Stockton East Water District v. United States

62 Fed. Cl. 379, 2004 U.S. Claims LEXIS 264
CourtUnited States Court of Federal Claims
DecidedOctober 4, 2004
DocketNo. 04-541L
StatusPublished
Cited by13 cases

This text of 62 Fed. Cl. 379 (Stockton East Water District v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stockton East Water District v. United States, 62 Fed. Cl. 379, 2004 U.S. Claims LEXIS 264 (uscfc 2004).

Opinion

OPINION

CHRISTINE O.C. MILLER, Judge.

Before the court after argument is defendant’s motion to dismiss pursuant to RCFC 12(b)(1) and (6) for, respectively, lack of subject matter jurisdiction and failure to state a claim upon which relief can be granted. The pivotal issue to be decided is whether the statute of limitations, 28 U.S.C. § 2501 (2000), bars a takings claim, when the claim was timely filed in federal district court and thereafter transferred under 28 U.S.C. § 1631 (2000), but the court had ordered plaintiffs to effect transfer over ten years earlier. Defendant also objects to plaintiffs’ pleading a breach of contract, in addition to the takings claim, in the complaint filed in the Court of Federal Claims. Finally, defendant raises the law of the case doctrine to foreclose plaintiffs from relitigating any issues necessary to maintain their action in the Court of Federal Claims.

Litigation over this dispute began in 1993 with a complaint filed in the United States District Court for the Eastern District of California. Over ten years later, after 368 docket entries, that court ordered a partial transfer of the action to the Court of Federal Claims. In the interim the district court dealt with extensive motions, a number of intervening parties, consolidation of related cases, and stays — all of which involved complex legal issues of constitutional dimensions, touching on principles of federalism, and interpretation of statutes in existence for over a century. The district court’s daunting procedural and substantive embrace of this multi-party litigation, as the record of those proceedings filed by the parties evidences, affords this court the rare opportunity to acknowledge the diligence of a fellow trial judge.

The 2004 transfer of this action created a forum authorized to hear a takings claim once subject to a 1994 memorandum opinion of dismissal and order to transfer it, but nevertheless still subject to the district court’s jurisdiction. Although the transfer order no doubt rejuvenated plaintiffs’ claim, the ten-year lapse in time between the 1994 dismissal order and the 2004 transfer order gives rise to the Government’s arguments before this court.

The presentation of the factual and procedural background of this case derives from the parties’ efforts to provide the relevant orders and opinions from the federal district court action prior to transfer. Because defendant raises the law of the ease doctrine by its motion to dismiss, this court presents a separate analysis of the pertinent portions of the district court’s rulings.1

[382]*382FACTS

Plaintiffs are Stockton East Water District (“SEWD”), Central San Joaquin Water Conservation District (“Central”), San Joaquin County, City of Stockton, and California Water Service Company (“CWSC”), each of which is involved with the provision of municipal, industrial, and agricultural water, as well as the operation and maintenance of water facilities, within California’s San Joaquin Valley — -just south of Sacramento County. This ease involves a dispute over two 1983 agreements involving SEWD, Central, and the United States Bureau of Reclamation (“Reclamation”) for the appropriation of water after completion of California’s second largest earthfill dam, the New Melones Dam.

According to the Court of Federal Claims complaint entitled “Amended Complaint for Just Compensation and Breach of Contract,” filed April 20, 2004 (the “2004 Amended Complaint”)2, the New Melones Dam was part of the Central Valley Project (“CVP”), a federal reclamation project authorized by the Flood Control Acts of 1944 and 1962, Flood Control Act of Dec. 22, 1944, Pub.L. No. 78-534, § 10, 58 Stat. 887, 900-02; Flood Control Act of Oct. 23, 1962, Pub.L. No. 87-874, § 203, 76 Stat. 1173, 1191-92. See 2004 Amended Complaint 1111. Damn construction began in 1966 and was completed in 1978, while filling of the New Melones Reservoir (the “Reservoir”), which has a capacity of 2.4 million acre-feet and 100 miles of shoreline, began in 1983.

With the Flood Control Acts, Congress directed that Reclamation construct and operate the dam “pursuant to the Federal reclamation laws.” Flood Control Act of Oct. 23, 1962 § 203, 76 Stat. at 1191. The Reclamation Act of 1902, Pub.L. No. 57-161, 32 Stat. 388, also discussed in plaintiffs’ complaint, required Reclamation to apply for appropriate state permits, and the California Resources Control Board (the “SWRCB”) imposed certain restrictions of the use of the water — a decision subject to extensive litigation including review by the United States Supreme Court. See California v. United States, 438 U.S. 645, 98 S.Ct. 2985, 57 L.Ed.2d 1018 (1978).

To comply with the SWRCB’s requirements, as interpreted by the federal courts, Reclamation was required to demonstrate that it had “firm commitments” before impounding water for consumptive use. 2004 Amended Complaint 1113. To accomplish that milestone, Reclamation commenced contract negotiations with SEWD and Central. These negotiations allowed Reclamation to receive approval from the SWRCB. Id. 111113-15.

In 1983 the parties finalized their contract negotiations, and Reclamation entered into separate contracts with SEWD and Central for the provision of a certain quantity of water on an annual basis “for irrigation and domestic purposes.” 2004 Amended Complaint 111114, 16-17. The contracts required the water districts to “construct and install” at their own expense water delivery systems to carry the water from the Reservoir to the water district facilities. Id. 1118.

SEWD, relying on these contracts, contracted with CWSC, the City of Stockton, and other water districts, not parties to this litigation, to provide them with water received from the New Melones Reservoir. In exchange SEWD received assistance with the financing of the water delivery systems. The City of Stockton, CWSC, and the other water districts that are not part of this lawsuit also have undertaken construction of water delivery facilities in reliance on the Melones Contract. Plaintiffs allege that the cost of the entire delivery system exceeded $65 million.3 2004 Amended Complaint UH19-22.

According to plaintiffs, Reclamation has failed to provide water in accordance with the contracts. This defalcation is the basis for plaintiffs’ claims, now before this court, for a taking without just compensation as required by the Fifth Amendment and for breach of contract. Because the 2004 Amended Complaint pleads the breach of contract based on the allegations supporting their takings claim, the allegations of the [383]*383complaint filed by plaintiffs in 1993 in the district court become critical. See Complaint, Stockton E. Water Dist. v. United States, No. CIV-S-93-1577 DFL GGH (E.D. Cal., filed Oct. 1, 1993) (the “1993 Complaint”).

According to the 1993 Complaint, the Central Valley Project Improvement Act, Pub.L. No. 102-575, title XXXIV, 106 Stat. 4600, 4706-31 (1992) (the “CVPIA”), precipitated Reclamation’s alleged -wrongful conduct. See 1993 Complaint HH 28-39. Among other things, the CVPIA imported the requirements of the Endangered Species Act, 16 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roseberry-Andrews v. James
District of Columbia, 2018
Roseberry-Andrews v. Wilson
292 F. Supp. 3d 446 (D.C. Circuit, 2018)
Stockton East Water District v. United States
101 Fed. Cl. 352 (Federal Claims, 2011)
Brown v. United States
84 Fed. Cl. 400 (Federal Claims, 2008)
Weber v. United States
71 Fed. Cl. 717 (Federal Claims, 2006)
Dalles Irrigation District v. United States
71 Fed. Cl. 344 (Federal Claims, 2006)
International Resource Recovery, Inc. v. United States
64 Fed. Cl. 150 (Federal Claims, 2005)
Smelser v. United States
62 Fed. Cl. 768 (Federal Claims, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
62 Fed. Cl. 379, 2004 U.S. Claims LEXIS 264, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stockton-east-water-district-v-united-states-uscfc-2004.