UNIT Company

CourtArmed Services Board of Contract Appeals
DecidedFebruary 12, 2018
DocketASBCA No. 60581
StatusPublished

This text of UNIT Company (UNIT Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
UNIT Company, (asbca 2018).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) UNIT Company ) ASBCA No. 60581 ) Under Contract No. W911KB-07-D-0014 )

APPEARANCE FOR THE APPELLANT: Michael A. Brain, Esq. Law Offices of Royce & Brain Anchorage, AK

APPEARANCES FOR THE GOVERNMENT: Thomas J. Warren, Esq. Acting Engineer Chief Trial Attorney Carl F. Olson, Esq. Kyle B. Davis, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Alaska

OPINION BY ADMINISTRATIVE JUDGE NEWSOM ON THE GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT

Before the Board is the government's motion for summary judgment. Appellant, UNIT Company (UNIT), alleging defective specifications, seeks recovery of the costs incurred to design, furnish, and install piping for certain air handling and air conditioning units. In its motion, the government contends that UNIT failed to provide contractually-required notice, which failure, it asserts, bars recovery. For the reasons set forth below, we deny the motion for summary judgment.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. The government awarded Task Order 0001, under Contract No. W911KB-07-D-0014 (contract), to UNIT on 11 May 2011. 1 The task order called for the construction of a battle command training center at Joint Base Elmendorf-Richardson in Alaska, for a firm-fixed price of $20,025,555.00. (Revised R4, tab 3 at 84-86)

2. The contract incorporated Federal Acquisition Regulation (FAR) 52.236-21, SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997). The portion of this clause raised in the present motion is subsection (a), which states in relevant part:

1 In describing the facts, we draw justifiable inferences in favor of the non-moving party, as is required when ruling on a summary judgment motion. C/2 Inc., ASBCA Nos. 56257, 56337, 11-2 BCA iJ 34,823 at 171,353. In case of discrepancy in the figures, in the drawings, or in the specifications, the matter shall be promptly submitted to the Contracting Officer, who shall promptly make a determination in writing. Any adjustment by the Contractor without such a determination shall be at its own risk and expense.

(Revised R4, tab 20 at 1434, tab 23 at 5191)

3. UNIT subcontracted with Klebs Mechanical (Klebs) to perform mechanical work, including installation of air supply, distribution, ventilation, and exhaust systems. This work included installation of the air handling units (AHUs) and computer room air conditioning units (CRACs). (App. supp. R4 at 10-13; app. br., Martin aff. 112, 5)

4. The function of an AHU is to heat, cool, and filter building air. AHUs contain coils for heating or cooling. The AHU works by passing air over the coils, then pushing the heated or cooled air through ducts to the building. For this project, the AHUs contained three large coils, one for preheating, one for heating, and one for cooling. To achieve the desired temperatures in the coils, fluid was to be pumped through large-diameter supply and return pipes running from building boilers and air conditioners to the AHU coils. Piping also connected the AHUs to control assemblies in service vestibules. (App. br., Martin aff. 11 5-6)

5. The function of a CRAC is to maintain the temperature, air distribution and humidity in the network room or data center. CRACs remove hot air from these rooms. For this project, air flowed through connective piping from the CRACs to rooftop fluid coolers, which ejected the hot air outside. (App. br., Martin aff. 1 6, Klebs aff. 11 6, 9)

6. According to UNIT, the contract drawings and specifications lacked certain engineering design information that was necessary to install the AHUs and CRACs. UNIT asserts that the drawings did not show the supply and return piping for the AHUs, did not show piping detail within the service vestibules, did not show how to connect components to the coil control assemblies, did not show connections to other appurtenances, and lacked detail about piping between the CRACs and the rooftop fluid coolers. (App. br., Martin aff. 1 7, Klebs aff. 11 6, 9)

7. UNIT asserts that Klebs interpreted this lack of detail to conclude that the AHU and CRAC suppliers - and not Klebs - would supply the piping and related design engineering for the AHUs or CRACs (app. br., Klebs aff. 18). During performance, however, those vendors supplied neither the piping nor related design

2 detail, allegedly leaving Klebs without sufficient information or supplies with which to install them and ensure that they functioned properly (id. ,i,i 10-11 ).

8. As the project progressed, contractors and subcontractors could pose questions to the government by submitting a "request for information" (RFI) form. Each RFI was dated and numbered, and the government provided a written response. The RFI form stated in bold letters:

NOTE: THE RFI SYTEM IS INTENDED TO PROVIDE AN EFFICIENT MECHANISM FOR RESPONDING TO CONTRACTOR'S REQUESTS FOR INFORMATION. IT DOES NOT PROVIDE AUTHORITY TO PROCEED WITH ADDITIONAL WORK. IF THE CONTRACTOR CONSIDERS THE RFI RESPONSE A CHANGED CONDITION, PROVIDE WRITTEN NOTICE TO THE CONTRACTING OFFICER'S REPRESENATIVE IN ACCORDANCE WITH CONTRACT PROVISIONS.

(Revised R4, tab 7 at 126)

9. During 2011, 2012, and 2013, UNIT and Klebs submitted multiple RFis to the government about the AHUs and CRACs (app. br., Martin aff. ,i 4, ex. 1 at 4-26). At least some of these RF Is posed questions that appear to have concerned the AHU and CRAC piping and engineering design (app. br., Martin aff., ex. 1 at 15, 17, 25). A few examples included RFI Nos. 0227, 0234, 0354, and 0376, quoted below.

10. RFI No. 0227, dated 28 March 2012, stated:

Information Requested: There are no pipe sizes shown from CRACU-1 &2 to their corresponding dry coolers. Sheet M241 shows the pipe sizes from AC-1 &2 to their dry coolers, but there is nothing documented anywhere in the drawings showing us pipe sizes for CRACU-1&2.

The government response, dated 30 March 2012, stated in relevant part:

The CRAC system was intended to be Vendor provided for full and complete system. Note 5 in the Computer Room AC Unit Schedule indicates the need for providing a complete and functional system. The Vendor should be

3 consulted for sizing of piping based upon the pumps selected by the Vendor.

(App. br., Martin aff., ex. 1 at 15)

11. RFI No. 0234, dated 11 April 2012, stated:

There are no piping details in-the contract drawings for the preheat coils and the heating coils for AHU-1, 2, and 3. Please provide piping details for the preheat coils and the heating coils for these units.

The government responded on 23 April 2012:

Since the heating coils utilize pressure independent control valves, Detail A5/M32 l applies to their installation.

(App. br., Martin aff., ex. 1 at 17)

12. RFI No. 0353, dated 21 December 2012, stated:

AHU-1&2 may require additional unplanned work efforts including, but not limited to, condensate lines that stub out into the service vestibules. The condensate lines appear to require a p-trap below the services vestibule floor and would connect together to a main line that would run under the AHU and exit through the architectural curb. There is no design/engineering specificity for this effort.

The government responded on 11 January 2013:

This matter will be assigned to Change Item #036, and will be the subject of future correspondence.

(App. br., Martin aff., ex. 1 at 21)

13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Hoel-Steffen Construction Co. v. United States
456 F.2d 760 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
UNIT Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/unit-company-asbca-2018.