West v. Jarvi

266 P.2d 1040, 44 Wash. 2d 241, 1954 Wash. LEXIS 275
CourtWashington Supreme Court
DecidedFebruary 16, 1954
Docket32341
StatusPublished
Cited by11 cases

This text of 266 P.2d 1040 (West v. Jarvi) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
West v. Jarvi, 266 P.2d 1040, 44 Wash. 2d 241, 1954 Wash. LEXIS 275 (Wash. 1954).

Opinion

Hill, J.

— Hilda M. Jarvi entered into a contract with West Builders, a copartnership hereinafter referred to as West, for the construction of an addition to her rest home. Numerous differences arose between Mrs. Jarvi and West, some of major importance and some trivial except as they became cumulative. West finally refused to continue with the construction. Other builders were then employed by Mrs. Jarvi to complete the work.

*243 This action was commenced by West to foreclose a building contractor’s lien for $10,290. The heating and electrical contractors and Pioneer Sand & Gravel Company, a corporation, hereinafter called Pioneer, were joined as parties defendant because they had filed liens against the property. They filed cross-complaints seeking foreclosure of their respective liens. Mrs. Jarvi cross-complained against West for damages incurred by her as a result of its abandonment of the contract, including the sum she was compelled to expend to complete the contract and damages for her loss of income because of the failure of West to complete the addition within the time specified in the contract.

West was awarded judgment in the amount of $6,700.61, together with foreclosure of a contractor’s. lien in that amount, plus interest, costs, and $1,200 attorneys’ fee, together with an additional $2,000 attorneys’ fee in the event of an appeal to this court. Pioneer was granted judgment against West for $518.50, and its lien against appellant’s property was foreclosed. It was denied costs and attorney’s fee in the superior court, but was awarded a $250 attorney’s fee in the event of an appeal to this court. Mrs. Jarvi was denied recovery on her cross-complaint. (The relief granted to the heating and electrical contractors is not here material, no appeal having been taken from the judgments in their favor.)

The formula adopted by the trial court to determine the amount of the recovery to which West was entitled was based upon the premise that the contract had been substantially completed by West. The judgment was based upon the contract price, $20,900, plus extras in the amount of $1,462.80 and the three per cent sales tax on the whole ($22,362.80), amounting to $670.86, making a total of $23,-033.66. The following deductions were then made from that total: the payments by Mrs. Jarvi to West and its subcontractors, $14,996.98; the cost of finishing the work under the contract, $981; and certain additional credits to which Mrs. Jarvi was entitled totaling $355.07. The total amount thus credited to her was $16,333.05, leaving a balance due West of $6,700.61, for which amount judgment was entered.

*244 Mrs. Jarvi appeals from those portions of the judgment which grant recovery and foreclosure of the lien to West and foreclosure of Pioneer’s hen, and which deny her recovery on her cross-complaint. Twenty-two assignments of error are made: sixteen directed against the findings of fact, five against conclusions of law, and one in general terms, stating that the trial court erred in not dismissing the actions brought by West and Pioneer and in not granting appellant recovery upon her cross-complaint.

While appellant does not, as we understand her position, object to the formula applied by the trial court, she objects to any judgment in favor of West, and, if it is to have a judgment, she objects to the inclusion of and the amounts of various items in the list of extras, and to the exclusion of certain items or amounts for which she believes she is entitled to credit.

The major questions were: Did West substantially complete its contract? and, Did Mrs. Jarvi’s attitude and conduct justify West’s refusal to complete the contract? The trial court answered yes to both questions, and we cannot say that its findings on those ultimate and decisive facts are not supported by substantial evidence. It necessarily follows that Mrs. Jarvi was not entitled to recover on her cross-complaint against West because she and not West had breached the contract, and that West was entitled to recover against her the amount due on the contract, together with the value of such extras as were established, and to have its lien foreclosed. The major issues in her controversy with West having been decided adversely to her on the facts, there remain for consideration only her contentions with reference to those specific items which affect the amount of, but not the right to, a judgment and the foreclosure of West’s lien.

On most of these items, as on the major issues, there is no issue of law. The trial court’s findings are in almost every instance based upon substantial evidence. A discussion of that evidence would be of no interest and of no value to anyone except the litigants; consequently, except where there are issues of law and where the evidence does not *245 support the findings, no reference will be made to the items challenged.

Appellant urges that the holding of the trial court that West’s liability for the cost of the heating system was limited to $2,000, was a modification of the written contract by parol testimony. Under the trial court’s finding that the heating plans and specifications were not available to West when it submitted its bid or when the contract was signed, the statement by appellant’s architect that the heating system would not cost more than $1,800 or $2,000 and that the bid might be submitted on that basis, would make $2,000 the limit chargeable against West for that item. This is not a case of modification of a contract, but of a bid and contract made and conditioned upon a representation by appellant’s architect and binding upon her. Boynton v. Johnson, 68 Wash. 370, 123 Pac. 522 (1912); Sando v. Kalberg, 138 Wash. 247, 244 Pac. 576 (1926); McGregor v. First Farmers’-Merchants’ Bank & Trust Co., 180 Wash. 440, 40 P. (2d) 144 (1935), obiter.

Appellant urges that her agreement with the architect was such that he had only a very limited agency. Whatever may have been the limitations on the architect’s authority as between appellant and himself, West, until it knew of such limitations, had a right to assume that the usual relationship existed between owner and architect. Sando v. Kalberg, supra.

One of the principal extra items claimed by West was for enlarging certain window openings and furnishing and installing larger windows. Appellant says that the windows had to be changed to conform to the requirements of RCW 74.32.100 [c/. Rem. Supp 1945, § 8358k] that in a “place of refuge” “Window space shall not be less than one-fifth of the floor space.” The trial court was convinced that the windows as originally installed were in accordance with the plans and specifications prepared by the architect, and that West was entitled to be compensated as an extra for the changes ordered by appellant. The authorities cited to the effect that “laws governing citizens of a state are presumed to be incorporated into contracts made by them” *246 have no application to the present situation.. The contract as made was a perfectly lawful one.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shelcon Construction Group, LLC v. Haymond
351 P.3d 895 (Court of Appeals of Washington, 2015)
Shelcon Construction Group v. Scott Haymond
Court of Appeals of Washington, 2015
John W. Goodwin, Inc. v. Fox
1999 ME 33 (Supreme Judicial Court of Maine, 1999)
Schumacher Painting Co. v. First Union Management, Inc.
850 P.2d 1361 (Court of Appeals of Washington, 1993)
J. A. Jensen & Assocs. v. Souder
25 Va. Cir. 382 (Fairfax County Circuit Court, 1991)
Mullen Lumber Co. v. Lore
537 N.E.2d 123 (Massachusetts Supreme Judicial Court, 1989)
Airefco, Inc. v. Yelm Community Schools No. 2
758 P.2d 996 (Court of Appeals of Washington, 1988)
Liner v. Armstrong Homes of Bremerton, Inc.
579 P.2d 367 (Court of Appeals of Washington, 1978)
Huzzy v. Culbert Construction Co.
489 P.2d 749 (Court of Appeals of Washington, 1971)
Larson v. Duclos
281 P.2d 458 (Washington Supreme Court, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
266 P.2d 1040, 44 Wash. 2d 241, 1954 Wash. LEXIS 275, Counsel Stack Legal Research, https://law.counselstack.com/opinion/west-v-jarvi-wash-1954.