Bill Whorff, Inc. v. Breakwater Design & Build, Inc.
This text of Bill Whorff, Inc. v. Breakwater Design & Build, Inc. (Bill Whorff, Inc. v. Breakwater Design & Build, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
STATE OF MAINE SUPERIOR COURT . CUMBERLAND, ss. - '-'-" . CIVIL ACTION / DOCKET NO: RE-07-090/ ;}: 0 J RE-07- 0 9 1 : \. /2: Ar·_C/.lM ''-J . . ,v,/I i _3!PI-I/c)I)Oi; : BILL WHaRFF, INC.,
Plaintiff, ORDER v.
BREAKWATER DESIGN & BUILD, INC.
Defendant,
And
ATLAS ENTERPRISES, LLC,
Defendant.
This case comes before the Court on Plaintiff Bill Whorff, Inc.'s Motion for
Summary Judgment pursuant to M.R. Civ. P. 56(c) and Defendant Atlas Enterprise,
LLC's Motion to Strike.
PROCEDURAL AND FACTUAL BACKGROUND The dispute in this case arises from the design and construction of Sunset
Terrace Subdivision, Boothbay Harbor Maine (the "Project"). Defendant Atlas
Enterprise LLC (Atlas) is the owner of the property. Defendant Breakwater
Design & Build, Inc. (Breakwater) was the general contractor on the Project and
Plaintiff Bill Wharff, Inc. (Wharff) was the subcontractor on the Project.
Beginning in May 2005, Atlas and Breakwater entered into two contracts
for the design and creation of the infrastructure of the Subdivision. The first
contract, entered into on May 11, 2005 was for the design of the subdivision. The second contract, entered into in October 2005, was for the building of the
infrastructure of the Subdivision.
On October 10, 2005, Breakwater and Whorff entered into several
subcontractor contracts for the construction of the Subdivision infrastructure.
Under the terms of that contract, Whorff was to provide monthly invoices for
services rendered. Payments were timely made until April 30, 2006. Whorff last
provided labor, services and materials for the Project on July 31, 2006.
On September 18, 2006, Whorff recorded a Notice of Mechanics' Lien
Claim in Lincoln County Registry of Deeds in Book 3739, Page 226 in order to
preserve a statutory mechanics' lien on the Property pursuant to 10 M.R.S.A §
3251.
Whorff alleges that Breakwater and Atlas owe unpaid invoices totaling
$105,400.00. Breakwater concedes that it has failed to pay Whorff's invoices and
concurs in the amounts due, contingent upon completion of the Project.
Breakwater defends its failure to pay Whorff asserting that Whorff has not
completed its obligations under the contracts and further that Breakwater is not
obligated to pay Whorff until Atlas has honored its contract with Breakwater by
paying on submitted invoices. Atlas, in turn defends by asserting that 1) it has
paid Breakwater for the amounts owed to Whorff under the subcontracts, and 2)
Breakwater misrepresented the cost of the Project and failed to adequately
research the actual cost. Based on this failure to research, Atlas asserts,
Breakwater has billed an excessive and unconsented-to amount under that
contract.
2 DISCUSSION
I. Standard of Review
Summary judgment is proper where there exist no genuine issues of
material fact such that the moving party is entitled to judgment as a matter of
law. M.R. Civ. P. 56(c); see also Levine v. R.B.K. Caly Corp., 2001 ME 77, A.2d 653, 655. A genuine issue is raised "when sufficient evidence requires a fact-finder to choose between competing versions of the truth at trial." Parrish v. Wright, 2003 :rvrn 90, potential to affect the outcome of the suit." Burdzel v. Sobus, 2000 ME 84, A.2d 573, 575. "A court may properly enter judgment in a case when the parties are not in dispute over the [material] facts, but differ only as to the legal conclusion to be drawn from these facts." Tondreau v. Sherwin-Williams Co., 638 A.2d 728,730 (Me. 1994). "If material facts are disputed, the dispute must be resolved through fact finding." Curtis v. Porter, 2001 ME 158, they must be resolved in favor of the non-moving party. Beaulieu v. The Aube Corp., 2002 ME 79, summary judgment is no longer an extreme remedy, it is not a substitute for trial." Arrow Fastener co. v. Wrabacon, Inc., 2007 ME 34,1 18, 917 a.2d 123, 127 (citing Curtis, 2001 ME 158,17,784 A.2d at 21-22). Whorff timely filed a mechanics' lien against the subject property on September 18, 2006 and now seeks enforcement of that lien. Mechanics' liens are available to "[w ]hoever performs labor or furnishes labor or materials ... used in 3 erecting, altering, moving or repairing a house, building or appurtenances ... by virtue of a contract with or by consent of the owner" in order "to secure payment thereof." 10 M.R.S. § 3251 (2007). "A lien is given upon the ground that the work has been a benefit to the realty, and has enhanced its value." Combustion Engineering, Inc. v. Miller Hydro Group, 577 A.2d 1186, 1188 (Me. 1990) (quoting Bangor Roofing & Sheet Metal Co. v. Robbins Plumbing Co., Inc., 151 Me. 145, 148, 116 A.2d 664,666 (1955)). a. Consent to Labor and Materials In order for a subcontractor to assert a mechanics' lien against a property where no contract exists between the owner and the subcontractor, the "subcontractor must prove (1) knowledge on the part of the owner of the nature and extent of the work being performed on the premises, and (2) conduct on the part of the owner justifying the expectation and belief on the part of the subcontractor that the owner consented." John W. Goodwin, Inc. v. Fox, 1999 ME 33, <]I IS, 725 A.2d 541, 543-44. In this case, it is undisputed that no contract exists between Whorff and Atlas and thus Whorff must prove that Atlas had knowledge of the nature and extent of the work being done and displayed conduct conveying consent. Whether or not Atlas consented to the scope of the work being done is a genuine issue of material fact in dispute. Atlas asserts that the scope and cost of the work exceeded that agreed to in its contract with Breakwater. Moreover, Atlas asserts that it sought information regarding the scope of the Project, but that the information was not provided to them until discovery. Accordingly summary judgment should be denied to Whorff on Count 1. 4 III. Breach of Contract Whorff brings a breach of contract claim against Breakwater for its failure to pay on the invoices under the October 2005 contracts. A material breach of contract occurs when a party to a contract fails to perform a "duty so material and important [to the contract] as to justify the injured party in regarding the whole transaction as at an end." Jenkins, Inc. v. Walsh Brothers, Inc., 2001 ME 98, 1 13, 776 A.2d 1229, 1234. Breakwater asserts that it is not in breach because no monies are due until Whorff has satisfied its obligations under the contract, which Breakwater asserts, Whorff has not yet done. Whorff counters that billing is monthly under the contract and that, accordingly, Breakwater has breached the contract for failing to pay the monthly invoices. Alternatively, BreakwaterII. Mechanics' Liens
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Bill Whorff, Inc. v. Breakwater Design & Build, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/bill-whorff-inc-v-breakwater-design-build-inc-mesuperct-2008.