Oak Ridge Builders, Inc. v. Howland

CourtSuperior Court of Maine
DecidedOctober 10, 2006
DocketPENcv-03-17
StatusUnpublished

This text of Oak Ridge Builders, Inc. v. Howland (Oak Ridge Builders, Inc. v. Howland) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oak Ridge Builders, Inc. v. Howland, (Me. Super. Ct. 2006).

Opinion

STATE OF MAINE DISTRICT COURT PENOBSCOT, SS. BANGOR CIVIL ACTION

Oak Ridge Builders, Inc. PlaintifflCounterclaim Defendant 1 PENOBSCOT COUNTY I Decision and Judgment DONALD 1. GARBRECHT L A W LIBRARY

OCT 1 6 2006 Todd M. Howland et al., DefendantsICounterclaim Plaintiffs

Hearing was held on the complaint and counterclaim. On each hearing date, the parties were present with counsel. Following the hearing, the parties filed written argument, which the court has considered in conjunction with the record evidence. The parties' claims arise out of a home construction contract, under which Todd M. Howland and Julie M. Howland purchased an unimproved houselot from Oak Ridge Builders, Inc. and then entered into a contract with Oak Ridge for the construction of their house. During the course of the construction project, the parties' relationship became entangled in sharp disagreement regarding their rights and obligations, and Oak Ridge did not complete construction of the house. This lawsuit followed. In early 1992, the Howlands purchased the prospective houselot from Oak Ridge. The gross purchase price for the lot was $40,000. However, the parties agreed that if the Howlands engaged Oak Ridge to build the house, they would receive a credit of $5,000. In late January 2002, the parties entered into a written home construction contract, which consisted of the principal instrument and a number of other referenced documents, such as several house designs, a list of features that would be included in the houseplan, and a schedule for disbursements that would be paid to Oak Ridge as the construction progressed. See plaintiff's exhibits 2-4,6, 8,67; defendants' exhibit 2. Oak Ridge drafted the contract instrument. The total price stated in the contract was $174,250, which included the price for the land. The court concludes that the contract was not integrated. It does not purport to constitute an integrated agreement. Further, as is demonstrated by many of the disputes generated by the evidence, its terms, when viewed within the four-corners of the instrument, were not unambiguous and sufficiently exhaustive to be seen as the definitive expression of the parties' agreement. One of the ambiguities affecting the contract is a lack of internal clarity about whether the contract price does or does not include the $5,000 credit to which the Howlands were entitled because they chose Oak Ridge as the contractor. The contract refers to the price as "[tlhe total contract price, which includes the real estate lot, equipment, materials and labor. . . ." The price of the real estate was subject to a $5,000 adjustment, and the time when the Howlands would receive that credit is not made specific. Although Oak Ridge's principal, Frank Pawlendzio, testified that he took that credit into account when he calculated the "total contract price" of $174,250, the better objective evidence is that as of the time Oak Ridge stopped working on the construction project in September 2002, it still had not given the Howlands that credit against the amount they owed. That evidence is found in a note that Pawlendzio wrote on a copy of the disbursement schedule after work had stopped, where he indicated that of the payments that the Howlands had made to Oak Ridge, $40,000 was attributable to the land purchase. See plaintiff's exhibit 35. If, as Pawlendzio contends, the Howlands already had received that credit, then the figure that Pawlendzio wrote on that document would have been $35,000. Oak Ridge and the Howlands also became parties to a three-way contract with Bangor Savings Bank, which provided the construction money for the project. See plaintiff's exhibit 7. As part of that contractual agreement, Oak Ridge agreed to keep the property and structures free of any mechanic's liens or claims. The construction work began in April, when earthwork was performed and the foundation poured.' By mid-July, Oak Ridge requested the first disbursement that would be triggered by construction progress. It sought and, on July 24, received payment of $41,825. This payment covered all items associated with the first draw under the

1 Oak Ridge itself actually did not perform any of the construction work. Rather, its role was to provide that work entirely through subcontractors. disbursement schedule, as well as some - but not all - items that would have been the basis for the second draw amount. Under the arrangement among Oak Ridge, the Howlands and the bank, the bank was authorized to disburse money to Oak Ridge only with the approval and consent of the H o ~ l a n d s . ~ During the month of August, disagreements between Oak Ridge and the Howlands, which had started to appear in July, escalated. One of the problems that arose related to the roof trusses that Oak Ridge installed. Oak Ridge placed the trusses 24 inches on center (OC). The Howlands complained that they should be placed closer together (16 inches OC) to provide proper support for loads such as snow. This, however, was not part of the contract, and the evidence establishes that with adequately sturdy roof sheathing (namely, 518" plywood sheathing, instead of M" sheathing that would be used if the trusses were placed closer together), Oak Ridge's installation of the trusses was sufficient. See plaintiff's exhibit 26. Nonetheless, the parties' disagreement about the roof system was symptomatic of a relationship that was becoming more difficult. By letter dated August 26, the Howlands presented Pawlendzio with an "action plan," under which they wanted Oak Ridge to complete certain aspects of the house construction, even though that work was out of the sequence set out in the disbursement schedule, because they were concerned about the change in seasons. See plaintiff's exhibit 21. In that letter, the Howlands wrote that they would not authorize the bank to pay Oak Ridge the third draw under the disbursement schedule if Oak Ridge did not finish the items of work they specified in the letter, "even if it means waiting until spring when weather conditions permit optimum conditions for seeding the lawn," which was one of the jobs the Howlands listed in their letter. (Oak Ridge had sought and been paid

2 It does not appear that the express terms of the construction loan agreement or the home construction contract required the Howlands to approve any disbursement made by the bank to Oak Ridge. However, the parties engaged in a practice under which the bank would not make such payments in the absence of the Howlands' consent. In fact, the relationship between Oak Ridge and the Howlands collapsed in September when, at least at one point, the Howlands advised Oak Ridge that they would not authorize the bank to pay Oak Ridge any money, despite the pendency of Oak Ridge's payment request, until it satisfied certain demands. The loan officer testified that the bank was otherwise prepared to release funds to Oak Ridge. only one draw. However, based on the groups of tasks listed in the disbursement schedule, Oak Ridge's second progress schedule would encompass some of the work that would constitute the predicate for the third draw as identified in that schedule.) Promptly after receiving the letter, Pawlendzio wrote back to the Howlands, advising that Oak Ridge would try to accommodate their directions but also pointed out that the next disbursement due to it was not conditioned on completing work that would be the basis for a subsequent draw. See plaintiff's exhibit 22. In fact, on or just prior to September 7, Oak Ridge made a written request for payment of $28,125. Although the request itself it not included in the trial record, the basis for the amount of that request is set out in a document that Pawlendzio created later in the month. See plaintiff's exhibit 35.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Associated Builders, Inc. v. Coggins
1999 ME 12 (Supreme Judicial Court of Maine, 1999)
John W. Goodwin, Inc. v. Fox
1999 ME 33 (Supreme Judicial Court of Maine, 1999)
Jenkins, Inc. v. Walsh Bros., Inc.
2001 ME 98 (Supreme Judicial Court of Maine, 2001)
Advanced Construction Corp. v. Pilecki
2006 ME 84 (Supreme Judicial Court of Maine, 2006)
Suminski v. Maine Appliance Warehouse, Inc.
602 A.2d 1173 (Supreme Judicial Court of Maine, 1992)
Colquhoun v. Webber
684 A.2d 405 (Supreme Judicial Court of Maine, 1996)
Down East Energy Corp. v. RMR, INC.
1997 ME 148 (Supreme Judicial Court of Maine, 1997)
William Mushero, Inc. v. Hull
667 A.2d 853 (Supreme Judicial Court of Maine, 1995)
Deering Ice Cream Corp. v. Colombo, Inc.
598 A.2d 454 (Supreme Judicial Court of Maine, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Oak Ridge Builders, Inc. v. Howland, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oak-ridge-builders-inc-v-howland-mesuperct-2006.