Cincinnati Insurance v. United States

71 Fed. Cl. 544, 2006 U.S. Claims LEXIS 153, 2006 WL 1645031
CourtUnited States Court of Federal Claims
DecidedJune 2, 2006
DocketNo. 05-751C
StatusPublished
Cited by1 cases

This text of 71 Fed. Cl. 544 (Cincinnati Insurance v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cincinnati Insurance v. United States, 71 Fed. Cl. 544, 2006 U.S. Claims LEXIS 153, 2006 WL 1645031 (uscfc 2006).

Opinion

OPINION

FIRESTONE, Judge.

Pending before the court is a motion by the defendant, the United States (“government” or “United States”), to dismiss the equitable subrogation claim of the plaintiff, [545]*545Cincinnati Insurance Company (“plaintiff’ or “CIC”), for failure to state a claim upon which relief can be granted, pursuant to Rule 12(b)(6) of the Rules of the United States Court of Federal Claims (“RCFC”), or, in the alternative, the government seeks summary judgment pursuant to RCFC 56. The government contends that the plaintiff, a Miller Act, 40 U.S.C. §§ 3131-3134 (2000 & Supp. 2002), surety of a government contractor who fulfilled its obligations under a payment bond on a government construction contract, may not state a claim against the United States pursuant to the doctrine of equitable subro-gation.2 Because the plaintiff paid subcontractors pursuant to its payment bond obligations, rather than taking over performance of the contract, the government argues that the plaintiffs claim for reimbursement of its costs through the doctrine of equitable sub-rogation must be dismissed.3 In the alternative, the government seeks summary judgment on the plaintiff’s claim that the United States was arbitrary and capricious in making a progress payment to the contractor rather than to the plaintiff after the plaintiff notified the government that it believed the contractor to be in default on the contract. The government argues that as a matter of law, Federal Acquisition Regulation (“FAR”) § 28.106-7 (2006) prohibited the government from withholding the payment from the contractor because the contract was still being performed.

The plaintiff argues that a payment bond surety is subrogated not only to the rights of the subcontractors who it pays, but also to the rights of the prime contractor, who is in privity of contract with the government, and that therefore a payment bond surety may state a claim for equitable subrogation in this court. The plaintiff also argues that the government is not entitled to summary judgment because FAR § 28.106-7 did not prohibit the government from withholding the payment at issue from the contractor because performance was substantially complete.

For the reasons that follow, the court agrees with the plaintiff that payment bond sureties are subrogated to the rights of both the subcontractors whom it pays and the prime contractor, who is in privity of contract with the government. Therefore the government’s motion to dismiss is DENIED. The court also finds that there is a genuine issue of material fact, which precludes summary judgment on the merits of the plaintiffs claim. Therefore, the government’s motion for summary judgment is also DENIED.

BACKGROUND

The following facts are undisputed unless otherwise noted.4 In 2003, the U.S. Army Corps of Engineers (“Corps”) entered into a construction contract with Lasker, Inc. (“Lasker”), No. EACA03-03-C-0011, to perform work at the C-130J Engine and Propel-lor Storage Building, Little Rock Air Force Base in Pulaski County, Arkansas, for a total contract price of $1,811,000. As surety, the [546]*546plaintiff provided performance and payment bonds in the amount of $1,811,000. On June 17, 2004, Lasker submitted Pay Application No. 10 seeking $146,247.40. Including this $146,247.40 payment, Lasker had received a total of $1,636,923.60, leaving a balance of contract funds of $183,684.40, the equivalent of approximately 10% of the initial contract price. On June 23, 2004, the Corps advised the plaintiff that the Corps contemplated paying Lasker only $67,000 and retaining $116,000 for closeout, punch list, and incomplete work. On June 25, 2004, the plaintiff sent a letter to the Corps indicating that it had received claims from Lasker’s subcontractors and stated that the plaintiff was withdrawing all of its previous consents with respect to payments being made to Lasker.

The government’s exhibit 6, which is a government form completed in response to Lasker’s Pay Application No. 10, states that the actual percentage of work completed was 98%, and that “contract substantially complete ... on 18 June 2004.” In the government’s proposed findings of uncontroverted fact, the government proposes that “as of June 18, 2004, the contract was 98% complete.” The plaintiff only admits that the contract was substantially complete as of June 18, 2004. The plaintiff does admit that as of that date, several punch list items still needed to be addressed.

On June 26, 2004, the contracting officer’s representative advised Lasker that Pay Application No. 10 was not a proper invoice. The reasons stated included the fact that the remaining contract balance was insufficient to protect the government’s interest for outstanding payments to subcontractors, the fact that subcontractors had not been paid from previous progress payments, and the fact that Lasker’s certification of the application pursuant to FAR § 52.232-5(c), which requires a contractor to certify that all payments due to subcontractors have been paid, was inconsistent with its nonpayment of subcontractors. On July 27, 2004, Lasker submitted a revised Pay Application No. 10 and included a certification pursuant to FAR § 52.232-5(c), although it still had not paid its subcontractors.

On August 4, 2004, payment was made to Lasker in the amount of $106,447.50, without objection. On that same day, the plaintiff sent a letter to the Corps demanding that all further payments be forwarded directly to the plaintiff. On August 30, 2004, the plaintiff sent a letter to the Corps advising that it had learned of the August 4, 2004 payment to Lasker and demanding that the Corps reimburse the plaintiff for costs and expenses related to the “premature release of contract funds.” On September 10, 2004, the contracting officer responded that it was his opinion that he had been precluded from withholding payment to Lasker by FAR § 26.106-7(a). The letter also stated that the Corps had received an Assignment of Claims, which directed that the plaintiff should receive payments under the contract, on August 12, 2004, but that payment to Lasker had already been made.

The plaintiff filed its complaint in this court on July 14, 2005. The plaintiff claims that it was damaged in the amount of $86,500 by the government’s payment of $106,447.50 to Lasker. The government filed its motion to dismiss, or in the alternative, for summary judgment, on October 27, 2005. Oral argument was held on April 28, 2006.5

I. Motion to Dismiss

In Commercial Casualty Insurance Co. of Georgia v. United States, No. 03-2033, this court issued an opinion on May 26, 2006 addressing the government’s argument that payment bond sureties may not maintain claims for reimbursement in this court. This court held that a payment bond surety steps into the shoes of the prime contractor and asserts the prime contractor’s contract claim, and that therefore a payment bond surety may maintain a suit against the United States for retained contract funds still in the government’s possession. The court will not [547]*547repeat the analysis here. Instead, the court attaches its opinion in Commercial Casualty as Appendix A and adopts that reasoning.

Moreover, in an opinion in Capitol Indemnity Corp. v. United States, No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National American Insurance v. United States
72 Fed. Cl. 451 (Federal Claims, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
71 Fed. Cl. 544, 2006 U.S. Claims LEXIS 153, 2006 WL 1645031, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cincinnati-insurance-v-united-states-uscfc-2006.