Parker-Danner Co. v. Nickerson

554 A.2d 1193, 1989 Me. LEXIS 53
CourtSupreme Judicial Court of Maine
DecidedMarch 14, 1989
StatusPublished
Cited by9 cases

This text of 554 A.2d 1193 (Parker-Danner Co. v. Nickerson) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parker-Danner Co. v. Nickerson, 554 A.2d 1193, 1989 Me. LEXIS 53 (Me. 1989).

Opinion

CLIFFORD, Justice.

Defendants Malcolm A. Sibulkin and Lauri, Inc. 1 (Sibulkin) appeal from a judgment of the Superior Court (Franklin County; Bradford, J.) in favor of plaintiff Parker-Danner Company (Parker-Danner). The court awarded Parker-Danner $6,766.22, plus interest and costs, in its lien claim against Sibulkin. for construction equipment and supplies rented by Parker-Danner to defendants James Nickerson and Nickerson Associates, Inc. (Nickerson) and used by Nickerson, a contractor, to help construct a dam and pumphouse on Sibul-kin’s property in Avon. Finding no error, we affirm the judgment.

Sibulkin contracted with Nickerson, as the general contractor, to construct a con *1194 Crete dam and pumphouse in Avon at the site of the Sibulkin toy factory. The contract provided that Sibulkin would reimburse Nickerson for the cost of the work, including “[rjental charges of all necessary machinery and equipment” and that “[mjaterials for the project should be ordered by the Contractor but shall be invoiced to and paid for by the Owner.” The contract also provided that the architect was Sibulkin’s representative during construction.

Parker-Danner, alleging that it supplied rental equipment to Nickerson for use at the job site in the construction of the dam, for which it was not paid, filed a Mechanic’s Lien Complaint 2 in Superior Court against the defendants. 3 The court awarded damages to Parker-Danner, 4 finding that the equipment, a portable air compressor, rock drill and water pump, were supplied by Parker-Danner to Nickerson and used in the construction of the dam, that Parker-Danner had not been paid its fair and reasonable rental charge, and that Si-bulkin consented to the use of the rental equipment on the construction project.

I.

Parker-Danner’s lien claim was brought under 10 M.R.S.A. § 3251 (1980). That section provides in pertinent part as follows:

Whoever ... furnishes ... materials, including repair parts of machines used, or performs services either as ... an owner-renter, owner-lessor, or owner-supplier of equipment used in erecting, altering ... or repairing a ... building or appurtenances ... including the clearing, grading, draining, excavating or landscaping of the ground adjacent to and upon which any such above-named objects are constructed, by virtue of a contract with or by consent of the owner, has a lien thereon and on the land on which it stands and on any interest such owner has in the same, to secure pay-' ment thereof, with costs....

In order for Parker-Danner to prevail, it thus had to convince the court that Sibul-kin, as owner of the dam, consented to the use of the rental equipment.

Contrary to Sibulkin’s contention that the court impermissibly inferred consent on the part of Sibulkin solely by virtue of the terms of the contract authorizing Nicker-son to rent equipment and providing for Sibulkin to pay those rental charges, 5 the court’s determination that Sibulkin consented to the use of the rental equipment was actually based on Sibulkin’s imputed knowledge of that use. The contract provided, and Sibulkin in his testimony admitted, that Sibulkin’s architect was his agent for purposes of the construction project. The court specifically found that the architect had actual knowledge of the requirement for and the use of the rental equipment at the dam site, a finding supported in the record. The court correctly imputed the architect’s knowledge to Sibulkin. Restatement (Second) of Agency § 268(l)(c) (1958). In view of that imputed knowledge, the court’s conclusion that Sibulkin, who never objected to the use of rental equipment, consented to its use, was not clearly *1195 erroneous. Shaw v. Young, 87 Me. 271, 276, 32 A. 897 (1895).

II.

The trial of this case lasted one-half day. Sibulkin’s case consisted of the testimony of Sibulkin, which ended at noon on the day of the trial. Sibulkin requested permission to call his architect, identified as Rick Has-kell, who was unavailable until the next day. Haskell had not been listed as a witness in the Report of Conference of Counsel filed with the court, and Sibulkin had not notified the other parties until two days prior to trial that Haskell was a potential witness. The court sustained the objections of Parker-Danner and Nickerson to Haskell being allowed to testify.

The pretrial order in this case permitted additional previously unlisted witnesses to be called only after court approval, providing for their exclusion for lack of notice upon a showing of prejudice. In excluding the testimony of Haskell, the court erroneously relied on a three-day notice requirement for adding witnesses under M.R. Civ.P. 16(a)(3)(N), a rule no longer effective at the time of trial, and, in any event, not applicable to this case, which was subject to its own pretrial order. Sibulkin argues on appeal that the judgment should be vacated because Haskell’s testimony was crucial to his case, would have been admissible under the terms of the pretrial order in the case and was impermissibly excluded following an application of the wrong rule. In addition, he argues that Haskell’s testimony was admissible as impeachment or rebuttal evidence.

Sibulkin has not preserved the error he raises now on appeal. At trial Sibulkin did not direct the court’s attention to the pretrial order in the case nor did he point out the inapplicability of M.R.CÍV.P. 16(a)(3)(N). The court was not given the opportunity to consider the admissibility of Haskell’s testimony under the pretrial order, the proper standard that should have been applied. Mattson v. Mattson, 376 A.2d 473, 477 (Me.1977); Moulton v. Perkins, 116 Me. 218, 222, 100 A. 1020 (1917).

Moreover, Sibulkin did not make an offer of proof as to Haskell’s expected testimony. It is thus impossible on appeal to properly assess Sibulkin’s claims that Parker-Danner would not have been prejudiced by the short notice and that the testimony would have been admissible under the pretrial order, or that the testimony was in the nature of impeachment or rebuttal evidence. M.R.Evid. 103(a)(2) precludes appeals based on a ruling excluding evidence unless a substantial right is affected and “the substance of the evidence was made known to the court by offer or was apparent from the context within which questions were asked.” By the failure to direct the court’s attention to its reliance on the wrong rule in excluding the testimony of Haskell, and by not making an offer of proof as to the nature of that testimony, Sibulkin has not properly preserved for appeal any error the court may have made in its exclusion.

III.

Sibulkin’s final assertion is based on the court’s denial of his motion for a new trial. At trial, Nickerson testified that the rental equipment was kept and used regularly at the job site during nearly the entire contract period.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gelband v. Hilton
Maine Superior, 2011
F.R. Carroll, Inc. v. TD Bank, N.A.
2010 ME 115 (Supreme Judicial Court of Maine, 2010)
Bean v. Cummings
2008 ME 18 (Supreme Judicial Court of Maine, 2008)
John W. Goodwin, Inc. v. Fox
1999 ME 33 (Supreme Judicial Court of Maine, 1999)
Eastman v. Eastman-Veres
1997 ME 26 (Supreme Judicial Court of Maine, 1997)
Mondello v. General Electric Co.
650 A.2d 941 (Supreme Judicial Court of Maine, 1994)
Pooler v. Clifford
639 A.2d 1061 (Supreme Judicial Court of Maine, 1994)
Wellstone Partners v. J & M Construction Co.
581 A.2d 789 (Supreme Judicial Court of Maine, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
554 A.2d 1193, 1989 Me. LEXIS 53, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parker-danner-co-v-nickerson-me-1989.