Pittsburg Iron & Steel Engineering Co. v. National Tube Works Co.

39 A. 76, 184 Pa. 251, 1898 Pa. LEXIS 888
Supreme Court of Pennsylvania·Decided January 3, 1898·No. Appeal, No. 145·Published·Cited by 8 cases

Opinion

Opinion by

Mb. Justice Dean,

On June 11, 1892, the plaintiff entered into a written contract with defendant to erect a Bessemer steel plant of eight buildings, equipped with all the machinery necessary for the operation of a Bessemer steel pipe manufactory. The defendant agreed to have all building foundations ready for the super[259] structures by December 1, 1892, and all other foundations by January 1, 1893. At the date of the contract defendant was operating on part of the same ground an iron pipe plant, employing about 7,000 men. In view of this, and to avoid as much as possible the interruption to their business while the new work was in progress, this clause was inserted in the contract : “ It is understood that this contract is to be completed on or before June 1, 1893, and as a failure on the part of the party of the first part to complete the work embraced in this contract would, in view of the necessities of the party of the second part and the requirements of its business, involve great loss to the second party which it would be difficult to estimate, it is hereby agreed that for each day after June 1, 1893, that the work remains unfinished, the first party shall pay to the second party the sum of three hundred dollars as liquidated damages.”

The work was not completed until about January 1, 1894, seven months after the date fixed in the contract, although defendant was partly in possession from October, 1893. The consideration was to be $340,000, in nearly equal instalments at sixty days’ intervals, commencing September 15, 1892. The plaintiff admitted payments to the amount of $323,300.65 on the contract, but claimed the additional sum of $53,011.38, for changes and additions to the original specifications, which, with a balance unpaid on the principal contract of $16,699.35, made the entire sum claimed $69,710.73. The plaintiff averred in its statement: 1. The contract and amount of claim. 2. That the delay of plaintiff in completion of contract of June 1,1893, was attributable solely to defendant’s conduct; that it had not prepared the foundations for the structures by December 18, 1892; that at its request, during the progress of the work, costly and extensive changes were made in the original plans, and large additions thereto, and by reason thereof the time was prolonged, but that, nevertheless, the work was completed as soon as possible. The affidavit of defense a/verred that defendant was entitled to have set off the $300 per day for so many days as plaintiff was in default after June 1,1893, in completion of building; denied the foundations were not ready at the times named in the contract; averred that all changes in the plans and work were voluntary on part of plaintiff, and that the delay [260] was caused by plaintiff’s neglect in preparing the working plans. It claimed damages by reason of plaintiff’s default, in the amount of $66,300.

The statement of claim and affidavit of defense made up the issue as tried in the court below. The evidence on each side was voluminous, and the contention was wholly one of fact to be settled by the jury; they found for plaintiff, $76,154.48, about the amount of plaintiff’s claim with interest, and we have this appeal by defendant, with fifteen assignments of error. The complaints of appellant in the assignments are that plaintiff failed to establish by competent evidence the facts on which it sought relief from strict performance of its contract as to time of completion, and further that the court below committed error in its instructions to the jury as to the rules which should control them in computation of defendant’s damages. As to the facts relied on by plaintiff to excuse it from strict performance, there was evidence tending to establish each one of them; contradicted, it is true, by evidence on part of defendant, but still' leaving the contention in such situation that the court could not say the evidence was insufficient; therefore, there was no error in submitting it to the jury.

Free access — add to your briefcase to read the full text and ask questions with AI

Pittsburg Iron & Steel Engineering Co. v. National Tube Works Co., 39 A. 76, 184 Pa. 251, 1898 Pa. LEXIS 888 (Pa. 1898).

39 A. 76 (Pittsburg Iron & Steel Engineering Co. v. National Tube Works Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Commonwealth v. W. P. Dickerson & Son, Inc.
400 A.2d 930 (Commonwealth Court of Pennsylvania, 1979)
Hartford Electric Applicators of Thermalux, Inc. v. Alden
363 A.2d 135 (Supreme Court of Connecticut, 1975)
Universal Builders, Inc. v. Moon Motor Lodge, Inc.
244 A.2d 10 (Superior Court of Pennsylvania, 1968)
Mazer v. Ladow
34 Pa. D. & C. 19 (Philadelphia County Court of Common Pleas, 1938)
Parish Mfg. Corp. v. Martin-Parry Corp.
131 A. 710 (Supreme Court of Pennsylvania, 1925)
Texter v. Wachs
73 Pa. Super. 19 (Superior Court of Pennsylvania, 1919)
Mayor of Baltimore v. Ault
94 A. 1044 (Court of Appeals of Maryland, 1915)
Wheeling Mold & Foundry Co. v. Wheeling Steel & Iron Co.
57 S.E. 826 (West Virginia Supreme Court, 1907)