Huzzy v. Culbert Construction Co.

489 P.2d 749, 5 Wash. App. 581, 1971 Wash. App. LEXIS 1087
CourtCourt of Appeals of Washington
DecidedOctober 12, 1971
Docket591-1
StatusPublished
Cited by19 cases

This text of 489 P.2d 749 (Huzzy v. Culbert Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Huzzy v. Culbert Construction Co., 489 P.2d 749, 5 Wash. App. 581, 1971 Wash. App. LEXIS 1087 (Wash. Ct. App. 1971).

Opinion

James, J.

Defendant Culbert Construction Co., Inc., contracted to build a house for plaintiff, John P. Huzzy. Without prior notice or demand Huzzy unilaterally terminated the contract, employed another contractor to complete construction, and instituted this action for damages. Huzzy procured writs of garnishment and impounded Culbert’s bank accounts.

Huzzy’s complaint alleges that Culbert breached the contract and “is guilty of having abandoned [its] obligations under the contract, including abandoning further work or building at the site.” He contends that Culbert breached the contract by its shoddy and defective workmanship and by causing delays which threatened the loss of a commitment for a favorable mortgage interest rate. Huzzy claims damages in an amount he alleges was required to remedy defects and to complete construction.

Culbert denies that it breached the contract. It asserts that the house was 90 to 95 per cent complete when Huzzy terminated the contract, and that any defects in construction were readily remediable. Culbert asserts that Huzzy caused or contributed to any delay.

Culbert cross-complained for the unpaid balance of the contract price,, plus extras, and less a.reasonable amount to cover the cost of finishing the house and remedying any *583 defects. Culbert also claimed damages for wrongful garnishment.

Concerning the claimed shoddy workmanship, the trial judge found that the defects were minor and that Culbert could have corrected them. Concerning the claimed delays, the trial judge found that to a substantial degree Huzzy caused them. Further, the trial judge found that Culbert had not abandoned the contract, but was summarily dismissed prior to an agreed extended completion date.

Based upon these findings of fact, the trial judge concluded that Culbert was not in default, but that Huzzy had breached the contract by his unilateral termination. The trial judge determined that Culbert should be given judgment against Huzzy in the amount of $1,537.24. This amount represents an award of $1,000 as damages for wrongful garnishment, plus the net amount due Culbert on the contract (after crediting the contract price plus extras) , plus the state sales tax and less the amount it would have cost Culbert to remedy any defects and complete construction.

On appeal Huzzy asserts that the trial court erred in holding that notice allowing Culbert an opportunity to complete the job was a condition precedent to both the termination of the contract and the suit for damages. In his oral opinion the trial judge did indicate that he felt a notice of claimed defects and an opportunity to remedy them was a “condition precedent” to the bringing of the action.

A trial judge’s oral opinion which is consistent with his formal findings of fact and conclusions of law may be used to interpret them. Ferree v. Doric Co., 62 Wn.2d 561, 383 P.2d 900 (1963). But a finding or conclusion stated in either an oral or a memorandum decision has no binding effect unless it is incorporated in the formal findings or conclusions. Wagner v. Wagner, 1 Wn. App. 328, 461 P.2d 577 (1969). Therefore, assignments of error addressed to oral or memoranda opinions are improper. Ferree v. Doric Co., supra. The authorities cited by Huzzy .to support the rule that an aggrieved party-to a breached contract ordi *584 narily need not give notice before bringing an action for damages, are therefore, not in point. Huzzy was not the aggrieved party and the judgment against him was not grounded upon his failure to give notice. The damages awarded Culbert were for Huzzy’s breach of the contract by his unilateral termination.

Huzzy’s assignments of error 4 through 17 are all addressed to the court’s formal findings of fact. As an appellate court we neither re-try factual issues nor weigh conflicting evidence. McGarvey v. Seattle, 62 Wn.2d 524, 384 P.2d 127 (1963). We review the evidence only to ascertain whether or not the trial judge’s findings are supported by substantial evidence. Reynolds Metals Co. v. Electric Smith Constr. & Equip. Co., 4 Wn. App. 695, 483 P.2d 880 (1971). Our review of the record satisfies us that the trial judge’s findings of fact are supported by substantial evidence.

The trial judge recognized that some of his formal findings of fact might more properly be denominated conclusions of law. His finding of fact 20 is: “The Findings of Fact herein Which are deemed to be conclusions of law would be amended to read as such.” Although the formal findings of fact do contain conclusions of law, we find that they are merely redundant and not inconsistent with the formal conclusions.

Huzzy assigns error to Culbert’s recovering damages for wrongful garnishment. His argument is that since he was allowed setoffs in an amount in excess of the funds impounded by the garnishment writs, the garnishment should not be adjudged wrongful. The argument is without merit.

The extraordinary advantage afforded a creditor by the garnishment statutes is a harsh remedy. 6 Am. Jur. 2d Attachment and Garnishment § 7 (1963). Huzzy’s right to impound Culbert’s bank accounts before judgment was conditioned upon his sworn statement that Culbert was indebted to him and that the debt was just, due and unpaid. RCW 7.32.010 (now RCW 7.33.010). But to recover damages for wrongful garnishment,'a defendant need not *585 prove that the plaintiff lacked probable cause, as is required in the case of an alleged wrongful attachment. Taylor v. Wilbur, 170 Wash. 265, 16 P.2d 457 (1932). A garnishment is wrongful if the plaintiff does not recover a judgment against the defendant. Olsen v. National Grocery Co., 15 Wn.2d 164, 130 P.2d 78 (1942). And even though the primary action be dismissed without prejudice, the garnishment is nevertheless wrongful. Maib v. Maryland Cas. Co., 17 Wn.2d 47, 135 P.2d 71 (1943). Therefore, the allowance of offsets does not cure the “wrongfulness” of Huzzy’s garnishment. The significant considerations are that Culbert was not in default, that Huzzy breached the contract by his precipitous and unilateral termination, and that Huzzy failed to recover a judgment against Culbert.

Huzzy also complains that the damages awarded for wrongful garnishment were excessive. Culbert’s evidence was that its credit was impaired and that it lost the opportunity to bid on three contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Of Washington v. Jonathon Brown
Court of Appeals of Washington, 2019
City of Walla Walla v. $401,333.44
262 P.3d 1239 (Court of Appeals of Washington, 2011)
Wagner Development, Inc. v. Fidelity & Deposit Co.
977 P.2d 639 (Court of Appeals of Washington, 1999)
Hagemann v. Worth
782 P.2d 1072 (Court of Appeals of Washington, 1989)
Tilly v. John Doe
746 P.2d 323 (Court of Appeals of Washington, 1987)
Wilkinson v. Sample
36 Wash. App. 266 (Court of Appeals of Washington, 1983)
Caribe Contracting Co. v. Edwards
18 V.I. 194 (Supreme Court of The Virgin Islands, 1982)
Department of Social & Health Services v. Gerlack
612 P.2d 382 (Court of Appeals of Washington, 1980)
In Re the Marriage of McKinney
546 P.2d 456 (Court of Appeals of Washington, 1976)
Ruskin Fisher & Associates, Inc. v. Mt. Spokane Chair Lift, Inc.
540 P.2d 1393 (Court of Appeals of Washington, 1975)
Pierce County v. Thurston County
536 P.2d 3 (Court of Appeals of Washington, 1975)
Bank of Anacortes v. Cook
517 P.2d 633 (Court of Appeals of Washington, 1974)
Reid Sand & Gravel, Inc. v. Bellevue Properties
502 P.2d 480 (Court of Appeals of Washington, 1972)
Federal Finance Co. v. Solomon
501 P.2d 627 (Court of Appeals of Washington, 1972)
Cromwell v. Gruber
499 P.2d 1285 (Court of Appeals of Washington, 1972)
Hemisphere Loggers & Contractors, Inc. v. Everett Plywood Corp.
499 P.2d 85 (Court of Appeals of Washington, 1972)
Grant v. Morris
498 P.2d 336 (Court of Appeals of Washington, 1972)
Van Horn v. Van De Wol, Inc.
497 P.2d 252 (Court of Appeals of Washington, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
489 P.2d 749, 5 Wash. App. 581, 1971 Wash. App. LEXIS 1087, Counsel Stack Legal Research, https://law.counselstack.com/opinion/huzzy-v-culbert-construction-co-washctapp-1971.