Anthony P. Miller, Inc. v. Needham

35 F. Supp. 332, 1940 U.S. Dist. LEXIS 2528
CourtDistrict Court, E.D. Pennsylvania
DecidedSeptember 9, 1940
DocketCiv. No. 92
StatusPublished

This text of 35 F. Supp. 332 (Anthony P. Miller, Inc. v. Needham) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anthony P. Miller, Inc. v. Needham, 35 F. Supp. 332, 1940 U.S. Dist. LEXIS 2528 (E.D. Pa. 1940).

Opinion

KIRKPATRICK, District Judge.

This is a suit by a general contractor upon three surety bonds, given by a subcontractor, one of the defendants, with the Bonding Company, the other defendants, as surety, for damages to the plaintiff by reason of the subcontractor’s delay and inefficiency in prosecuting the work, hjs failure to complete the work, and his failure to fiay material bills in a substantial amount.

[333]*333The case was tried to the Court without a jury and, at the trial, the parties stipulated the first two items of damage to be $13,000, and have agreed to liquidate the amount of unpaid claims of materialmen after the trial, in the event that the Court finds the defendant liable. The subcontractor has not been served with process, and the sole question, therefore, is whether or not the Bonding Company is liable on the bond, and, if so, the nature and extent of its obligation.

The defenses are: First, fraud on the part of the subcontractor participated in by the plaintiff, in procuring the bond; and, second, overpayments by the contractor to the subcontractor.

Miller — it is not necessary to distinguish between Anthony P. Miller and the corporation plaintiff — had a contract with the Government for the construction of what is known as Westfield Acres Housing Project in New Jersey. Three items of the work — heat, plumbing, and outside distribution — were let to Needham by a subcontract executed September 3, 1936. Needham’s bond to Miller as obligee, with the Bonding Company as surety for the performance of the work, was executed September 22, 1936. The work was begun September 24, 1936. Needham abandoned his contract December 24, 1937.

The defense of fraud is based upon the fact that Needham, who was decidedly weak financially, arranged for what has been called euphemistically an “overnight loan” of $10,000 with the Mainland National Bank — a small country bank of which Miller was president — and included as an asset in his financial statement to the Bonding Company a cash deposit of $10,000 thereby obtained. As a matter of fact, simultaneous with his obtaining the loan, he gave his check to the Bank for the full amount, with the result that what appeared to be a deposit was never available to' him and was not a cash asset at all. The whole transaction was a pure fraud, and was an inducing cause for the defendant’s becoming surety.

However, there is not, in my judgment, sufficient evidence to connect Miller with the fraud or to establish the fact that he had knowledge of it. I am not basing this conclusion upon his denials nor upon those of Needham, nor upon the testimony of Ware, the cashier of the Bank, and I do not make the finding requested by the plaintiff that Miller did not know of or participate in the fraud. But there is no direct testimony, in evidence, that he did, and, without such testimony, the circumstances, though affording plenty of ground for suspicion, are not sufficient to constitute evidence of the fact. Needham, it is true, did make several statements, sworn and unsworn, to the effect that Miller in his presence arranged with the cashier of the Bank for the loan, but, by stipulation,' the only testimony of Needham’s received in evidence was a deposition made June 21, 1940. By reason of Needham’s physical condition this deposition was made before the official Court Reporter without counsel being present. As to his various earlier statements, the stipulation was that they might be received in evidence, but solely for the purpose of impeaching his credibility. I reject his deposition upon all controverted facts as wholly unworthy of belief, but that does not supply the evidence necessary to establish the defendant’s point. My finding, therefore, is that the defendant has failed to meet the burden of proof in respect of Miller’s knowledge of and participation in Needham’s fraud.

It is undisputed that Miller, from the beginning of the work, financed Needham through the medium of ninety-day acceptances. These trade acceptances were given by Miller from time to time, ostensibly on the basis of materials actually contracted for, in order to allow Needham to obtain trade discounts as well as to meet payrolls. It is also undisputed that as a result of advances obtained in this manner, Needham, when he quit the job on December 24, 1937, had received approximately $46,000 more than the 85% of the value of the completed work to which he was entitled under the first clause of Article XIII of his contract with Miller, and that the contractor’s retained percentage was invaded to that extent. There is a dispute as to when the over-payments began, the plaintiff contending that in the case of each trade acceptance the payment to Needham was made when Miller paid the acceptance at the Bank 90 days after it was- given. This is not a correct view of the transaction. The transaction in effect consisted in Miller borrowing the money from the Bank, advancing it to Needham, and repaying the Bank in 90 days. I therefore find that the overpayments began almost immediate* [334]*334ly after the work was started and continued until Needham left the job.

A more substantial dispute had to do with a later clause of Article XIII, which provided that the contractor might, in order to expedite the work, make payments (in addition to the regular 85% on estimates) to the subcontractor for materials prepared and ready for delivery, upon production of fire insurance policies and evidence that the materials were stored for the subcontractor. Even if this clause be stretched to support all payments made by the contractor for all labor and materials that actually went into the job, it remains undisputed that a large part of the money received by Needham on the trade acceptances was diverted from the job to other purposes. Needham puts this amount at about $17,000. The plaintiff argues that it is about $7,700. However, I accept the testimony of the defendant’s accountant upon this point and find that the amount of money which Needham received from Miller which did not go into the Westfield Project amounted to $33,788.21.

The law of New Jersey governs, and it is stated as follows in Meyer v. Standard Accident Insurance Co., 1935, 114 N.J.L. 483, 490, 177 A. 255, 259: “It is a general principle that any material alteration in a building contract will release nonconsenting sureties upon a bond given to guarantee the faithful performance of the contract, and to protect the owner against any claims or liens for labor or materials used in the construction of the building. Whether a payment made by the owner before it has become due, or in an amount larger than provided for in the contract, is such a material alteration of the contract, as to release the sureties, is a question upon which the decisions do not agree; but the great weight of authority seems to be that such payments will release the sureties, the argument being not only that the sureties are entitled to have the amounts reserved in the contract applied to the satisfaction of possible liens or claims against the building, but also that the fact that there are earned, but unpaid, moneys in the hands of the owner, will act as an incentive to the contractor to execute his contract in a faithful manner.’’

The plaintiff urges that Judge Arant in a very interesting article in the University of Pennsylvania Law Review for April, 1932, vol. 80, p. 842,1 has demonstrated that the view that overpayments by a contractor constitutes material alterations of the contract is fallacious.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meyer v. Standard Accident Insurance Co.
177 A. 255 (Supreme Court of New Jersey, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
35 F. Supp. 332, 1940 U.S. Dist. LEXIS 2528, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anthony-p-miller-inc-v-needham-paed-1940.