Conway Constr. Co. v. City of Puyallup

CourtWashington Supreme Court
DecidedJuly 8, 2021
Docket98753-0
StatusPublished
Cited by3 cases

This text of Conway Constr. Co. v. City of Puyallup (Conway Constr. Co. v. City of Puyallup) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Conway Constr. Co. v. City of Puyallup, (Wash. 2021).

Opinion

NOTICE: SLIP OPINION (not the court’s final written decision)

The opinion that begins on the next page is a slip opinion. Slip opinions are the written opinions that are originally filed by the court. A slip opinion is not necessarily the court’s final written decision. Slip opinions can be changed by subsequent court orders. For example, a court may issue an order making substantive changes to a slip opinion or publishing for precedential purposes a previously “unpublished” opinion. Additionally, nonsubstantive edits (for style, grammar, citation, format, punctuation, etc.) are made before the opinions that have precedential value are published in the official reports of court decisions: the Washington Reports 2d and the Washington Appellate Reports. An opinion in the official reports replaces the slip opinion as the official opinion of the court. The slip opinion that begins on the next page is for a published opinion, and it has since been revised for publication in the printed official reports. The official text of the court’s opinion is found in the advance sheets and the bound volumes of the official reports. Also, an electronic version (intended to mirror the language found in the official reports) of the revised opinion can be found, free of charge, at this website: https://www.lexisnexis.com/clients/wareports. For more information about precedential (published) opinions, nonprecedential (unpublished) opinions, slip opinions, and the official reports, see https://www.courts.wa.gov/opinions and the information that is linked there. FILE For the current opinion, go to https://www.lexisnexis.com/clients/wareports/. THIS OPINION WAS FILED IN CLERK’S OFFICE FOR RECORD AT 8 A.M. ON SUPREME COURT, STATE OF WASHINGTON JULY 8, 2021 JULY 8, 2021 ERIN L. LENNON SUPREME COURT CLERK

IN THE SUPREME COURT OF THE STATE OF WASHINGTON

) CONWAY CONSTRUCTION ) COMPANY, ) ) Petitioner / Cross-Respondent, ) No. 98753-0 ) v. ) ) En Banc CITY OF PUYALLUP, ) ) Respondent / Cross-Petitioner. ) Filed: July 8, 2021 _______________________________)

GONZÁLEZ, C.J.—The city of Puyallup (City) hired Conway Construction

Company to build a road. The contract between the two allowed the City to

terminate the contract early either for its convenience or on Conway’s default, but

a termination for convenience would result in more costs for the City. The City

did terminate the contract partway through construction, claiming Conway

defaulted. After a lengthy bench trial, the trial court concluded that Conway was

not in default when the City terminated the contract and converted the termination

into one for convenience. We affirm the trial court’s decision. We also hold that

the City is not entitled to an offset for any defective work discovered after

termination because the City did not provide Conway with the contractually For the current opinion, go to https://www.lexisnexis.com/clients/wareports/. Conway Constr. Co. v. City of Puyallup, No. 98753-0

required notice and opportunity to cure. Finally, we hold that Conway is entitled

to attorney fees under the terms of the contract. Accordingly, we affirm in part and

reverse in part.

BACKGROUND

The City contracted with Conway to build the nation’s first arterial roadway

with pervious concrete. As is customary with public works projects, the City set

the terms of the project and wrote the contract. The contract included several

documents. As a transportation project, the contract incorporated the Washington

State Department of Transportation’s Standard Specifications for Road, Bridge,

and Municipal Construction (Standard Specifications). The City amended and

added terms to the Standard Specifications. Additionally, the City drafted a

separate project-specific contract (Public Works Contract) that provided separate

contract terms. Along with the project manual and other bid documents, these

documents governed the project.

There were a number of problems with the project. The City issued a

number of nonconformance reports to Conway in early 2016, which warned

Conway that some of its work did not meet contract specifications. The City also

saw unsafe work conditions and reported them to the Washington State

Department of Labor & Industries (L&I).

2 For the current opinion, go to https://www.lexisnexis.com/clients/wareports/. Conway Constr. Co. v. City of Puyallup, No. 98753-0

Citing the notice requirements in the Standard Specifications, the City gave

Conway a notice of suspension and breach of contract on March 9, 2016. The

notice identified nine contract violations. 1 Under the contract, Conway had 15

days to remedy these violations. Conway disputed the violations but also took

steps to remedy the breaches. On several occasions, Conway asked to meet and

discuss the City’s concerns. The City’s engineer refused, stating that “the required

actions seem to be clear, therefore I don’t see the need for a meeting.” Trial Ex.

46, at 2.

On March 25, 2016, the City issued a final notice of termination for default

to Conway and withheld further payments. Several weeks later, L&I cited Conway

for a serious safety violation. Roughly four months after termination, the City

found more defective concrete panels that needed to be replaced.

Conway sued the City, arguing that the termination for default was improper

and should be converted to a termination for convenience under the contract. After

a lengthy trial, the trial court found that the termination was for convenience. The

court denied the City an offset for Conway’s defective work and awarded Conway

damages including attorney fees.

1 These violations were 1) Wall C was installed incorrectly, 2) a wire between signal poles to hang traffic signals needed to be removed, 3) disputed payment for permeable ballast, 4) permeable ballast was contaminated by other construction activities, 5) 34 pervious concrete panels were nonconforming, 6) Conway was hampering the work of utilities in the area and needed to improve coordination, 7) additional traffic control signs were needed, 8) the installed concrete needed to be maintained by sweeping, and 9) jobsite safety violations. Trial Ex. 44. 3 For the current opinion, go to https://www.lexisnexis.com/clients/wareports/. Conway Constr. Co. v. City of Puyallup, No. 98753-0

The Court of Appeals largely affirmed, but it reversed Conway’s award for

attorney fees. The City and Conway both sought discretionary review, which we

granted. Associated General Contractors of Washington submitted an amicus brief

on the issue of attorney fees in support of Conway.

ANALYSIS

A trial court’s findings of fact are reviewed for substantial evidence, “which

requires that there be a sufficient quantum of evidence in the record to persuade a

reasonable person that a finding of fact is true.” Pardee v. Jolly, 163 Wn.2d 558,

566, 182 P.3d 967 (2008) (citing Sunnyside Valley Irrig. Dist. v. Dickie, 149

Wn.2d 873, 879, 73 P.3d 369 (2003)). We review conclusions of law de novo. Id.

(citing Sunnyside, 149 Wn.2d at 880).

I. Termination

A termination for default must be based on good cause, such as the

contractor’s failure to meet the requirements of the contract. See 5860 Chi. Ridge,

LLC v. United States, 104 Fed. Cl. 740, 755 (2012). By contrast, a termination for

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Conway Constr. Co. v. City of Puyallup, Counsel Stack Legal Research, https://law.counselstack.com/opinion/conway-constr-co-v-city-of-puyallup-wash-2021.