John W. Goodwin, Inc. v. Fox

1999 ME 33, 725 A.2d 541, 1999 Me. LEXIS 33
CourtSupreme Judicial Court of Maine
DecidedFebruary 16, 1999
StatusPublished
Cited by11 cases

This text of 1999 ME 33 (John W. Goodwin, Inc. v. Fox) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John W. Goodwin, Inc. v. Fox, 1999 ME 33, 725 A.2d 541, 1999 Me. LEXIS 33 (Me. 1999).

Opinion

DANA, J.

[¶ 1] Edward A. Fox appeals from a judgment entered in the Superior Court (Hancock County, Marscmo, J.) in favor of John W. Goodwin, Inc., contending that Goodwin, a subcontractor, failed to join an indispensable party, the general contractor; Fox, the owner, did not consent to the costs of Goodwin’s labor and materials beyond the prices set forth in the general contract; and the court erred in calculating the judgment awarded to Goodwin. We affirm the judgment of the Superior Court.

[¶2] Fox hired R.H. Campbell, Inc. to build a house on Fox’s property in Cape Rosier. Campbell hired Goodwin as a subcontractor for concrete and masonry. Campbell submitted monthly applications for payments to William Sepe, Fox’s architect and agent, who compared the application for payment with the work performed, and after approving the application, sent it on to Fox for payment. Fox was required to make payment to Campbell within ten days and was authorized to withhold five percent of each payment as a retainage.

[¶3] Campbell paid Goodwin during the course of construction, and Goodwin provided lien waivers as it received payments. On December 12, 1990, Goodwin signed a lien waiver indicating to Campbell and Fox that it had been paid in full for all work billed through that date.

[¶4] After December 12, 1990, Goodwin submitted four invoices to Campbell for work performed thereafter. Sepe testified that, in accordance with the billing procedure set forth in the general contract, he never saw Goodwin’s invoices to Campbell. Sepe admitted, however, that Goodwin was working actively on the site from December 1990 to May 1991. Fox paid Campbell for work invoiced through March 15, 1991, but Campbell did not pay Goodwin.

[¶ 5] On May 15, 1991, Campbell walked off the job claiming that Fox. had failed to provide timely progress payments. Because Campbell walked off the job, Fox refused to pay Campbell’s last application for payment. All construction work on Fox’s house stopped. On May 17, 1991, Goodwin recorded a mechanic’s lien against Fox’s property pursuant to 10 M.R.S.A. §§ 3251-3269 (1997 & Supp.1998).

[¶ 6] Goodwin supported its demand for $38,383 with copies of invoices submitted to Campbell after December 12, 1990. The invoices are inconsistent with the applications for payment submitted by Campbell to Fox during the same period. For example, Goodwin submitted invoices totaling $37,411 to Campbell. By contrast, during this period Campbell’s application for payment to Fox listed costs of only $2,248 attributable to the concrete and masonry components of the total contract.

*543 [¶ 7] After Campbell walked off the job, Goodwin refused to complete the masonry work because Fox would not honor its claim against Campbell. Fox hired another subcontractor to finish the masonry. Fox testified that his estimate of the total cost overrun attributable to Campbell’s failure to complete the job was $200,000.

[¶ 8] Goodwin filed a complaint against Fox in September 1991. In March 1992, Goodwin moved to amend its complaint to add Campbell as a defendant. Fox opposed the motion and moved for a summary judgment because Goodwin originally failed to join Campbell as an indispensable party. The court granted Fox’s motion, and Goodwin appealed. We held that Campbell was, indeed, an indispensable party and that the court abused its discretion when it denied Goodwin’s motion to amend. See John W. Goodwin, Inc. v. Fox, 642 A.2d 1339, 1341 (Me.1994).

[¶ 9] While the case was on appeal, Goodwin brought a separate action against Campbell, obtaining a judgment for $38,383 in February 1994. The judgment remains unsatisfied because Campbell is insolvent.

[¶ 10] After this Court’s decision, Goodwin filed an amended complaint in June 1995, naming Campbell and Fox as defendants. At the time Goodwin brought the complaint. Campbell’s corporate status was suspended. In July 1995, Goodwin served Campbell with the amended complaint, but Campbell never filed an answer. 1

[¶ 11] After a bench trial in October 1997, the court concluded that Goodwin performed services and contributed materials to Fox equal to the claimed $38,383, and that Fox consented to these services and materials. In addition, the court concluded that the retainage held by Fox was the limit of Fox’s exposure to Goodwin’s lien. Fox appealed.

I. FAILURE TO JOIN AN INDISPENSABLE PARTY

[¶ 12] Fox argues that Goodwin’s original failure to join Campbell as an indispensable party may not be subsequently remedied because the suspension of Campbell’s corporate status prevents Goodwin from joining Campbell, and Goodwin is also barred by res judi-cata from bringing another claim against Campbell. We disagree.

[¶ 13] Goodwin did not fail to join Campbell. First, contrary to Fox’s contention, a suspended corporation may be sued. See DiPietro v. Boynton, 628 A.2d 1019, 1021-22 (Me.1993) (corporation’s claims not dismissed on basis of suspended corporate status when corporate powers reinstated before defendant’s motion to dismiss); see also 13-A M.R.S.A. §§ 1101, 1122 (1981) (corporation’s capacity to be sued ends two years after formal dissolution). Second, Campbell never raised the defense of res judicata, and if Fox can assert the defense on Campbell’s behalf, he failed to do so in the Superior Court. See M.R. Civ. P. 8(c) (party must set forth res judicata as an affirmative defense); Reed v. Tracy, 435 A.2d 745, 746 (Me.1981) (defense of res judicata waived when it is not raised by the pleadings). Therefore, Goodwin satisfied its obligation to join Campbell as an indispensable party by serving Campbell with the amended complaint.

II. CONSENT TO LABOR AND MATERIALS

[¶ 14] Fox argues that his consent was limited to the prices set forth in the general contract attributable to masonry and concrete. We disagree.

[¶ 15] In order for Goodwin to assert a mechanic’s lien on Fox’s property. Goodwin must either have a contract with or the consent of Fox. 10 M.R.S.A. § 3251 (Supp.1998). 2 Because Goodwin did not con *544 tract with Fox, Goodwin had to demonstrate that Fox consented to Goodwin’s labor and materials. To establish an owner’s consent, a subcontractor must prove (1) knowledge on the part of the owner of the nature and extent of the work being performed on the premises, and (2) conduct on the part of the owner justifying the expectation and belief on the part of the subcontractor that the owner had consented. See Carey v. Boulette, 158 Me. 204, 213, 182 A.2d 473, 478 (1962). The mechanic’s lien law will be “construed and applied liberally ‘to further [its] equity and efficacy, when it is clear that the lien has been honestly earned.’ ” John W. Goodwin, Inc., 642 A.2d at 1341 (quoting Twin Island Dev.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
1999 ME 33, 725 A.2d 541, 1999 Me. LEXIS 33, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-w-goodwin-inc-v-fox-me-1999.