Conway Constr. Co. v. City of Puyallup

490 P.3d 221, 197 Wash. 2d 825
Washington Supreme Court·Decided July 8, 2021·No. 98753-0·Published·Cited by 6 cases

Opinion

FILE THIS OPINION WAS FILED IN CLERK’S OFFICE FOR RECORD AT 8 A.M. ON SUPREME COURT, STATE OF WASHINGTON JULY 8, 2021 JULY 8, 2021 ERIN L. LENNON SUPREME COURT CLERK

IN THE SUPREME COURT OF THE STATE OF WASHINGTON

) CONWAY CONSTRUCTION ) COMPANY, ) ) Petitioner / Cross-Respondent, ) No. 98753-0 ) v. ) ) En Banc CITY OF PUYALLUP, ) ) Respondent / Cross-Petitioner. ) Filed: July 8, 2021 _______________________________)

GONZÁLEZ, C.J.—The city of Puyallup (City) hired Conway Construction

Company to build a road. The contract between the two allowed the City to

terminate the contract early either for its convenience or on Conway’s default, but

a termination for convenience would result in more costs for the City. The City

did terminate the contract partway through construction, claiming Conway

defaulted. After a lengthy bench trial, the trial court concluded that Conway was

not in default when the City terminated the contract and converted the termination

into one for convenience. We affirm the trial court’s decision. We also hold that

the City is not entitled to an offset for any defective work discovered after

termination because the City did not provide Conway with the contractually Conway Constr. Co. v. City of Puyallup, No. 98753-0

required notice and opportunity to cure. Finally, we hold that Conway is entitled

to attorney fees under the terms of the contract. Accordingly, we affirm in part and

reverse in part.

BACKGROUND

The City contracted with Conway to build the nation’s first arterial roadway

with pervious concrete. As is customary with public works projects, the City set

the terms of the project and wrote the contract. The contract included several

documents. As a transportation project, the contract incorporated the Washington

State Department of Transportation’s Standard Specifications for Road, Bridge,

and Municipal Construction (Standard Specifications). The City amended and

added terms to the Standard Specifications. Additionally, the City drafted a

separate project-specific contract (Public Works Contract) that provided separate

contract terms. Along with the project manual and other bid documents, these

documents governed the project.

There were a number of problems with the project. The City issued a

number of nonconformance reports to Conway in early 2016, which warned

Conway that some of its work did not meet contract specifications. The City also

saw unsafe work conditions and reported them to the Washington State

Department of Labor & Industries (L&I).

2 Conway Constr. Co. v. City of Puyallup, No. 98753-0

Citing the notice requirements in the Standard Specifications, the City gave

Conway a notice of suspension and breach of contract on March 9, 2016. The

notice identified nine contract violations. 1 Under the contract, Conway had 15

days to remedy these violations. Conway disputed the violations but also took

steps to remedy the breaches. On several occasions, Conway asked to meet and

discuss the City’s concerns. The City’s engineer refused, stating that “the required

actions seem to be clear, therefore I don’t see the need for a meeting.” Trial Ex.

46, at 2.

On March 25, 2016, the City issued a final notice of termination for default

to Conway and withheld further payments. Several weeks later, L&I cited Conway

for a serious safety violation. Roughly four months after termination, the City

found more defective concrete panels that needed to be replaced.

Conway sued the City, arguing that the termination for default was improper

and should be converted to a termination for convenience under the contract. After

a lengthy trial, the trial court found that the termination was for convenience. The

court denied the City an offset for Conway’s defective work and awarded Conway

damages including attorney fees.

1 These violations were 1) Wall C was installed incorrectly, 2) a wire between signal poles to hang traffic signals needed to be removed, 3) disputed payment for permeable ballast, 4) permeable ballast was contaminated by other construction activities, 5) 34 pervious concrete panels were nonconforming, 6) Conway was hampering the work of utilities in the area and needed to improve coordination, 7) additional traffic control signs were needed, 8) the installed concrete needed to be maintained by sweeping, and 9) jobsite safety violations. Trial Ex. 44. 3 Conway Constr. Co. v. City of Puyallup, No. 98753-0

The Court of Appeals largely affirmed, but it reversed Conway’s award for

attorney fees. The City and Conway both sought discretionary review, which we

granted. Associated General Contractors of Washington submitted an amicus brief

on the issue of attorney fees in support of Conway.

ANALYSIS

A trial court’s findings of fact are reviewed for substantial evidence, “which

requires that there be a sufficient quantum of evidence in the record to persuade a

reasonable person that a finding of fact is true.” Pardee v. Jolly, 163 Wn.2d 558,

566, 182 P.3d 967 (2008) (citing Sunnyside Valley Irrig. Dist. v. Dickie, 149

Wn.2d 873, 879, 73 P.3d 369 (2003)). We review conclusions of law de novo. Id.

(citing Sunnyside, 149 Wn.2d at 880).

I. Termination

A termination for default must be based on good cause, such as the

contractor’s failure to meet the requirements of the contract. See 5860 Chi. Ridge,

LLC v. United States, 104 Fed. Cl. 740, 755 (2012). By contrast, a termination for

convenience clause in a contract generally gives a public entity “the right to

terminate ‘at will,’” assuming no bad faith or abuse of discretion. John Reiner &

Co. v. United States, 163 Ct. Cl. 381, 390, 325 F.2d 438 (1963). 2

2 Termination for convenience clauses were developed in federal government contracts after the Civil War to allow the government to cancel military contracts “when changes in wartime technology or cessation of conflict rendered them unnecessary.” SAK & Assocs. v. Ferguson 4 Conway Constr. Co. v. City of Puyallup, No. 98753-0

These two forms of termination result in different financial consequences for

the contractor. Here, the contract specifies that under a termination for default, the

contractor must pay any extra costs the City incurs to complete the project,

including a new contractor’s higher prices, and payments are withheld until the

project is finished. Trial Ex. 1, at 1-81 (Standard Specifications section 1-

08.10(1)). Under the termination for convenience clause, however, the contractor

is entitled to be paid for actual work performed until the date of termination. Trial

Ex. 1, at 1-88 (Standard Specifications section 1-09.5).

The Standard Specifications incorporated into the contract automatically

convert an improper termination for default into a termination for convenience.

Trial Ex. 1, at 1-81 (Standard Specifications section 1-08.10(1) (stating that in the

event a “notice of termination for default has been issued and it is later determined

for any reason that the Contractor was not in default, the rights and obligations of

the parties shall be the same as if the notice of termination had been issued

Free access — add to your briefcase to read the full text and ask questions with AI

Conway Constr. Co. v. City of Puyallup, 490 P.3d 221, 197 Wash. 2d 825 (Wash. 2021).

490 P.3d 221 (Conway Constr. Co. v. City of Puyallup) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related