D&J Machinery, Inc.

CourtArmed Services Board of Contract Appeals
DecidedApril 19, 2022
DocketASBCA No. 62019
StatusPublished

This text of D&J Machinery, Inc. (D&J Machinery, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D&J Machinery, Inc., (asbca 2022).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - ) ) D&J Machinery, Inc. ) ASBCA No. 62019 ) Under Contract No. W912EP-15-C-0022 )

APPEARANCES FOR THE APPELLANT: Lochlin B. Samples, Esq. Jeanne M. Harrison, Esq. Karl Dix Jr., Esq. Smith, Currie & Hancock LLP Atlanta, GA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Bruce E. Groover, Esq. Codee L. McDaniel, Esq. Susan E. Symanski, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Jacksonville

OPINION BY ADMINISTRATIVE JUDGE WILSON ON APPELLANT’S MOTION FOR SUMMARY JUDGMENT AND THE GOVERNMENT’S MOTION TO STRIKE

Appellant, D&J Machinery, Inc., brings this appeal alleging that the United States Army Corps of Engineers (USACE or government) provided defective contract specifications, which then caused appellant to incur additional costs in an attempt to comply with the contract specifications. Appellant moves for summary judgment, arguing that the government breached an implied warranty that satisfactory contract performance would result from adherence to contract specifications. The government counters that the contract specifications at issue were performance specifications not design specifications, and no warranty existed. The government also moves to strike portions of appellant’s reply brief, which purportedly allege a new claim that USACE breached its duty to disclose superior knowledge related to design of the anchor block system under the above-referenced contract. Appellant counters that the government’s contention that it raised a new claim in its reply brief fails to distinguish a new argument from a new claim. For the reasons stated below, appellant’s motion is denied and as such, the government’s motion to strike is rendered moot. STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On September 18, 2015, the Army Corps of Engineers awarded Contract No.W912EP-15-C-0022 to D&J Machinery. The firm-fixed-price contract was intended to improve water deliveries and the historical natural hydrologic conditions within the Shark River Slough, through construction of control structures and a seepage canal at the Everglades National Park, Miami, Florida. (Compl. at 2; R4, tab 2 at 293-94)

2. Principal elements of this contract, as they apply to this appeal, were the construction of three gated concrete control structures, completion of seepage canal C-358, and the backfill and reconstruction of a pump station. Each control structure was to be equipped with a manually operated double leaf slide gate system, 84” diameter High Density Polyethylene (HDPE) 1 pipe with tie-down anchor blocks, handrails, an access hatch, and lightning protection system. (R4, tab 2 at 293)

3. The project was designed by the Jacksonville District, U.S. Army Corps of Engineers (R4, tab 2 at 235), with performance-based elements (see e.g., R4, tab 2 at 482, 511 § 3.1.4, 512 § 3.2.2).

4. The contract specifications include Section 03 31 01.00 10 – CAST-IN- PLACE STRUCTURAL CONCRETE FOR CIVIL WORKS. Section 1.2 – Design Requirements, which requires the contractor to “select concrete mixture proportions so that the strength and W/C requirements are met. Submit concrete mixture proportions as determined by the contractor and submitted for review.” (R4, tab 2, at 498) Section 1.3 – Submittals, requires that government approval was required for elements noted with a “G”. Concrete mixture proportions, underwater concrete methods and equipment, and cementitious materials, admixtures, and curing compound were all designated with a “G”. (R4, tab 2 at 501-02) Section 3.2.2 – Placing Concrete Underwater reiterates the requirement for approval of the methods and equipment and states, “[d]eposit concrete in water by a tremie or concrete pump” (R4, tab 2 at 512). Flowable fill is not referenced in either sections 1.3 or 3.2.2.

5. Section 03 31 01.00 10 – CAST-IN-PLACE STRUCTURAL CONCRETE FOR CIVIL WORKS, references flowable fill in Part 2 – PRODUCTS, 2.1 – Materials. Section 2.1.8 Flowable Fill states in its entirety, “[f]lowable fill shall be non-excavatable meeting FDOT standards under Section 121.” (R4, tab 2 at 507)

6. Contract drawings C-08, S-02, and S-03 reflect that HDPE pipe would be attached to each of the three control structures. The drawings also show that flowable

1 See, Terms and Abbreviations (R4, tab 3 at 671).

2 fill would be placed between and around each HDPE pipe, with required elevations for the flowable fill. (R4, tab 3 at 685, 690-91)

7. Flowable fill, as discussed in contract drawings C-8, S-02, and S-03, refer the contractor to Division 31 – EARTHWORK for guidance (R4, tab 2 at 569-79). Flowable fill is not discussed by name in Division 31 – EARTHWORK (R4, tab 3 at 569-79).

8. Flowable fill is commonly used as a substitute for earthen backfill and the contract specifications did not include guide specifications for flowable fill (app. mot. at 4-5; app. mot. at ex. A, Higgins declaration ¶¶ 16-17; ex. B, Swindle declaration ¶¶ 16-18).

9. Drawing S-01 of the contract contains structural notes on the installation of the HDPE pipes, including “due to the natural buoyancy of the HDPE culverts, the culverts shall be lowered into place with the aid of weights and by filling the pipes profile with water” (R4, tab 3 at 689). The structural notes do not otherwise describe any suggestions or guidance relating to installation or project completion.

10. Drawing S-02 is a general plan for the contract that reflects structural details for the final product. It does not reflect any specifications for the process of installation or construction of any element. (R4, tab 3 at 690)

11. On December 19, 2016, appellant submitted a request for approval, ENGForm 4025, for “Flowable Fill Concrete Mixture” with two different concrete mix design proposals, one excavatable and one non-excavatable (R4, tab 24 at 4398-400). The government replied on January 10, 2017 via ENG Form 4025-R and stated “in accordance with Contract Specification Section 03 31 01.00 10, Paragraph 2.1.8, Flowable fill shall be “non-excavatable” meeting FDOT standards under Section 121. (R4, tab 25)

12. On March 30, 2017, the government sent Serial Letter C-0029 to appellant indicating that its “representative observed that there was an apparent failure to the formwork presumably allowing flowable fill to be discharged . . . [and] requests that you provide an action plan addressing [the] proposed measures to correct the work and achieve contract compliance” (R4, tab 26).

13. An April 13, 2017 response to Serial Letter C-0029 from appellant states, among a detailed explanation of work happening to remedy the flowable fill formwork failure, that appellant’s “review of the contract plans and specifications as well as confirming direction from USACE leads us to the ultimate conclusion that the contractual requirements for the underwater placement of flow fill is defective and was

3 the primary contributing factor to the flowable fill formwork failure” (R4, tab 28 at 4405).

14. On April 17, 2017, the government responded to appellant’s Serial Letter S-013 and requested additional information regarding the flowable fill formwork failure. The government additionally noted: “the government cannot support or understand [appellant’s] allegation of concluding that ‘contractual requirements related to underwater placement of flow fill is defective and was the primary contributing factor to the flowable fill formwork failure’”. (R4, tab 29 at 4407)

15. A May 15, 2017 Request for Information Report (RFI) from appellant requested approval for installation and backfilling of the HDPE culverts with flowable fill.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
J. L. Simmons Company, Inc. v. The United States
412 F.2d 1360 (Court of Claims, 1969)
Pure Gold, Inc. v. Syntex (u.s.a.), Inc.
739 F.2d 624 (Federal Circuit, 1984)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
USA Petroleum Corporation v. The United States
821 F.2d 622 (Federal Circuit, 1987)
Stuyvesant Dredging Company v. The United States
834 F.2d 1576 (Federal Circuit, 1987)
Blake Construction Company, Inc. v. The United States
987 F.2d 743 (Federal Circuit, 1993)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
Varilease Technology Group, Inc. v. United States
289 F.3d 795 (Federal Circuit, 2002)
Ordnance Research, Inc. v. United States
609 F.2d 462 (Court of Claims, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
D&J Machinery, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/dj-machinery-inc-asbca-2022.