Summit Construction Co. v. Yeager Garden Acres, Inc.

470 P.2d 870, 28 Colo. App. 110, 1970 Colo. App. LEXIS 681
CourtColorado Court of Appeals
DecidedMarch 17, 1970
Docket70-009. (Supreme Court No. 22402.)
StatusPublished
Cited by13 cases

This text of 470 P.2d 870 (Summit Construction Co. v. Yeager Garden Acres, Inc.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Summit Construction Co. v. Yeager Garden Acres, Inc., 470 P.2d 870, 28 Colo. App. 110, 1970 Colo. App. LEXIS 681 (Colo. Ct. App. 1970).

Opinion

470 P.2d 870 (1970)

SUMMIT CONSTRUCTION COMPANY and St. Paul Fire and Marine Insurance Company, Plaintiffs in Error,
v.
YEAGER GARDEN ACRES, INC., Defendant in Error.

No. 70-009. (Supreme Court No. 22402.)

Colorado Court of Appeals, Div. I.

March 17, 1970.
Rehearing Denied April 2, 1970.
Certiorari Denied June 11, 1970.

*871 Weller, Friedrich & Hickisch, H. Gayle Weller, John R. Hickisch, Denver, for plaintiffs in error.

Harden & Wyatt, Ralph B. Harden, Fort Collins, for defendant in error.

Selected for Official Publication.

SILVERSTEIN, Chief Judge.

This case was originally filed in the Supreme Court of the State of Colorado and subsequently transferred to the Court of Appeals under authority vested in the Supreme Court.

This is an action for damages for breach of contract, brought by defendant in error, hereinafter called plaintiff or Yeager, Inc., against plaintiffs in error, hereinafter called defendants or Summit and St. Paul Ins. Co.

The contractual agreement between Yeager, Inc. and Summit consists of three documents; a contract for the construction of a shopping center, dated November 2, *872 1961 (Exhibit A); an addendum thereto (Exhibit C), undated, but stating, "—this shall be a full and complete understanding as of June 18, 1962;" and an agreement (Exhibit G) dated October 3, 1962.

Exhibit A is a contract for the construction of a shopping center by Summit, as principal contractor, for Yeager, Inc. on land owned by Yeager, Inc. The contract is a Standard Form of Agreement issued by The American Institute of Architects and provides, inter alia, that the building would be built according to drawings and specifications prepared by C. Clay Davis, an architect employed by Summit, and that plans and specifications of W. T. Grant Co. and National Tea Co. (tenants in the building) shall be part of the contract.

As the construction progressed numerous differences arose between the parties and Exhibit C was executed. It states that the parties, "—desire to settle any and all claims, counter claims, adjustments, charges and work orders to this date." (June 18, 1962) The contract then sets forth several specific changes to the original contract after stating, "—such amendments being made without prejudice to or in any way affecting the bond and contract of November 2, 1961." Exhibit C further provides, "That the Contractor shall proceed to complete the building in accordance with plans and specifications as stated in the contract of November 2, 1961, said plans as amended by the plans dated June 18, 1962, and signed by the parties hereto —."

The project was substantially completed by October 3, 1962, at which time there still remained disputes between the parties. The parties again desiring "to settle and determine all outstanding disputes," executed Exhibit G whereby Yeager, Inc. agreed to pay an agreed sum to Summit and Summit agreed to perform various specified acts and stated, "That the Contractor does hereby represent and warrant to the Owner that the project has been completed in accordance with the plans and specifications approved by W. T. Grant Company and Miller Super Markets (National Tea Co.), —." The agreement then states, "[E]ach of the parties does hereby, irrevocably, release the other, of and from all claims, demands and damages of every kind and character except for the specific undertakings herein made the obligation of the Contractor."

St. Paul Ins. Co. executed a contract bond (Exhibit B) on the project. Its only defense to the action is that it is released from liability to the extent that the principal, Summit, may have been released by the execution of Exhibits C and G. This is correct. If the principal is released by the obligee so is its surety. 50 Am.Jur. 987 (Suretyship § 126)

Two basic issues are raised by Summit:

1. The execution of Exhibits C and G settled all disputes then existing between the parties and released Summit from all liability from all deficiencies (if any) then existing and known to Yeager, Inc., including those alleged in the complaint.

2. Even if Summit was not released, the project was completed in compliance with the terms of the contract.

In addition both parties assert that the trial court erred in its assessment of damages.

As to the first issue, we agree with the findings of the trial court and hold that the execution of Exhibits C and G did not release Summit (or its surety, St. Paul Ins. Co.) from its obligation to complete the project in accordance with the plans and specifications as provided in the contract. The problem as to which plans and specifications controlled will be discussed later.

Exhibit C sets forth many specific items of dispute and claims of both parties. One of the claims of Yeager, Inc. was, "—for failure to complete in accordance with the plans and specifications in the amount of Three Thousand Dollars ($3000.00)—." As stated above by this addendum, the Contractor agreed to complete the building according to the plans signed by Yeager, *873 Inc. It is undisputed that the job was not completed when Exhibit C was signed and the obligation to complete remained with Summit.

Exhibit G was executed after the project was purportedly completed. In this agreement Summit agreed to perform certain acts, warranted the completion of the project as above set forth and was paid $84,000.00 by the owner, Yeager, Inc. Summit now asserts that it is not liable on its warranty because other covenants in the same agreement release it and because Yeager, Inc. knew or should have known that the representation of warranty was not true when made.

Neither of these claims has merit. In order to settle the dispute each party agreed to perform certain acts and undertook obligations. One of the obligations of Summit was the warranty of completion. The release which has been quoted above specifically excepts the undertakings of the Contractor, including the warranty. The construction asserted by Summit would render the warranty meaningless and surplusage. Written instruments must be construed, if possible, to give effect to all of their provisions. Century Refining Co. v. Hall, 10 Cir., 316 F.2d 15, Grimes v. Barndollar, 58 Colo. 421, 148 P. 256.

The evidence discloses that the full extent of the asserted deviations from the plans and specifications was not discovered until after Exhibit G was signed. This was exactly the possibility that Yeager, Inc. desired to protect itself against in requiring the warranty. Although some cases hold that an express warranty does not survive acceptance with knowledge of defects, Harrist v. Spencer-Harris Tool Co., 244 Miss. 84, 140 So.2d 558, the more recent cases hold that a, "seller may bind himself against patent defects, if the warranty is so worded." Zachry v. McKown, Tex.Civ.App., 326 S.W.2d 227, Williston on Contracts, 3rd Edition, § 972, Vol. 8, P. 497.

Since Summit was not released the next question to be determined is whether or not Summit breached the contract by failing to complete the project in accordance with the plans and specifications. A careful reading of the pertinent exhibits establishes that the plans and specifications which control are those prepared by C. Clay Davis and approved by W. T. Grant Co. and Miller Super Markets (National Tea Co.).

At the trial seven sets of specifications and ten sets of plans were admitted in evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Heritage Village Owners Ass'n v. Golden Heritage Investors, Ltd.
89 P.3d 513 (Colorado Court of Appeals, 2004)
Sanford v. Kobey Bros. Construction Corp.
689 P.2d 724 (Colorado Court of Appeals, 1984)
Eastlake Construction Co. v. Hess
686 P.2d 465 (Washington Supreme Court, 1984)
Worthen Bank & Trust Co., National Ass'n v. Silvercool Service Co.
687 P.2d 464 (Colorado Court of Appeals, 1984)
Olson Plumbing & Heating, Inc. v. Douglas Jardine, Inc.
626 P.2d 750 (Colorado Court of Appeals, 1981)
Kniffin v. Colorado Western Development Co.
622 P.2d 586 (Colorado Court of Appeals, 1980)
BA MTG. CO., INC. v. Unisal Development, Inc.
469 F. Supp. 1258 (D. Colorado, 1979)
Crnkovich v. Scaletta
277 N.W.2d 416 (Nebraska Supreme Court, 1979)
Duncan v. Schuster-Graham Homes, Inc.
578 P.2d 637 (Supreme Court of Colorado, 1978)
Yeager Garden Acres, Inc. v. Summit Const. Co.
513 P.2d 458 (Colorado Court of Appeals, 1973)
Godwin-Bevers Co., Inc. v. GP Enterprises, Inc.
502 P.2d 1124 (Colorado Court of Appeals, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
470 P.2d 870, 28 Colo. App. 110, 1970 Colo. App. LEXIS 681, Counsel Stack Legal Research, https://law.counselstack.com/opinion/summit-construction-co-v-yeager-garden-acres-inc-coloctapp-1970.