Loyland v. Stone & Webster Engineering Corp.

514 P.2d 184, 9 Wash. App. 682
CourtCourt of Appeals of Washington
DecidedDecember 17, 1973
Docket1566-1
StatusPublished
Cited by15 cases

This text of 514 P.2d 184 (Loyland v. Stone & Webster Engineering Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Loyland v. Stone & Webster Engineering Corp., 514 P.2d 184, 9 Wash. App. 682 (Wash. Ct. App. 1973).

Opinion

*683 Williams, J.

— Kenneth Loyland and George Edwin Cross brought this action against Stone & Webster Engineering Corporation to recover for personal injuries which they sustained while employed by a general contractor who was building an addition to the Rocky Reach Hydroelectric Dam located in Chelan County, Washington. The cause was tried to the court, sitting with a jury, and resulted in a verdict of $40,000 for Loyland and $35,000 for Cross. Stone & Webster appeals from the judgment entered on the verdict.

The facts are these: Public Utility District No. 1 of Chelan County by written contract employed Stone & Webster with responsibility

to design and to supervise, direct and administer the construction of the four unit extension ... to the Rocky Reach Hydroelectric Power Plant to complete the plant.

Also, it was specified in the contract that Stone & Webster was required to act as the district’s “Engineers, Purchasing Department and Construction Supervisors” and would

make all necessary engineering studies and determinations, recommend to you the type and character of equipment and of construction required and prepare plans and specifications for equipment, materials and construction work, . . .

Stone & Webster agreed that it would “supervise the entire construction, including all building operations, installation of all equipment and all other features” and would “provide for inspection of important items and require the fulfillment of all contracts in accordance with the plans and specifications.”

The district promised to pay Stone & Webster a fixed fee for its performance and also a fee for the salaries of certain of its employees including those of its “Inspection-Expediting” department “for the time they are engaged on your (the district’s) work plus an equal amount for overhead expenses.”

*684 The district then entered into a contract with Halverson-Mason for the general construction of the project. The form of the contract was prepared by Stone & Webster in great detail. The pertinent portions of the section on concrete provide that the contractor shall

Furnish all materials and equipment and manufacture, transport, place, finish, protect and cure concrete, and prepare surfaces of existing concrete and surfaces of concrete between placements. The Contractor will have the option of either furnishing a batching plant at the job site to supply concrete, or using ready-mixed concrete in accordance with specification for Ready-Mixed Concrete ASTM C94. Whichever source of concrete is utilized, the facilities must be in accordance with applicable specifications and approved by the Engineers.

In addition, it was provided:

The Contractor shall provide all formwork as required to receive and form all concrete work, conforming to the shapes, lines and dimensions of the members as shown on the Construction Drawings. Forms shall be substantial and sufficiently tight to prevent leakage of mortar or liquid; properly supported, braced and tied together and of ample strength and rigidity to support adequately, without deflection or distortion, the pressure and weight of the concrete as a liquid together with the movement of men and equipment. Vibration of concrete increases the fluid pressure on forms, which should be designed for higher pressures than otherwise.

Also, “The type, shape, size, quality and strength of all materials of which the forms are made shall be subject to the approval of the Engineers.”

The Contractor shall provide equipment adequate for handling and placing concrete containing the maximum size aggregate and low slump concrete mixes. Approval of the Engineers shall be obtained before beginning a run of concrete.

The contractor was charged with compliance with safety regulations which Stone & Webster had authority to prescribe.

At the time of the accident, the general contractor, Halvorson-Mason, was completing placement of concrete into a *685 large form which it had designed and built. When about 400,000 pounds of wet concrete had been placed, the form broke, cascading the concrete, part of the form, and Loyland and Cross, who were working beneath the pour, into the Columbia River, causing the injuries complained of.

Stone & Webster assign error to three instructions given to the jury by the court, the court’s refusal to give nine proposed instructions and its refusal to sustain the challenge to the sufficiency of the evidence. The three instructions given about which error is claimed are:

The plaintiffs claim that the defendant was negligent in (2) failing to properly supervise the construction or manner of use of concrete forms erected by the general contractor; (b) failing to warn plaintiffs of any dangers or hazards that might exist; (c) failing to halt the activities of the general contractor when a hazardous condition existed. The plaintiffs claim that defendant’s conduct was a proximate cause of injuries and damage to plaintiffs. The defendant denies these claims. The defendant further denies the nature and extent of the claimed injuries and damage.
The foregoing is merely a summary of the claims of the parties. You are not to take the same as proof of the matters claimed and you are to consider only those matters which are established by the evidence. These claims have been outlined solely to aid you in understanding the issues.

Instruction No. 3.

Washington State Safety Standards for Construction Work applicable to the general contractor, HalvorsonMason, provides as follows:
“WAC 296-40-135 — Persons to be Notified of Work Overhead. When it is necessary for employees to work above other employees, those working underneath shall be notified, and when employees are put to work underneath other employees, those working overhead shall be notified.”
“WAC 296-40-420 — Concrete Work.
(2) Concrete forms shall be checked during pour to prevent danger of collapse, and constant supervision over same shall be maintained.”

Instruction No. 7.

*686 Engineers who plan and supervise construction projects are under a duty to exercise ordinary care for the safety of workmen on the project, and not to expose them to hidden dangers which are known or through the exercise of reasonable care should have been known to the engineers.

Instruction No. 8. .

Stone & Webster contends that it did exercise due care in the preparation of the plans and carefully inspected the work to the extent that it was required to do so by the contract with the utility district. It is claimed that the inspections had nothing to do with the strength or stability of the forms’ structure but only to make sure that the finished product would conform to the “line, grade and finish” specified in the plans.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michaels v. CH2M Hill, Inc.
171 Wash. 2d 587 (Washington Supreme Court, 2011)
Riggins v. Bechtel Power Corp.
722 P.2d 819 (Court of Appeals of Washington, 1986)
Moloso v. State
644 P.2d 205 (Alaska Supreme Court, 1982)
Porter v. Stevens, Thompson & Runyan, Inc.
602 P.2d 1192 (Court of Appeals of Washington, 1979)
Jarrard v. Seifert
591 P.2d 809 (Court of Appeals of Washington, 1979)
Krieger v. J. E. Greiner Co.
382 A.2d 1069 (Court of Appeals of Maryland, 1978)
Bayne v. Todd Shipyards Corp.
568 P.2d 771 (Washington Supreme Court, 1977)
Detweiler Bros., Inc. v. John Graham & Co.
412 F. Supp. 416 (E.D. Washington, 1976)
Amant v. Pacific Power & Light Co.
520 P.2d 181 (Court of Appeals of Washington, 1974)
J & J Electric, Inc. v. Gilbert H. Moen Co.
516 P.2d 217 (Court of Appeals of Washington, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
514 P.2d 184, 9 Wash. App. 682, Counsel Stack Legal Research, https://law.counselstack.com/opinion/loyland-v-stone-webster-engineering-corp-washctapp-1973.