J & J Electric, Inc. v. Gilbert H. Moen Co.

516 P.2d 217, 9 Wash. App. 954, 1973 Wash. App. LEXIS 1296
CourtCourt of Appeals of Washington
DecidedNovember 19, 1973
Docket550-3
StatusPublished
Cited by8 cases

This text of 516 P.2d 217 (J & J Electric, Inc. v. Gilbert H. Moen Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J & J Electric, Inc. v. Gilbert H. Moen Co., 516 P.2d 217, 9 Wash. App. 954, 1973 Wash. App. LEXIS 1296 (Wash. Ct. App. 1973).

Opinion

Green, C.J.

A lien foreclosure action brought by J & J Electric, Inc., an electrical subcontractor, against First Baptist Homes, Inc. mushroomed into a series of claims and counterclaims with additional parties. The other participants are: Gilbert H. Moen Company, the prime contractor, and its surety, St. Paul Fire & Marine Insurance Co.; United Pacific Insurance Company, J & J Electric’s surety; Manson Bennett of Seattle, and Paddock & Hollingberry of Yakima, architects; and Bouillon, Christofferson & Schairer, electrical engineers. These claims and counterclaims were disposed of by the court without a jury. J & J Electric and United Pacific appeal from a judgment entered in favor of Moen against them for $110,907.74 plus costs. United Pacific appeals from the summary judgment dismissing its claim against the architects and engineers.

On May 19, 1967, Gilbert H. Moen Company, as prime contractor, executed a contract with First Baptist Homes to construct an 11-story, 153-unit senior citizens home in Yakima. On July 15, Moen subcontracted the performance of *956 the electrical work to J & J Electric. Thereafter, United Pacific issued a surety bond insuring J & J Electric’s faithful performance. J & J Electric’s performance was materially deficient under its contract. On June 29, 1968, Moen notified J & J Electric in writing that unless the deficiencies were cured by July 22, another electrical subcontractor would be secured to complete the contract. About October 4, 1968, the approximate time the prime contract was to have been completed, Moen terminated J & J Electric and tendered to United Pacific the opportunity to correct and complete the work required by the electrical subcontract. It refused and Wilson Electric Company was employed by Moen to correct and complete the electrical work. This work was satisfactorily completed and accepted on April 4, 1969.

Error is assigned to the italicized portion of the following findings of fact:

11.
Mr. Donald Moen was advised on several occasions, starting early in the job by Bouillon, Christofferson and Schairer that there were deficiencies in J & J’s electrical work. That he was unaware of the substantial nature of these deficiencies and understood that the same were being called to the attention of the architect and relied upon the architect’s judgment in connection therewith.
13.
J & J Electrical thereafter commenced to furnish labor and material in connection with said contracts. J & J’s performance was materially deficient and substantially deviated from and did not reasonably conform to the requirements of the contract plans and specifications or the National Electric Code. Such defects and deviations were of such a nature as to substantially and adversely affect Moen’s ability to meet its prime contract obligations with the building owner. On June 29, 1968, Moen timely delivered to J & J Electric a detailed and adequate notice of intent to terminate the subcontract (Exhibit 12), allowing J & J a reasonable time to correct said deficiencies and deviations. Moen thereafter delayed exercise of its* termination right and of actual termination of the subcontract upon J & J’s implied request and *957 upon J &J’s express assurances of correction of said deficiences and deviations. That on July 23, 1968, Moen received additional assurances that they would be timely corrected. That under the circumstances Moen was justified in relying upon these additional assurances and allowing additional time to J & J Electric in which to make such corrections. The delay in terminating J & J’s performance under the sub-contract was known by J & J to be conditional upon their timely making correction of the deficiencies and deviations complained of. It became clear in mid-September, 1968, that J & J’s deficiencies and deviations were not being corrected in reasonable compliance with the subcontract and Moen terminated the subcontract and terminated J & J Electric from the job.
15.
United Pacific Insurance Company was not prejudiced, injured or damaged by Moen’s delay in removing J & J Electric from the job either by reason of the time granted by Moen to J & J Electric in the notice of June 29, 1968 (Exhibit 12) or in Moen’s extending the time granted therein. After June 28, 1968, United Pacific Insurance Company was as aware as Moen was with the problems of J & J’s performance, or had access to and received the same information as did Moen regarding such work; that United Pacific knew or had access to the same knowledge as was available to Moen as to the nature of the work to be done by Wilson Electric in correcting the deficiencies and deviations in J & J’s electrical work. That United Pacific Insurance Company was aware that Wilson Electric was retained to correct such deficiencies and deviations and working upon a cost-plus basis and acquired knowledge during the period of Wilson’s work that the actual correction costs would be greater than the previous estimates and greater than the amount of retainage in the hands of Moen.
United Pacific Insurance Company is not entitled to a release as surety by reason of any payment in excess of what was owed to J & J Electric by Gilbert H. Moen Company. That at the time of the last progress payment by Gilbert H. Moen Company to J & J Electric on June 10, 1968, in the sum of $13,885.25, they knew there were deficiencies in J & J’s work but had no reason to believe that they were of sufficient magnitude or of such a nature as to jeopardize timely completion of the con *958 tract. That in light of the then information and. the retainage still remaining, the payment was reasonably paid. Moen was not reasonably advised as to the number or severity of the defects of J & J’s work at any time during the course of the job.
21.
The defects and deficiencies corrected by Wilson Electrie occurred throughout the project. In taking over the work to correct and complete the same, Gilbert H. Moen Company entered into a substantially different contract with Wilson Electric Company than it had with J & J Electric. The nature of the work to be done by Wilson Electric Company under the direction of Gilbert H. Moen Company was primarily of a corrective nature. This was known to United Pacific Insurance Company. Defendant Moen’s tender of the work to the United Pacific Insurance Company for completion, together with the need, for immediate action in completing the work pursuant to Gilbert H. Moen Company’s contract with Yakima First Baptist Homes, Inc., together with the difference in the nature of work to be done, entitled Gilbert H. Moen Company to reasonable latitude in making its contract with Wilson Electric Company to correct the work, and this was not unreasonably done.
22.
The building contract between the owner, Yakima First Baptist Homes, Inc., and the contractor, Gilbert H.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ducolon Mechanical, Inc. v. Shinstine/Forness, Inc.
893 P.2d 1127 (Court of Appeals of Washington, 1995)
Watson, Watson, Rutland/Architects, Inc. v. BD. OF EDUC.
559 So. 2d 168 (Supreme Court of Alabama, 1990)
Transamerica Insurance Company v. City Of Kennewick
785 F.2d 660 (Ninth Circuit, 1986)
Transamerica Insurance v. City of Kennewick
785 F.2d 660 (Ninth Circuit, 1986)
WF Holt Co. v. a & E Elec. Co., Inc.
665 S.W.2d 722 (Court of Appeals of Tennessee, 1983)
Mayor of Columbus v. Clark-Dietz & Associates-Engineers, Inc.
550 F. Supp. 610 (N.D. Mississippi, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
516 P.2d 217, 9 Wash. App. 954, 1973 Wash. App. LEXIS 1296, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-j-electric-inc-v-gilbert-h-moen-co-washctapp-1973.