Parish Mfg. Corp. v. Martin-Parry Corp.

131 A. 710, 285 Pa. 131, 1926 Pa. LEXIS 416
CourtSupreme Court of Pennsylvania
DecidedNovember 25, 1925
DocketAppeal, 41
StatusPublished
Cited by22 cases

This text of 131 A. 710 (Parish Mfg. Corp. v. Martin-Parry Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parish Mfg. Corp. v. Martin-Parry Corp., 131 A. 710, 285 Pa. 131, 1926 Pa. LEXIS 416 (Pa. 1925).

Opinion

Opinion by

Mr. Justice Sadler,

The Martin-Parry Corporation, defendant, was engaged in the manufacture of automobile trucks, and, on December 19,1919, ordered from the plaintiff, the Parish Manufacturing Corporation, 1,000 frames, required in the construction of the completed motors. Deliveries were promised in four equal parts during the months of March, April, May and June of the year following. Later, certain changes were made in the specifications, and, on March 1st, the original order was confirmed, the price being slightly increased because of the alterations requested. At that time, prompt shipments were demanded, but the seller expressed doubt as to its ability to furnish the finished product in less than four to six weeks, agreeing, however, to forward in April. A second modification was made on the 22d of that month, affecting only one-half of the order, and, a few days later, a further change in the location of a drilling hole was authorized.

On May 8th, a small number of frames were sent, but all of their necessary parts had not been forwarded by the 20th. During the period until July 12th, less than one-half had been delivered, though frequent requests for speedy completion of the order appear. On the latter date, attention was called expressly to the failure to comply with the provision of the contract requiring 250 a month to be furnished. It was not until after the 16th of July that the plaintiff started to manufacture the remaining 511. On August 4th, the contract having been assigned in the meantime to another, as will be noticed hereafter, the plaintiff was asked by the assignee to delay completion of the work on hand, and, in the October following, it attempted to cancel the unfilled *135 portion of the order. This suit was instituted against the buyer to recover under the original contract, for loss sustained. The defense was based on an alleged novation, and on the ground that a rescission was justified because of the unreasonable delay in the making of deliveries. From the judgment entered upon the verdict for plaintiff, this appeal was taken.

Errors in the admission and refusal of testimony, in answers to certain points submitted by the respective parties, and to portions of the charge of the court, are averred. Three questions are suggested which require consideration. Was there a novation, and a release of the defendant by the assignment of the contract to the Atlas Truck Corporation, under the circumstances appearing? If there was no discharge of liability worked thereby, did the evidence disclose such a breach of the contract by the seller, in delaying delivery, as to justify a rescission? If defendant remained responsible for the loss sustained, was the proper measure of damages applied? The answer to all of these queries involved a consideration of facts for the jury, but, it is contended, certain trial errors appear which render necessary the granting of a new hearing.

The facts relied upon to establish the novation are briefly as follows: On May 15, 1920, the buyer, the present defendant, transferred its truck business to the Atlas Truck Corporation. Of this action, the plaintiff was promptly notified, and requested to signify its formal assent to the assignment. This was declined, unless performance by the assignee was guaranteed, which defendant agreed to, upon condition that the liability should continue until such time as the new corporation furnished a satisfactory financial statement. The latter was sent on June 29th, and, on its face, showed a large excess of assets over liabilities, and no dissatisfaction with it on this score, or any other, was thereafter made by the seller. From June 1st, all correspondence, with reference to the manufacture of the trucks, *136 was had with the assignee, and continued to the time of bringing this suit. The completed frames were delivered to it, and its checks were issued in payment. From proof of these facts, the jury was asked to find a substitution of the Truck Corporation for the Martin-Parry Corporation, thus relieving the latter from liability in the present proceeding.

The burden is upon one who alleges a novation, to establish it by proper proof, and, in the absence of an agreement that the original obligation be extinguished, and a new one substituted, the original debtor is not released: Jones v. Commonwealth Casualty Co., 255 Pa. 566. Consent to the change in parties must be shown (Wright v. Hanna, 210 Pa. 349; McCartney v. Kipp, 171 Pa. 644), but “may be established by circumstances showing such assent, as well as by expressed words”: 3 Williston on Contracts 3208. The applicable rule has been thus stated: “Doubtless parties to bilateral contracts frequently attempt to effect the substitution of the liability of a new party for that of one of the original parties, and frequently call such an attempted transaction an assignment. By whatever name the parties may call the transaction, if it is made clear that the so-called assignor intends by the transaction to be free from all further liability, it seems that acceptance, by the other party to the contract, of any subsequent performance from the so-called assignee, would amount to assent to a proposed novation, and the so-called assignor would be discharged from further liability” : 1 Williston on Contracts 783.

The correctness of this legal contention was recognized by the learned court below, but the manner of its presentation to the jury is complained of, in that an undue burden of proof was placed on the defendant. It were instructed that, before the evidence offered could have the effect of establishing a novation, the circumstances and facts must show “that the inevitable business conclusion could be no other than [that] it [plain *137 tiff] had substituted” the assignee for the contractor by consent, and “inevitably [led] to the conclusion that it considered the contract as changed.” All that was required of defendant was to establish the disputed fact by the weight of the testimony. At another point, not in connection with the discussion of the relevant evidence, such a declaration appears, but we cannot say that the result may not have been affected by the repeated misstatement referred to: Benjamin v. Colonial Hotel Co., 268 Pa. 459.

In the opinion overruling the motion for a new trial it is suggested that there is doubt as to the legal sufficiency of the evidence to prove a novation, and attention is called to the fact that there was a close relation between the old and new corporations, as shown by the manner of conducting the business, but this, in itself, was not sufficient to establish any fraud, or render the contract between them invalid. It was a fact to be considered, with all the other circumstances, by the jury, under proper instructions: South Side Trust Co. v. Washington Tin Plate Co., 252 Pa. 237.

Plaintiff insists the evidence established no more than an assignment of the contract, and not a novation releasing the assignor from further liability, and to establish which, consent to the change, either express or implied, must be proved. If an assignment, the rights of the creditor remain, for a debtor cannot relieve himself from an undertaking by a mere transfer of his agreement to another, though he may have an action over against the assignee, if compelled to make payments which the latter was bound to liquidate: Blue Star Nav. Co. v. Emmons C. M. Co., 276 Pa. 352; Washington N. Gas Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Franks
95 B.R. 346 (E.D. Pennsylvania, 1989)
Grant Service Co. v. Levy
452 A.2d 19 (Superior Court of Pennsylvania, 1982)
McAlpine v. AAMCO Automatic Transmissions, Inc.
461 F. Supp. 1232 (E.D. Michigan, 1978)
First Pennsylvania Bank, N. A. v. Triester
380 A.2d 826 (Superior Court of Pennsylvania, 1977)
Peninsula Truck Lines, Inc. v. Tooker
388 P.2d 958 (Washington Supreme Court, 1964)
Yoder v. T. F. Scholes, Inc.
173 A.2d 120 (Supreme Court of Pennsylvania, 1961)
Dempsey v. Stauffer
182 F. Supp. 806 (E.D. Pennsylvania, 1960)
Swift v. Allan
128 A.2d 260 (Court of Appeals of Maryland, 1957)
Moritz v. Fisher
6 Pa. D. & C.2d 25 (Lawrence County Court of Common Pleas, 1955)
Gulf Oil Corporation v. Texas City Refining, Inc.
218 F.2d 196 (Fourth Circuit, 1954)
Associates Discount Corp. v. Greisinger
103 F. Supp. 705 (W.D. Pennsylvania, 1952)
Mazer v. Ladow
34 Pa. D. & C. 19 (Philadelphia County Court of Common Pleas, 1938)
Le Bar, to Use v. Patterson
187 A. 278 (Superior Court of Pennsylvania, 1936)
Decker v. Richard J. Seltzer, Inc.
176 A. 29 (Superior Court of Pennsylvania, 1934)
Taylor v. Stanley Co. of America
158 A. 157 (Supreme Court of Pennsylvania, 1931)
Himmelberger v. Central State Bank
224 N.W. 550 (Supreme Court of Iowa, 1929)
Citizens' Bk. of Wind Gap v. Lipschitz
145 A. 831 (Supreme Court of Pennsylvania, 1929)
Reimers v. Tonne
221 N.W. 574 (Supreme Court of Iowa, 1928)
Parish Manufacturing Corp. v. Martin-Parry Corp.
143 A. 103 (Supreme Court of Pennsylvania, 1928)
Atlantic City Tire & Rubber Corp. v. Southwark Foundry & MacHine Co.
137 A. 807 (Supreme Court of Pennsylvania, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
131 A. 710, 285 Pa. 131, 1926 Pa. LEXIS 416, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parish-mfg-corp-v-martin-parry-corp-pa-1925.