GEMS Environmental Management Services

CourtArmed Services Board of Contract Appeals
DecidedJuly 2, 2024
Docket61737, 61831, 62322, 62323, 62324, 62325, 62326, 62327, 62328, 62329, 62330, 62331, 62332, 62333, 62785, 62786, 62787
StatusPublished

This text of GEMS Environmental Management Services (GEMS Environmental Management Services) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GEMS Environmental Management Services, (asbca 2024).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) GEMS Environmental Management ) ASBCA Nos. 61737, 61831, 62322 Services ) 62323, 62324, 62325 ) 62326, 62327, 62328 ) 62329, 62330, 62331 ) 62332, 62333, 62785 ) 62786, 62787 ) Under Contract No. W91238-15-D-0014 )

APPEARANCE FOR THE APPELLANT: Casey J. McKinnon, Esq. Cohen Seglias Pallas Greenhall & Furman PC Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Alfred L. Faustino, Esq. Kevin A. Cullen, Esq. Colby K. Stewart, Esq. Amanda R. Fuller, Esq. Schuyler Lystad, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Sacramento

OPINION BY ADMINISTRATIVE JUDGE PROUTY ON CROSS-MOTIONS FOR PARTIAL SUMMARY JUDGMENT

The parties in this construction contract dispute have crossed-moved 1 for partial summary judgment over several issues mostly involving contract interpretation and three more purely legal matters: installation-wide changes in security requirements during contract performance; whether a contractor is entitled to costs for responding to a request for proposal that the government later decided was unnecessary; and the availability of interest as a remedy for retainage of progress payments. These cross-motions do not address all of the issues before us in these appeals, nevertheless, their consideration had the potential to either resolve some particular appeals or at least narrow the factual issues that the parties will need to prove at trial. For the

1 To be more specific, the government moved for partial summary judgment on seven claims before us while GEMS only cross-moved on five of these claims, while opposing the government’s motion on the remaining two. reasons to be explained below, we hereby grant the government’s motion for partial summary judgment in part and completely deny appellant, GEMS Environmental Management’s (GEMS), cross-motion for partial summary judgment. As will be seen, the portions of the government’s motion which we deny are those portions for which the government has not provided sufficient evidence at this point to support judgment in its favor.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTIONS

I. The Project and General Contract Terms

On September 29, 2015, the United States Army Corps of Engineers (the Corps) awarded to GEMS the above-captioned multiple award task order contract (the contract) to perform design-build construction services at the Military Ocean Terminal Concord (MOTCO) in California (see ASBCA No. 61831 R4, tab 4). On the same day it also issued to GEMS its first task order (TO) on the contract (see ASBCA No. 61737 R4, tab 3).

The purpose of this TO was for GEMS to design and build a one-story General Purpose Maintenance Shop (the GPMS) and a one-story Storage Building at MOTCO (see ASBCA No. 61831 R4, tab 8 at GOVTO 1521 (¶ 1.1), GOVTO 1522 (¶2.1)) 2. The solicitation for the TO (also referred to herein as the RFP) further explained the purpose of the GPMS, which was to provide indoor facilities for the repair and maintenance of over-sized top-pick spreaders known as “super-stackers,” which had previously needed to be worked on in the outdoors (id. at GOVTO 1523).

Though the RFP included conceptual drawings, those were not intended to represent the entire design of the building or even, necessarily, its complete orientation. Thus, Contract Specification § 01 10 10 ¶ 6.7.1 provides in relevant part:

Preferred building location and orientation of the new facility is shown on C-120. The final site design shall be determined by the contractor meeting the minimum provisions of all applicable references indicated in these RFP documents and with the final approval of the contracting officer. . .

(ASBCA No. 61831 R4, tab 8 at GOVTO 1542)

2 “GOVTO ___” is the Bates number for items in the respective Rule 4 files, except that we delete unnecessary zeroes. For example, a page Bates stamped as “GOVTO 000050” will be referenced herein as “GOVTO 50.”

2 The point of the conceptual drawings in the RFP, paragraph 1.5 of this specification stated, was to “indicate the general location of this facility, its approximate maximum size, and other system parameters that represent functional relationships of the project program” (ASBCA No. 61831 R4, tab 8 at GOVTO 1522). Paragraph 1.6 of the specification continued:

The government’s conceptual facility and site design provided in the RFP documents illustrates intent and functional relationships and does not indicate all necessary construction requirements or components. The written RFP describes associated technical, performance and system requirements. The Contractor is responsible for the complete Project design . . .

(Id.)

As explained in the RFP, the project was required to conform to the MOTCO Installation Design Guide (ASBCA No. 61831 R4, tab 8 at GOVTO 1521 (¶ 1.3)). It was also required to be designed and constructed “in accordance with the criteria contained herein and using industry standard materials and efficient practices” (id.).

The contract incorporated by reference Federal Acquisition Regulation (FAR) clause 52.236-21, Specifications and Drawings for Construction (FEB 1997) (see ASBCA No. 61831 R4, tab 4 at GOVTO 699). FAR 52.236-21 is a standard contract clause that provides in relevant part that, “[a]nything mentioned in the specifications and not shown in the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In the case of a difference between the drawings and specifications, the specifications shall govern.” FAR 52.236-21(a). 3

Another standard clause in the contract was included in paragraph 3 of “Supplemental Contract Requirements,” apparently attached to the RFP. That paragraph provided:

3. Authorities. Only a warranted Contracting Officer (either PCO or ACO) acting within their delegated limits has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an

3 The contract also incorporated by reference FAR 52.236-21 Alt I, Specifications and Drawings for Construction (Feb 1997) Alternative (APR 2004), (see ASBCA No. 61831 R4, tab 4 at GOVTO 699), but that FAR provision does not affect the issue before us today.

3 individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract you shall not proceed with the change and shall immediately notify the contracting officer.

(Gov’t mot. at Ex. B) 4

II. Facts Related to Two Claims Regarding a Driveway

A. Contract Specifications and Drawings Related to Parking and a Driveway

Section 6.7 of the task order specifications includes two 5 salient provisions to the driveway dispute. They are:

6.7.3 Parking Area. 10 new parking stalls, including 1 ADA compliant space, shall be provided to accommodate facility personnel. Parking areas are required to comply with the requirements of UFC 4-010-01.

6.7.4 Vehicle Access. One driveway entrance shall be provided on ‘A’ Street. See sheet C-120.

(See ASBCA No. 61831 R4, tab 8 at GOVTO 1542)

The contract drawings also indicate a driveway. The upper right hand side of Sheet C-120 (referenced in section 6.7.4 directly above), depicts an unlabeled driveway connecting “A” Street to the labeled parking area and to the “concrete hardstand and access” as may be seen below (see ASBCA No. 61831 R4, tab 8 at GOVTO 2011):

4 We refer to the government’s motion for partial summary judgment as “gov’t mot.” GEMS’s cross-motion and opposition is “app. mot.,” with the parties’ respective reply briefs, “gov’t reply” and “app.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horowitz v. United States
267 U.S. 458 (Supreme Court, 1925)
United States v. Diebold, Inc.
369 U.S. 654 (Supreme Court, 1962)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Sullivan v. Stroop
496 U.S. 478 (Supreme Court, 1990)
United States v. Winstar Corp.
518 U.S. 839 (Supreme Court, 1996)
Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Scott Timber Company v. United States
333 F.3d 1358 (Federal Circuit, 2003)
Road & Highway Builders, LLC v. United States
702 F.3d 1365 (Federal Circuit, 2012)
IBP, Inc. v. Alvarez
546 U.S. 21 (Supreme Court, 2005)
Almanza v. United States
935 F.3d 1332 (Federal Circuit, 2019)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
GEMS Environmental Management Services, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gems-environmental-management-services-asbca-2024.