Caribe Contracting Co. v. Edwards

18 V.I. 194, 1982 V.I. LEXIS 134
CourtSupreme Court of The Virgin Islands
DecidedMay 31, 1982
DocketCivil No. 1247/80
StatusPublished

This text of 18 V.I. 194 (Caribe Contracting Co. v. Edwards) is published on Counsel Stack Legal Research, covering Supreme Court of The Virgin Islands primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Caribe Contracting Co. v. Edwards, 18 V.I. 194, 1982 V.I. LEXIS 134 (virginislands 1982).

Opinion

SILVERLIGHT, Judge

MEMORANDUM OPINION

I. FACTS

This case presents a controversy between an owner of land and a building contractor arising out of an alleged breach of a construction contract.

The parties entered into a written contract “to construct a prefabricated house . . .” supplemented by “plans [and specifications] as prepared by [plaintiff] . . . ,”1 Execution of this contract occurred after an original draft had been modified to incorporate a schedule of payments which had been modified by the bank providing' the construction financing for the defendant. The bank is not a party to this action. In all other respects, the contract remained essentially unchanged and, I find, unambiguous. At a time when the building was approximately 89%2 complete the parties fell into disagreement and the stage was set for this dispute.

Two separate and distinct claims are asserted by plaintiff. The first seeks payment of the unpaid portion of the contract price and the second seeks recovery for certain extras allegedly performed by plaintiff at the behest of defendant. These claims will be addressed individually.

II. ADDITIONAL WORK

Plaintiff asserts a claim for each of the following items of work allegedly not covered by the contract.3

Site preparation $1,250.00
Extra block to elevate house 316.00
Extra window 110.00
Porch railing4 416.75
[197]*197Additional outside concrete work 130.00
Difference for ceramic tile plus soap dishes 207.25
Drainage field 320.00
TOTAL $2,859.00

Defendant resists payment for the site preparation and drainage field, asserting that both these items were covered by the contract price and did not constitute extras. She does not seriously dispute any of the remaining claims for extras.

A. Site Preparation

The contract to build the house states that “[a]ny unusual site problems which will cause additional cost will be added to the price quoted.” The evidence adduced at trial revealed no “unusual” problems which would require the Court to invoke this contract provision and allow additional compensation for the work done to the site. Plaintiff testified that the land had to be cleared and the brush, trees and boulders removed. Additionally, a hill had to be leveled. None of these items, however, constituted an impediment to the clearing which could be considered out of the ordinary. The contract contemplated situations whereby some feature of the land made site preparation for a prefabricated house more difficult and thereby more expensive than one would normally anticipate. Had the land been a rock bed, or an area having poor lateral support, the additional charges might be warranted. Here, they are not.

B. Drainage Field

Plaintiff contends that defendant is required to pay for the additional work done to the drainage/leaching field. The specifications set forth on the building plans5 under #13 provide for the installation of all plumbing and the plans show the septic tank details and seepage pit locations. Accordingly, there is no question that this work was contemplated under the contract. Levinson testified, however, that the defendant did not want the system shown on the plans, but was insistent that a leaching field be installed. Norman Williams, an official of the Department of Public Works, a disinterested witness, testified that when he inspected the house and septic tank he found the tank to be correct according to departmental regulations, but the pit too close to the tank. Because plaintiff obligated himself to install the pit, and did it incorrectly, he was required to [198]*198move the pit at his own expense. The increased cost of doing this work cannot be passed on to the defendant. The $320.00 claimed for the drainage field will not be allowed.

III. ANTICIPATORY BREACH

A more complex problem arises in determining what damages, if any, are appropriate for the breach of contract. Plaintiff has requested, by way of his complaint, $10,359.00, such sum representing the balance due on the contract. The original contract price was $37,200.00,6 payable in installments, each installment due upon completion of a percentage of the work, as certified by an appraiser from the bank securing the financing. The first four payments total-ling $29,760.00, were made as scheduled, the last on or about July 29, 1980. The balance then remaining on the contract was $7,440.00. The construction project was approximately 89% complete at this moment. On August 14, 1980, defendant sent Levinson a letter stating “Please be advised that I do not intend to make any more payments on the house until the following items are completed to my satisfaction . ...” (Plaintiffs Exhibit #3.) The first and second items listed deal with the manner and color of the painting job. The third item details a request for compensation for a shade tree which was removed during site preparation. Plaintiff replied to this by letter dated August 25, 1980. (Plaintiffs Exhibit #4.) At this point in time, plaintiff ceased any additional work on the house. Defendant then retained another contractor to complete the unperformed portion of the contract.

It is basic to our consideration that a valid, binding contract existed between the parties. In order to give rise to a claim for damages, a breach must have occurred. Since the statements of defendant contained in her letter of August 14, were prospective in nature, i.e., they related to her disinclination to pay for work which was either underway or about to be commenced, she may be said to have anticipatorily breached the contract. “If the promisor makes a definite statement to the promisee that he either will not or cannot perform his contract, this is a repudiation and will operate as an anticipatory breach unless the promisor had some justifying cause [199]*199for his statement.” 4 CORBIN ON CONTRACTS § 959 at 856 (1951).7

The defects of which defendant complained in her letter are not significant when the entire contract is considered as a whole. The variances, if extant at all, were either not material or readily curable. The plaintiff had “substantially performed” the 89% of the contract under the terms as agreed. See RESTATEMENT (SECOND) OF CONTRACTS § 237, comment d; § 241.8 Mary Edwards simply lacked sufficient cause to stop making the payments and did so at her own risk.

“Every breach gives rise to a claim for damages.” RESTATEMENT (SECOND) OF CONTRACTS § 236, comment a. The measure of damages for breach of contract is normally that amount which would put the plaintiff in the same position in which he would have been had the contract been performed. Dialist Co. v. Pulford, 399 A.2d 1374, 1379 (Md. Ct. Spec. App. 1979), citing to, United States v. Behan, 110 U.S. 338

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Behan
110 U.S. 338 (Supreme Court, 1884)
Guerini Stone Co. v. P. J. Carlin Construction Co.
240 U.S. 264 (Supreme Court, 1916)
Story Parchment Co. v. Paterson Parchment Paper Co.
282 U.S. 555 (Supreme Court, 1931)
Frank Sullivan Company v. Midwest Sheet Metal Works
335 F.2d 33 (Eighth Circuit, 1964)
Lee Shops, Inc. v. Schatten-Cypress Company
350 F.2d 12 (Sixth Circuit, 1965)
Huzzy v. Culbert Construction Co.
489 P.2d 749 (Court of Appeals of Washington, 1971)
Murray v. Americare-Medical Designs, Inc.
181 S.E.2d 871 (Court of Appeals of Georgia, 1971)
Crankshaw v. Stanley Homes, Inc.
207 S.E.2d 241 (Court of Appeals of Georgia, 1974)
George v. George F. Berkander, Inc.
169 A.2d 370 (Supreme Court of Rhode Island, 1961)
M & R Contractors & Builders, Inc. v. Michael
138 A.2d 350 (Court of Appeals of Maryland, 1958)
Dialist Co. v. Pulford
399 A.2d 1374 (Court of Special Appeals of Maryland, 1979)
John D. Copanos & Sons, Inc. v. McDade Rigging & Steel Erection Co.
403 A.2d 402 (Court of Special Appeals of Maryland, 1979)
Jacob & Youngs, Inc. v. Kent
129 N.E. 889 (New York Court of Appeals, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
18 V.I. 194, 1982 V.I. LEXIS 134, Counsel Stack Legal Research, https://law.counselstack.com/opinion/caribe-contracting-co-v-edwards-virginislands-1982.