RLI Insurance v. Indian River School District

556 F. Supp. 2d 356, 2008 U.S. Dist. LEXIS 43303, 2008 WL 2275487
CourtDistrict Court, D. Delaware
DecidedJune 3, 2008
DocketCivil Action 05-858-JJF
StatusPublished
Cited by3 cases

This text of 556 F. Supp. 2d 356 (RLI Insurance v. Indian River School District) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RLI Insurance v. Indian River School District, 556 F. Supp. 2d 356, 2008 U.S. Dist. LEXIS 43303, 2008 WL 2275487 (D. Del. 2008).

Opinion

MEMORANDUM OPINION

FARNAN, District Judge.

Pending before the Court are Motions for Summary Judgment, filed by each of the Defendants in this action, EDiS Company (“EDiS”) (D.I.88), Becker Morgan Group, Inc (“Becker Morgan”) (D.I.91) and Indian River School District (“Indian River”)(D.I.89). For the reasons discussed, the Court will grant the Defendants’ motions.

I. BACKGROUND

A. Factual Background

This action arises out of performance and payment bonds issued by Plaintiff, RLI Insurance Company (“RLI Insurance”), on behalf of McDaniel Plumbing and Heating, Inc. (“McDaniel”) in conjunction with McDaniel’s contract with Indian River for mechanical, plumbing and automatic temperature control construction on a construction project designated as New *358 Sussex Central High School in Georgetown, Delaware (“the Project”), which was entered on or about August 28, 2002. Because Indian River is a public school district, the Project was governed by Delaware’s State Procurement Act, 29 Del. C. § 6962, which required the execution of a performance bond for McDaniel’s work on the Project. Accordingly, on or about September 5, 2002, RLI Insurance, as surety, issued performance and payment bonds (hereinafter, “the Bond”) for the Project to McDaniel, for the benefit of Indian River. By reference, the Bond incorporated the terms of the construction contract between McDaniel and Indian River.

Indian River engaged Becker Morgan as project architect, and EDiS as construction manager. As architect, Becker Morgan provided Indian River with schematic design documents, design development documents, construction documents and bidding phase and construction administration phase services. (D.I. 91 at Exh. A, Art. 2.) As construction manager, EDiS provided administrative, management and related services to coordinate scheduled activities and responsibilities of the project contractors with each other and with EDiS, Becker Morgan and Indian River to manage the Project. More specifically, EDiS scheduled and conducted meetings, coordinated the sequence of construction, maintained accounting records for the Project, reviewed payment applications, recorded Project progress, and oversaw Project contractors’ performances. (See D.I. 88 at Exh. A.)

Pursuant to the contract governing the relationship between Indian River and McDaniel, the “Standard Form of Agreement Between Owner and Contractor” (hereinafter, “the Contract”), EDiS and Becker Morgan were required to provide Indian River with information regarding Project work progress, and Project contractors’ entitlement to payment. After reviewing a contractor’s application for payment, EDiS and Becker Morgan would issue an Application and Certificate for Payment to Indian River. The Contract states:

The issuance of a separate Certificate of Payment or Project Certificate for Payment will constitute representations made separately by the Construction Manager and Architect to the Owner, based on their individual observations at the site and the date comprising the Application for Payment submitted by the Contractor, that the Work has progressed to the point indicated and that to the best of their knowledge, information and belief, the quality of the Work is in accordance with the Contract Documents.

(D.I. 95 at Exh. A, Art. 9.4.3.)

McDaniel began work on the Project on or about August 29, 2002. Over the next two years, Indian River made periodic progress payments to McDaniel based on EDiS’s and Becker Morgan’s certifications. During the course of the Project, McDaniel fell behind on its scope of work. However, EDiS and Becker Morgan continued to issue certifications for payment, and Indian River continued to issue payments to McDaniel, in reliance upon EDiS’s and Becker Morgan’s certification. RLI Insurance was notified in April 2004, by EDiS that McDaniel’s performance under the Contract was unsatisfactory, and that McDaniel had fallen behind schedule. (D.I. 95 at Exh. B.) By letter dated July 25, 2004, RLI Insurance instructed Christian McCone, the project manager for EDiS (“Mr. McCone”), to cease issuance of any further payments to McDaniel without RLI Insurance’s consent. (D.I. 95 at Exh. C.) RLI Insurance’s letter was copied to Indian River. (Id.) However, EDiS and Becker Morgan authorized additional pay *359 ments to McDaniel. According to Indian River, this payment was made by joint check to McDaniel and one of its unpaid subscribers, who refused to ship equipment to the Project until they were paid, and that RLI Insurance expressly consented to this joint payment on August 17, 2004, by letter stating that “notwithstanding [RLI Insurance’s] previous directive to hold distribution of any funds, we agree with the issuance of the joint checks at this point and authorize their release.” (D.I. 100 at Exh. 4.)

On October 11, 2004, Indian River terminated McDaniel’s employment under the Contract for non-performance, and failure to pay subcontractors or suppliers. Indian River submitted a claim under the Bond for the completion of the Project. RLI Insurance denied the Bond, contending that Indian River had not complied with its contractual obligations by issuing payments to McDaniel in excess of the value of the work actually performed, or for work that was never performed, and filed this action for declaratory judgment, breach of fiduciary duty and negligent misrepresentation. RLI Insurance also asserted negligent misrepresentation claims against EDiS and Becker Morgan. Indian River filed a counterclaim against RLI Insurance for costs to correct and complete McDaniel’s scope of work.

Pursuant to Indian River’s motion for summary judgment, RLI Insurance consented to the entry of judgment in Indian River’s favor as to Counts II and III of its complaint, RLI Insurance’s claims against Indian River for breach of fiduciary duty, and negligent misrepresentation.

II. LEGAL STANDARD

In pertinent part, Rule 56(c) of the Federal Rules of Civil Procedure provides that a party is entitled to summary judgment if a court determines from its examination of “the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any,” that there are no genuine issues of material fact and that the moving party is entitled to judgment as a matter of law. Fed.R.Civ.P. 56(c). In determining whether there is a triable dispute of material fact, a court must review all of the evidence and construe all inferences in the light most favorable to the non-moving party. Valhal Corp. v. Sullivan Assocs., Inc., 44 F.3d 195, 200 (3d Cir.1995).

However, a court should not make credibility determinations or weigh the evidence. Reeves v. Sanderson Plumbing Prods., Inc., 530 U.S. 133, 150, 120 S.Ct. 2097, 147 L.Ed.2d 105 (2000).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
556 F. Supp. 2d 356, 2008 U.S. Dist. LEXIS 43303, 2008 WL 2275487, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rli-insurance-v-indian-river-school-district-ded-2008.