-v-ross-va-1902.