Meyer v. Standard Accident Insurance Co.

177 A. 255, 114 N.J.L. 483, 1935 N.J. LEXIS 261
CourtSupreme Court of New Jersey
DecidedFebruary 12, 1935
StatusPublished
Cited by10 cases

This text of 177 A. 255 (Meyer v. Standard Accident Insurance Co.) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meyer v. Standard Accident Insurance Co., 177 A. 255, 114 N.J.L. 483, 1935 N.J. LEXIS 261 (N.J. 1935).

Opinion

The opinion of the court was delivered by

Wells, J.

This is an appeal from a judgment entered in the Supreme Court for the sum of $2,760.48 and costs, upon a verdict found by the trial court sitting in the Essex Circuit without a jury, in favor of the plaintiff and against the defendant.

The case was submitted on an agreed state of facts.

Jerrold H. Meyer (hereinafter designated Meyer), the plaintiff, as owner, entered into an agreement with Philco Construction Company (hereinafter designated Philco Company) for the construction of certain buildings, for which Meyer was to pay Philco Company the sum of $55,000 in certain installments at agreed times as the work progressed; the final installment of $15,000 was not to be paid until the building was fully completed in compliance with the plans and specifications. The contract provided for advances in such payments, but provided always that in each case a certificate of the architect be produced showing the work done according to the specifications, and the final certificate of the *485 architect was not to be issued “until the contractor has furnished satisfactory evidence that there are no outstanding liens or claims for materials furnished or labor performed on any part of his work.”

The contract and specifications were duly filed in the clerk’s office of Essex county on June 3d, 1930.

Under the terms of the contract the Philco Company agreed “to obtain and furnish an indemnity bond covering the faithful performance and the completion of this contract in compliance with the plans and specifications.”

Accordingly, the Philco Company, as principal, and the appellant, Standard Accident Insurance Company (hereinafter designated as Insurance Company), as surety, entered into a written obligation with Meyer in the amount of $55,000, on the following conditions: “the said Philco Construction Company shall well and faithfully do and perform the things agreed by them to be done and performed according to the terms of said contract, and shall pay all lawful claims of subcontractors, materialmen and laborers, for labor performed and materials furnished in the carrying forward, performing or completing of said contract, we agreeing and assenting that this undertaking shall be for the benefit of any materialman or laborer having a just claim, as well as for the obligee herein.”

The contract above mentioned was specifically made a part of this bond, and the two must be read together and construed as a whole. Standard Gas Power Corporation v. New England Casually Co., 90 N. J. L. 570; Skillman v. U. S. Fidelity S Guaranty Co., 101 Id. 511.

On October 9th, 1930, the Decker Building Material Company (hereinafter designated as Decker Company) filed a stop-notice in the office of the clerk of Essex County, and two days later served a copy of the same on the plaintiff Meyer. Said notice made claim for $2,142.19 for materials furnished to the Philco Company which were used in the construction of the buildings.

The Philco Company paid Decker Company $500 on account after the .notice was served, leaving a balance duo *486 thereon of $1,642.19. Meyer, at the time of the filing of said stop-notice, had paid out to the Philco Company, or its assignees, all of the moneys due or to become due on the contract except the sum of $7,290. Before October 9th, 1930, the plaintiff had been served with and received certain orders and assignments given by the Philco Company to various subcontractors. After being served with the Decker Company stop-notice, Meyer expended the remaining sum of $7,290, without any architect’s certificate, by payment to the holders of the said assignments or orders, but did not honor or pay the claim of the Decker Company.

The Decker Company thereupon brought suit and recovered judgment against the Philco Company for the balance due on its claim, and issued execution thereon, which was returned unsatisfied.

The Decker Company also instituted suit against Meyer, who filed an answer claiming that he had expended the fund and had no moneys owing to the Philco Company.

The late Chief Justice Gummere struck out this answer, and this court on appeal affirmed the judgment entered in the Supreme Court, in an opinion reported in 109 N. J. L. 408, in which it was held that under the sixth section of the Mechanics’ Lien act a stop-notice materialman had priority over an assignee or person having an order. Mr. Justice Donges, who delivered the opinion for the court, said: “There is nothing in the proofs to show that the sums of money in question were actually due to the subcontractors assignees, but it clearly appears that the money was still for all practical purposes in the hands of the owner who could not disregard the stop-notice and pay subcontractors who had orders or assignments.”

Upon paying the judgment obtained by the Decker Company against him, Meyer brought this suit against the defendant Insurance Company as surety on the Philco Company bond to recover the amount of the judgment, with $500 expended for counsel fees. From the judgment entered in favor of Meyer, the Insurance Company appeals and sets forth eight grounds of appeal, all of which contend generally, *487 that the judgment was erroneous in the light of the stipulated facts, and specifically, that payment of the orders and assignments as against the claim of the Decker Company was an act sufficient to discharge the defendant of liability on the bond.

By the terms of the contract and bond the defendant Insurance Company became surety, up to the amount of $55,000, that the Philco Company would faithfully perform the contract and pay all just and lawful claims of subcontractors, materialmen, and laborers. The latter obligation was extended for the benefit of such materialmen and laborers. The plaintiff, Meyer, on his part, was bound to make payments on the contract according to the terms thereof, and in accordance with the existing and pertinent law, so as not to prejudice the rights of the surety in the amount of the contract price, which was the only security existent for the protection of the defendant, Insurance Company. Plaintiff, Meyer, cannot hold the defendant surety liable beyond the precise terms of the bond, strictly construed. Skillman v. U. S. Fidelity & Guaranty Co., supra.

The rights of the Decker Company against the plaintiff, ■Meyer, which by virtue of this action are of concern to the defendant Insurance Company were governed by the Mechanics’ Lien act (3 Comp. Slat., p. 3290 and amendments'), the pertinent sections being 2, 3, 5 and 6. Construction and interpretation of these sections have evolved the following rules of law applicable here.

When a building contract, with the specifications, is duly filed with the clerk of the county in which the building or land is situate, the owner is then liable to the contractor alone for the work done and materials furnished. 3 Comp. Stat., p. 3293, § 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
177 A. 255, 114 N.J.L. 483, 1935 N.J. LEXIS 261, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meyer-v-standard-accident-insurance-co-nj-1935.