American Copper, Brass & Iron Works v. Galland-Burke Brewing & Malting Co.

70 P. 236, 30 Wash. 178, 1902 Wash. LEXIS 667
CourtWashington Supreme Court
DecidedOctober 3, 1902
DocketNo. 4110
StatusPublished
Cited by3 cases

This text of 70 P. 236 (American Copper, Brass & Iron Works v. Galland-Burke Brewing & Malting Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Copper, Brass & Iron Works v. Galland-Burke Brewing & Malting Co., 70 P. 236, 30 Wash. 178, 1902 Wash. LEXIS 667 (Wash. 1902).

Opinion

The opinion of the court was delivered by

Hadley, J.

This action was brought by respondent against appellant to recover a balance alleged to be due on a contract for furnishing certain equipments for a brewery then being constructed by the appellant. The contract was executed in writing and the provisions thereof material to be stated here were as follows:

“The American Copper, Brass & Iron Works agree to construct and build and deliver not later than the 1st of January, 1892, f. o. b. cars at Chicago, the following brewing equipments for the said Galland-Burke B. & M. Co. of [180]*180the size and quality of material and for the agreed price hereinafter stated, viz,: (Here follows a description of material.) All of said equipment to be furnished f. o. b. cars at Chicago for the sum of $5,800 (five thousand eight hundred dollars), which sum tire said Galland-Burke B. & M. Co. agree to pay for same, if up to specifications and contract and delivery made not later than Jan. 1, 1902. If later, then the said American C. B. & Iron Works are to deduct from said amount account of inconvenience, direct damage done to said G.-B. B. & M. Co. and as liquidated damages, the sum of $25.00 per day for each and every day that delivery is made f. o. b. later than said 1st Jany., 1902.”

The written contract is set out in haec verija in the complaint, and it is alleged that it was further agreed between the parties, at the time the contract was entered into, that the respondent should ascertain freight rates on the brewing equipment, and advise appellant, who was to decide and direct respondent whether to ship the equipment as a whole or “knocked down,” and that appellant also then and there agreed that the penalty claims would not be enforced except in the most extreme case of neglect; that said last mentioned stipulations were made a part of the contract, but by oversight or mistake were not included in the written contract. It is further alleged that pursuant to the agreement appellant was notified by respondent concerning the freight rates, but that appellant failed to advise or direct respondent how to ship, and thereby occasioned delay in the delivery of the equipment. It is also alleged that appellant extended the time in which the goods were to be delivered, and that respondent did not deliver the equipment by January 1, 1892, because of said extension of time, as well as because of the failure on the part of appellant to advise as to shipment; but that, as soon as respondent was directed as to the shipment, it complied with its part of the contract in every particular. The answer ad[181]*181mits that the contract set forth in the complaint is a true copy of the contract between the parties, and avers that by the terms thereof, if delivery of said goods was made after January 1, 1892, there should be deducted by respondent from the contract price the sum of $25 per day, as liquidated damages for each and every day that delivery was made f. o. b. later than said date; that respondent did not make such delivery on or before said date, but delayed the same until sixty days after said date, to the great inconvenience and damage of appellant in the sum of $1,500, which sum it asks shall be set off against the claim of respondent, and that appellant shall recover judgment against respondent. The allegations of the answer are denied by the reply. The cause was tried before a jury, and resulted in a verdict for the respondent in the sum of $870. Appellant moved for a new trial, which was denied, and judgment was thereafter entered in accordance with the verdict of the jury.

It is assigned as error that the court permitted the witness Meinshausen, who was president of the respondent company, to testify as to the alleged statements made by Mr. Sam. Galland in relation to the shipping of the goods, it being claimed by appellant that Sam. Galland had no connection with its company, except that he owned some of its stock. The witness Meinshausen testified, in effect, that Sam. Galland waived for the appellant company the stipulation in the written contract that the goods were to be delivered on or before January 1, 1892. The respondent company and its manufacturing plant were located in Chicago, and the appellant company had ordered this brewing equipment to be manufactured for shipment to Spokane, to be used in appellant’s brewery, then being constructed in Spokane. Sam. Galland went to Chicago, arriving there soon after January 1, 1892. He says he went there to be educated as a brewmaster. Whatever may [182]*182have been the primary purpose in going to Chicago, it nevertheless appears that while there he called at the respondent’s place of business, and had some conversation with the officers of respondent company relative to the shipment of this brewing outfit. The witness Meinshausen testified that, when Sam. Galland called at the respondent’s place of business, “we showed him these things, and everything was all ready, and he says: ‘We are not ready. You can keep it as long as you want to. I will let you know when to ship it.’ ” Objection was made to the statement of any conversation between the witness and Sam. Galland until it was first shown that the latter had some authority to hind the appellant company. On the statement of respondent’s counsel that they had a letter from appellant company which would show such authority, the court observed as follows: “If you propose to introduce a letter of that kind in evidence, I will not require you to withdraw the witness now and show that first; hut it is incompetent testimony unless that is shown. I will overrule the objection now.” The witness then proceeded to give testimony similar to that already mentioned, and also to the effect that under the instructions of Sam. Gal-land respondent proceeded to put the equipment together, so that it could he shipped “set up” ready to he put in place upon its arrival in Spokane; and that he so requested in order that the expense of sending men to Spokane to erect it might be avoided — all of which witness claimed was to the delay of respondent. Appellant urges that the letter showing authority from it to Sam. Galland, and to which counsel and court had theretofore referred, was never produced, and that the testimony of the witness should, therefore, not have been permitted to go to the jury under the trial court’s own ruling. A letter was, however, produced, signed by the appellant company, and [183]*183directed to the respondent company, dated February 22, 1892, which was probably six weeks after the alleged conversation with Sam. Galland. This letter was in reply to one from respondent, dated the 18th of the same month, in which had been inclosed a statement of goods already said to be shipped, and which letter also advised appellant that a draft had been forwarded for one-half of the contract price. In the appellant’s reply letter is the following: “It would not be right for us to pay the agreed amount % until the stuff was shipped. On receipt of this, if you have sent kettle, Grant and cooler, why please satisfy our Sam. G. that stuff is coming forward and have him wire us and we will take care of draft.” The above mention of “Sam. G.” it is not disputed refers to Sam. Galland, and being over the signature of appellant, directed to respondent, concerning the subject matter of the shipment of the goods, we think it became a question for the jury to determine whether appellant had authorized Sam. Galland to represent it to the extent of making the statements concerning which the witness Meinshausen testified.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Foster v. Montgomery Ward & Co.
163 P.2d 838 (Washington Supreme Court, 1945)
Smith v. Lambert Transfer Co.
187 P. 362 (Washington Supreme Court, 1920)
Madler v. Silverstone
104 P. 165 (Washington Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
70 P. 236, 30 Wash. 178, 1902 Wash. LEXIS 667, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-copper-brass-iron-works-v-galland-burke-brewing-malting-co-wash-1902.