Bill Whorff, Inc. v. Breakwater Design & Build, Inc.

CourtSuperior Court of Maine
DecidedMarch 24, 2008
DocketCUMre-07-090and091
StatusUnpublished

This text of Bill Whorff, Inc. v. Breakwater Design & Build, Inc. (Bill Whorff, Inc. v. Breakwater Design & Build, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bill Whorff, Inc. v. Breakwater Design & Build, Inc., (Me. Super. Ct. 2008).

Opinion

STATE OF MAINE SUPERIOR COURT . CUMBERLAND, ss. - '-'-" . CIVIL ACTION / DOCKET NO: RE-07-090/ ;}: 0 J RE-07- 0 9 1 : \. /2: Ar·_C/.lM ''-J . . ,v,/I i _3!PI-I/c)I)Oi; : BILL WHaRFF, INC.,

Plaintiff, ORDER v.

BREAKWATER DESIGN & BUILD, INC.

Defendant,

And

ATLAS ENTERPRISES, LLC,

Defendant.

This case comes before the Court on Plaintiff Bill Whorff, Inc.'s Motion for

Summary Judgment pursuant to M.R. Civ. P. 56(c) and Defendant Atlas Enterprise,

LLC's Motion to Strike.

PROCEDURAL AND FACTUAL BACKGROUND The dispute in this case arises from the design and construction of Sunset

Terrace Subdivision, Boothbay Harbor Maine (the "Project"). Defendant Atlas

Enterprise LLC (Atlas) is the owner of the property. Defendant Breakwater

Design & Build, Inc. (Breakwater) was the general contractor on the Project and

Plaintiff Bill Wharff, Inc. (Wharff) was the subcontractor on the Project.

Beginning in May 2005, Atlas and Breakwater entered into two contracts

for the design and creation of the infrastructure of the Subdivision. The first

contract, entered into on May 11, 2005 was for the design of the subdivision. The second contract, entered into in October 2005, was for the building of the

infrastructure of the Subdivision.

On October 10, 2005, Breakwater and Whorff entered into several

subcontractor contracts for the construction of the Subdivision infrastructure.

Under the terms of that contract, Whorff was to provide monthly invoices for

services rendered. Payments were timely made until April 30, 2006. Whorff last

provided labor, services and materials for the Project on July 31, 2006.

On September 18, 2006, Whorff recorded a Notice of Mechanics' Lien

Claim in Lincoln County Registry of Deeds in Book 3739, Page 226 in order to

preserve a statutory mechanics' lien on the Property pursuant to 10 M.R.S.A §

3251.

Whorff alleges that Breakwater and Atlas owe unpaid invoices totaling

$105,400.00. Breakwater concedes that it has failed to pay Whorff's invoices and

concurs in the amounts due, contingent upon completion of the Project.

Breakwater defends its failure to pay Whorff asserting that Whorff has not

completed its obligations under the contracts and further that Breakwater is not

obligated to pay Whorff until Atlas has honored its contract with Breakwater by

paying on submitted invoices. Atlas, in turn defends by asserting that 1) it has

paid Breakwater for the amounts owed to Whorff under the subcontracts, and 2)

Breakwater misrepresented the cost of the Project and failed to adequately

research the actual cost. Based on this failure to research, Atlas asserts,

Breakwater has billed an excessive and unconsented-to amount under that

contract.

2 DISCUSSION

I. Standard of Review

Summary judgment is proper where there exist no genuine issues of

material fact such that the moving party is entitled to judgment as a matter of

law. M.R. Civ. P. 56(c); see also Levine v. R.B.K. Caly Corp., 2001 ME 77,

A.2d 653, 655. A genuine issue is raised "when sufficient evidence requires a

fact-finder to choose between competing versions of the truth at trial." Parrish v.

Wright, 2003 :rvrn 90,

potential to affect the outcome of the suit." Burdzel v. Sobus, 2000 ME 84,

A.2d 573, 575.

"A court may properly enter judgment in a case when the parties are not

in dispute over the [material] facts, but differ only as to the legal conclusion to be

drawn from these facts." Tondreau v. Sherwin-Williams Co., 638 A.2d 728,730 (Me.

1994). "If material facts are disputed, the dispute must be resolved through fact­

finding." Curtis v. Porter, 2001 ME 158,

they must be resolved in favor of the non-moving party. Beaulieu v. The Aube

Corp., 2002 ME 79,

summary judgment is no longer an extreme remedy, it is not a substitute for trial." Arrow

Fastener co. v. Wrabacon, Inc., 2007 ME 34,1 18, 917 a.2d 123, 127 (citing Curtis, 2001

ME 158,17,784 A.2d at 21-22).

II. Mechanics' Liens

Whorff timely filed a mechanics' lien against the subject property on

September 18, 2006 and now seeks enforcement of that lien. Mechanics' liens are

available to "[w ]hoever performs labor or furnishes labor or materials ... used in

3 erecting, altering, moving or repairing a house, building or appurtenances ... by

virtue of a contract with or by consent of the owner" in order "to secure payment

thereof." 10 M.R.S. § 3251 (2007). "A lien is given upon the ground that the

work has been a benefit to the realty, and has enhanced its value." Combustion

Engineering, Inc. v. Miller Hydro Group, 577 A.2d 1186, 1188 (Me. 1990) (quoting

Bangor Roofing & Sheet Metal Co. v. Robbins Plumbing Co., Inc., 151 Me. 145, 148,

116 A.2d 664,666 (1955)).

a. Consent to Labor and Materials

In order for a subcontractor to assert a mechanics' lien against a property

where no contract exists between the owner and the subcontractor, the

"subcontractor must prove (1) knowledge on the part of the owner of the nature

and extent of the work being performed on the premises, and (2) conduct on the

part of the owner justifying the expectation and belief on the part of the

subcontractor that the owner consented." John W. Goodwin, Inc. v. Fox, 1999 ME

33, <]I IS, 725 A.2d 541, 543-44.

In this case, it is undisputed that no contract exists between Whorff and

Atlas and thus Whorff must prove that Atlas had knowledge of the nature and

extent of the work being done and displayed conduct conveying consent.

Whether or not Atlas consented to the scope of the work being done is a genuine

issue of material fact in dispute. Atlas asserts that the scope and cost of the work

exceeded that agreed to in its contract with Breakwater. Moreover, Atlas asserts

that it sought information regarding the scope of the Project, but that the

information was not provided to them until discovery. Accordingly summary

judgment should be denied to Whorff on Count 1.

4 III. Breach of Contract

Whorff brings a breach of contract claim against Breakwater for its failure

to pay on the invoices under the October 2005 contracts. A material breach of

contract occurs when a party to a contract fails to perform a "duty so material

and important [to the contract] as to justify the injured party in regarding the

whole transaction as at an end." Jenkins, Inc. v. Walsh Brothers, Inc., 2001 ME 98, 1

13, 776 A.2d 1229, 1234. Breakwater asserts that it is not in breach because no

monies are due until Whorff has satisfied its obligations under the contract,

which Breakwater asserts, Whorff has not yet done. Whorff counters that billing

is monthly under the contract and that, accordingly, Breakwater has breached

the contract for failing to pay the monthly invoices. Alternatively, Breakwater

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John W. Goodwin, Inc. v. Fox
1999 ME 33 (Supreme Judicial Court of Maine, 1999)
Maine Eye Care Associates P.A. v. Gorman
2006 ME 15 (Supreme Judicial Court of Maine, 2006)
Gagne v. Stevens
1997 ME 88 (Supreme Judicial Court of Maine, 1997)
Tucci v. City of Biddeford
2005 ME 7 (Supreme Judicial Court of Maine, 2005)
Burdzel v. Sobus
2000 ME 84 (Supreme Judicial Court of Maine, 2000)
Jenkins, Inc. v. Walsh Bros., Inc.
2001 ME 98 (Supreme Judicial Court of Maine, 2001)
Tondreau v. Sherwin-Williams Co.
638 A.2d 728 (Supreme Judicial Court of Maine, 1994)
Combustion Engineering, Inc. v. Miller Hydro Group
577 A.2d 1186 (Supreme Judicial Court of Maine, 1990)
Parrish v. Wright
2003 ME 90 (Supreme Judicial Court of Maine, 2003)
Paffhausen v. Balano
1998 ME 47 (Supreme Judicial Court of Maine, 1998)
Beaulieu v. the Aube Corp.
2002 ME 79 (Supreme Judicial Court of Maine, 2002)
Bangor Roofing & Sheet Metal Co. v. Robbins Plumbing Co.
116 A.2d 664 (Supreme Judicial Court of Maine, 1955)
Curtis v. Porter
2001 ME 158 (Supreme Judicial Court of Maine, 2001)
Portland Valve, Inc. v. Rockwood Systems Corp.
460 A.2d 1383 (Supreme Judicial Court of Maine, 1983)
Levine v. R.B.K. Caly Corp.
2001 ME 77 (Supreme Judicial Court of Maine, 2001)
Arrow Fastener Co., Inc. v. Wrabacon, Inc.
2007 ME 34 (Supreme Judicial Court of Maine, 2007)
Cummings v. Bean
2004 ME 93 (Supreme Judicial Court of Maine, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
Bill Whorff, Inc. v. Breakwater Design & Build, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/bill-whorff-inc-v-breakwater-design-build-inc-mesuperct-2008.