State v. Fidelity and Deposit Company of Maryland

194 A.2d 858, 57 Del. 24, 1963 Del. LEXIS 161
CourtSupreme Court of Delaware
DecidedOctober 23, 1963
StatusPublished
Cited by3 cases

This text of 194 A.2d 858 (State v. Fidelity and Deposit Company of Maryland) is published on Counsel Stack Legal Research, covering Supreme Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Fidelity and Deposit Company of Maryland, 194 A.2d 858, 57 Del. 24, 1963 Del. LEXIS 161 (Del. 1963).

Opinion

Terry, Chief Justice.

On or about April 18, 1958, James H. Wood, a general contractor, entered into a contract with the Board of Trustees of Delaware State College at Dover, Delaware, for certain construction work. Contemporaneous with this contract, Wood, as principal, and Fidelity and Deposit Company of Maryland, as surety, executed a labor and material payment bond in favor of the State College. In addition to containing the conditions enunciated in 29 Del. C. Sec. 69jp2, the bond contained the following provisions.

“3. No suit or action shall be commenced hereunder by any claimant,

“('a) Unless claimant shall have given written notice to any two of the following: The Principal, the Owner, or the Surety above named, within ninety (90) days after such claimant did or performed the last of the work *27 or labor or furnished the last of the material for which said claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the materials were furnished, or for whom the work or labor was done or performed. Such notice shall be served by mailing the - same by registered mail, postage prepaid, in an envelope addressed to the Principal, Owner, or Surety, at any place where an office is regularly maintained for the transaction of business, or served in the state in which the aforesaid project is located, save that such service need not be made by a public officer.”

On June 11, 1958, Wood accepted a bid submitted by plaintiff, Savery & Cooke, Inc., to furnish and erect miscellaneous iron work on the classroom and administration building. Plaintiff was not furnished a copy of the labor and material payment bond by any party. Plaintiff completed its primary obligations under its subcontract by November 25, 1959, and finishing work was completed by December 28, 1959. On April 29, 1960, plaintiff notified Wood and the architect of the default of Wood and its claim for payment; the defendant surety was notified on June 10, 1960.

When defendant surety refused to honor the claim for payment, plaintiff instituted suit in the court below. Defendant pleaded the notice provision cited above and moved for summary judgment. The lower court rejected plaintiff’s contention that the notice provision was invalid and granted the motion for summary judgment; it is from this order that plaintiff has appealed to this court.

The trial court, in addition to the decision discussed above, granted the surety’s motion for summary judgment in the action brought by plaintiff C. C. Oliphant and Son, Inc. on the labor and material payment bond. Since the facts in the Oliphant case are substantially identical to *28 those in the Savery & Cooke matter, we have consolidated both appeals for disposition by this decision. An examination of these cases indicates that the primary question raised by both appeals is the validity of the notice provision. However, the appeal of plaintiff Oliphant, in addition, presents three additional questions for consideration, which we shall first consider.

Plaintiff first contends that, assuming the validity of the notice provision, timely notice was given within the terms of this provision of the surety bond. Plaintiff’s argument is predicated upon its removal and reinstallation of an exhaust fan in April of 1960. Consequently, plaintiff argues, since notice was given to the prescribed parties within 90 days subsequent to April, 1960, plaintiff has satisfied the notice requirements of the surety bond. However, the work performed by plaintiff was not done pursuant to the contract with the general contractor, but rather was performed under the terms of a separate contract executed by plaintiff with another sub-contractor. In so performing the repair work required by the subcontractor, plaintiff admittedly was required to remove certain portions of roofing which it had installed pursuant to its contract with Wood. This removal' and replacement, however, was not work required under its general contract, but rather was work incidental to the work required by its separate contract with the subcontractor. Therefore, such work cannot be considered as ’’work or labor of [the furnishing of] the last of the material for which said claim is made,” as is required by the notice provision of the labor and material payment bond. The work was not performed pursuant to the contract guaranteed by the bond, and no claim is made against the principal for the work performed. Accordingly, the April, 1960 work does not toll the operation of the 90-day notice provision.

*29 Plaintiff’s second contention is that the invitation for bids received by its contained a proposed labor and material payment bond which did not contain the notice provision now in issue. Accordingly, plaintiff alleges that it was misled to its detriment by reliance upon the sample form contained in the invitation for bids. However, defendant, cannot be charged with responsibility for matters contained in the invitation for bids, and, absent any statutory requirements, defendant will be charged with only that liability that is expressly assumed by it in the contract of suretyship. See City of Ocala for Use of Standard Oil Co. v. Continental Casualty Company, 99 Fla. 736, 127 So. 326, 77 A.L.R. 8 (1930).

Finally, defendant, in addition to pleading the notice provision in both appeals, contends that plaintiff Oliphant is barred from recovery by virtue of the fact that plaintiff did not supply the general contractor with receipted bills. Under the terms of the prime contract, which was made applicable to subcontractors, no payment was to be made to the general contractor unless requests for payment were accompanied by receipted bills showing payment of subcontractors and material men. The evidence indicates that, despite this provision, the college authorities released monies to the general contractor without requiring these receipted bills. Specifically, the evidence indicates that plaintiff did not submit a receipted bill for the one payment which was received by it from Wood. However, no claim is made for such payment. It is obvious that plaintiff was under no obligation to give receipted bills for those claims which had not been paid, since such action would mislead both the principal and the defendant surety company. The question presented, therefore, is whether or pot the surety is discharged on its labor and material payment bond by the failure of the public authorities to insist upon *30 their contractual right for the presentment of receipted bills. In support of its contention, defendant cites Village of Chester v. Leonard, 68 Conn. 495, 37 A. 397 (1897), and Meyer v. Standard Accident Insurance Company, 114 N.J.L. 483, 177 A. 255 (1935). Both of these cases merely stand for the proposition that the owner itself may not hold the surety liable subsequent to its failure to' hold the prime contractor to its contractual obligations; these cases in no way indicate that the surety is discharged from its obligations on a labor and material payment bond.

The law is well-settled that any default by the public authorities will not discharge the surety from its obligation on the labor and material payment bond. See Des Moines Bridge & Iron Works v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

RLI Insurance v. Indian River School District
556 F. Supp. 2d 356 (D. Delaware, 2008)
State Ex Rel. Certain-Teed Products Corp. v. United Pacific Insurance
389 A.2d 777 (Superior Court of Delaware, 1978)
State Ex Rel. Christopher v. Planet Insurance Co.
321 A.2d 128 (Superior Court of Delaware, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
194 A.2d 858, 57 Del. 24, 1963 Del. LEXIS 161, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-fidelity-and-deposit-company-of-maryland-del-1963.