Suntech of Connecticut, Inc. v. Lawrence Brunoli, Inc.

72 A.3d 1113, 143 Conn. App. 581, 2013 WL 2993211, 2013 Conn. App. LEXIS 329
CourtConnecticut Appellate Court
DecidedJune 25, 2013
DocketAC 33485
StatusPublished
Cited by5 cases

This text of 72 A.3d 1113 (Suntech of Connecticut, Inc. v. Lawrence Brunoli, Inc.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Suntech of Connecticut, Inc. v. Lawrence Brunoli, Inc., 72 A.3d 1113, 143 Conn. App. 581, 2013 WL 2993211, 2013 Conn. App. LEXIS 329 (Colo. Ct. App. 2013).

Opinion

[583]*583 Opinion

BEACH, J.

The plaintiff, Suntech of Connecticut, Inc. (Suntech), appeals from the judgment of the trial court rendered in favor of the defendants, Lawrence Brunoli, Inc. (Brunoli), and Safeco Insurance Company of America (Safeco). Suntech claims the court erred in concluding that Suntech had not proven that (1) Brunoli breached its subcontract with Suntech and (2) Safeco violated General Statutes § 49-42. We affirm the judgment of the trial court.

The following facts, as found by the trial court, and procedural history are relevant to this appeal. Brunoli was the general contractor on a project known as “Renovations to Terminal A at Bradley Airport” (project). Brunoli contracted directly with the owner of the project, the Connecticut Department of Transportation (department). In April, 2005, Suntech entered into a subcontract with Brunoli under which Suntech, in connection with the project, was to construct and to install a large glass wall, known as a curtain wall, which was to form a substantial portion of the airport terminal. Under the subcontract, Suntech was to provide glass doors, glass, glazing, an aluminum framing system and a metal panel system.

There was, however, a discrepancy in the plans that the department had prepared and submitted to prospective bidders. The curtain wall appeared fourteen inches shorter in height in the structural plan than it did in the architectural plan. Under the specifications of the structural plan, the curtain wall would not have reached the roof of the building. Suntech reviewed the plans prior to making its bid and prior to entering into the subcontract with Brunoli. The bids or estimates submitted by Suntech were based, in part, on those plans; however, the discrepancy regarding the height of the curtain wall was not noticed at that time.

[584]*584After having been awarded the subcontract and having noticed the discrepancy, Suntech revised the plans for the glazed aluminum framing system (system) and provided a new shop drawing of the system to the department for its review and approval. Among other changes, the upper spans of the mullions—aluminum frames which support glass panels—were increased. The greater span of the curtain wall required a recalculation of the deflection criteria.1 The new deflection criteria, as reflected in the revised plans, required reinforced steel bars to be placed inside each mullion and required that the steel reinforcement be extended to a greater height within the mullions. This change added 44,000 pounds of steel to the mullions, and the deflection criteria were changed again after the steel reinforcement and new specifications were ultimately agreed upon.

Suntech submitted several revised cost estimates because of the changes in specifications. Brunoli approved two change orders that provided for an additional payment of $110,000. The department informed Suntech that the revised drawings for the system were not acceptable because they exceeded the maximum deflection criteria. After another series of discussions, Suntech submitted a request for a change order based on additional work and expenses. Brunoli transmitted Suntech’s request to the department, but the department rejected it.

Despite the fact that the department rejected Sun-tech’s request, Brunoli issued a change order (# 427) that authorized a payment by Brunoli itself—without payment by the department—to Suntech in the amount of $110,440. Brunoli claimed the payment was made under duress in that Suntech threatened to discontinue work on the project unless pending financial issues [585]*585were satisfactorily resolved. After the issuance of change order # 427, Brunoli pursued an appeal through the department’s contract board of review. The appeal submitted Suntech’s claim for the charges brought about by the changes in the plans. The department again rejected the submission. The project was finished more than three years after the anticipated completion date.

Suntech brought an action against Brunoli and Safeco, an insurance company that had issued a payment bond to Brunoli for the project at issue. Suntech alleged breach of contract, unjust enrichment, delay, and an action under General Statutes § 49-41a against Brunoli. Suntech alleged a violation of § 49-42 against Safeco. The court found for the defendants on the complaint.2 This appeal followed.

I

Suntech claims that the court erred in concluding that Brunoli did not breach its subcontract with Suntech. We disagree.

“The elements of a breach of contract action are the formation of an agreement, performance by one party, breach of the agreement by the other party and damages.” (Internal quotation marks omitted.) Pelletier v. Galske, 105 Conn. App. 77, 81, 936 A.2d 689 (2007), cert. denied, 285 Conn. 921, 943 A.2d 1100 (2008).

Within the context of the claims presented to us, the contract provisions at issue are clear and unambiguous; accordingly, our review of the provisions is plenary. “If a contract is unambiguous within its four comers, intent of the parties is a question of law requiring plenary review. . . . [When] the language of the contract is clear and unambiguous, the contract is to be given effect according to its terms. . . . [T]he individual clauses of [586]*586a contract . . . cannot be construed by taking them out of context and giving them an interpretation apart from the contract of which they are a part.” (Citation omitted; internal quotation marks omitted.) FCM Group, Inc. v. Miller, 300 Conn. 774, 811, 17 A.3d 40 (2011).

The subcontract provided in relevant part as follows. Suntech was to “[f]umish all materials, labor and equipment to perform work as described in the contract Drawings and special provisions, Connecticut D.O.T. standard specifications for Roads, Bridges and Incidental Construction Form 816, 2004 Addendums 1, 2, and 3. . . . Glass Doors . . . Glass & Glazing . . . Glazed Aluminum Framing System . . . Metal Panel Systems. . . . [A]s shown on Contract drawings; for the project entitled Bradley International Airport Terminal ‘A’ Renovations.”

The State of Connecticut Department of Transportation, Standard Specifications for Roads, Bridges and Incidental Construction, Form 816 (2004) (Form 816) was incorporated by reference into the subcontract. Section 1.05.01 of Form 816 provides in relevant part: “All work shall be subject to review by the Engineer. He shall decide all questions as to interpretation of the plans and specifications, and questions of mutual or respective rights of the Contractor and other Department contractors. The Engineer shall decide on an acceptable rate of progress, on the manner of performance, and what shall be deemed acceptable fulfillment of the contract.” Section 1.09.06 (1) regarding periodic payments provides in relevant part: “Once each month, the Engineer will make, in writing, current estimates of the value of work performed in accordance with the Contract, calculated at Contract unit prices, including but not limited to the value of materials complete in place and materials not yet incorporated into the Project, but approved by the Engineer for payment . . . .”

[587]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Electrical Contractors, Inc. v. 50 Morgan Hospitality Group, LLC
211 Conn. App. 724 (Connecticut Appellate Court, 2022)
Arch Ins. Co. v. Centerplan Constr. Co.
368 F. Supp. 3d 350 (D. Connecticut, 2019)
Suntech of Conn., Inc. v. Lawrence Brunoli, Inc.
164 A.3d 36 (Connecticut Appellate Court, 2017)
LM Ins. Corp. v. Connecticut Dismanteling, LLC
161 A.3d 562 (Connecticut Appellate Court, 2017)
Southhaven Associates, LLC v. McMerlin, LLC
Connecticut Appellate Court, 2015

Cite This Page — Counsel Stack

Bluebook (online)
72 A.3d 1113, 143 Conn. App. 581, 2013 WL 2993211, 2013 Conn. App. LEXIS 329, Counsel Stack Legal Research, https://law.counselstack.com/opinion/suntech-of-connecticut-inc-v-lawrence-brunoli-inc-connappct-2013.