Metric Construction Co. v. United States

83 Fed. Cl. 446, 2008 U.S. Claims LEXIS 252, 2008 WL 4165342
United States Court of Federal Claims·Decided September 3, 2008·No. No. 04-954 C·Published·Cited by 4 cases

Opinion

OPINION

BUSH, Judge.

Metric Construction Company, Inc. (Metric) seeks $138,845.35 for attorney’s fees and other litigation expenses it incurred in the subject matter. The details of the underlying case are set forth in the court’s post-trial opinion, Metric Construction Co. v. United States, 80 Fed.Cl. 178 (2008) (Metric II). Metric’s application for fees and expenses has been fully briefed by the parties, and oral argument was neither requested by the parties nor required by the court. Because the government’s position during this dispute was substantially justified, the court denies plaintiff’s application.

BACKGROUND

In 1999, Metric was awarded Contract No. DACA05-99-C-0030 (contract) to construct the Deployable Medical Systems Warehouse (warehouse) at Hill Air Force Base in Utah. Compl. at 2. When the warehouse roof developed serious leaks, the United States Army Corps of Engineers (Corps) required Metric to install a new roof. Metric’s claims before this court stemmed largely from the costs Metric incurred repairing water damage from the roof leaks, replacing damaged property in the warehouse and installing the second roof. On March 31, 2004, Metric submitted a certified claim for $2,173,091.85 to the Corps for these costs, but never received a final decision from the contracting officer.

Metric filed suit in this court on June 7, 2004, and pled three theories of entitlement to relief: breach of contract, constructive change/extra work, and breach of implied warranty. These claims survived defendant’s motion for summary judgment, primarily because of factual disputes related to the Corps’ design of structural steel underlying the roof and the issue of whether the Corps’ design specifications and communications with Metric, particularly in its response to Request for Information 173 (RFI 173), misrepresented information critical to proper roof installation. See Metric Constr. Co. v. [448]*448United States, 73 Fed.Cl. 611, 614-17 (2006) (Metric I).

Trial was held in Seattle, Washington in March 2007. The parties stipulated that Metric’s incurred costs related to the first roofs failure totaled $2,100,340. Because of the parties’ cooperation and the narrowing of relevant issues in dispute, the presentation of evidence once estimated to require eight to ten days was completed in a three day trial. Following post-trial briefing, the court awarded Metric an equitable adjustment to the contract of $1,323,214.20, plus interest. See Metric II, 80 Fed.Cl. at 196. Metric thus obtained more than half of the monetary relief it originally sought from the Corps and in this suit, and more than half of the incurred costs figure to which it stipulated at trial.

DISCUSSION

I. Overview of EAJA

The Equal Access to Justice Act (EAJA), codified at 28 U.S.C. § 2412 (2000), is a “fee-shifting” statute. Hubbard v. United States, 480 F.3d 1327, 1333 (Fed.Cir.2007). Although EAJA is a waiver of sovereign immunity that must be narrowly construed, the court must give effect to the waiver that Congress has afforded litigants against the United States. See Massie v. United States, 226 F.3d 1318, 1321 (Fed.Cir.2000) (noting that “[a]s a waiver of sovereign immunity, the EAJA is interpreted narrowly[,][b]ut this is not a talisman for permitting the government to avoid liability in all eases”) (citing Ed A. Wilson, Inc. v. Gen. Servs. Admin., 126 F.3d 1406, 1408 (Fed.Cir.1997)). “A party that prevails against the United States in a civil action is entitled, in certain circumstances, to an award of attorney’s fees, court costs, and other expenses.” Melkonyan v. Sullivan, 501 U.S. 89, 91, 111 S.Ct. 2157, 115 L.Ed.2d 78 (1991) (citing 28 U.S.C. § 2412). Certain criteria must be met by the applicant, including “timeliness of the application,” id. at 103, 111 S.Ct. 2157, not exceeding the maximum net worth for individuals or corporations, see Bazalo v. West, 150 F.3d 1380, 1384 (Fed.Cir.1998) (“The statute requires that the party seeking fees show that he is [financially] eligible to receive an award under the statute.”), and “prevailing party” status, see Rice Servs., Ltd. v. United States, 405 F.3d 1017, 1025 (Fed.Cir.2005) (noting that “to demonstrate that it is a ‘prevailing party,’ an EAJA applicant must show that it obtained an enforceable judgment on the merits or a court-ordered consent decree that materially altered the legal relationship between the parties, or the equivalent of either of those”) (citations omitted).

The United States Court of Appeals for the Federal Circuit has stated that

[t]he EAJA statute provides that a trial court must award attorney’s fees where: (i) the claimant is a “prevailing party”; (ii) the government’s position was not substantially justified; (iii) no “special circumstances make an award unjust”; and (iv) the fee application is timely submitted and supported by an itemized statement.

Libas, Ltd. v. United States, 314 F.3d 1362, 1365 (Fed.Cir.2003) (citing 28 U.S.C. § 2412(d)(1)(A)-(B); Comm’r, INS v. Jean, 496 U.S. 154, 158, 110 S.Ct. 2316, 110 L.Ed.2d 134 (1990)). As this list makes clear, the government may raise a defense, for which it bears the burden of proof, that its position in the controversy was “substantially justified.” Id. (noting that the language of § 2412(d)(1)(A) shows “that the government bears the burden of proving its position was substantially justified”) (citing Neal & Co. v. United States, 121 F.3d 683, 686 (Fed.Cir.1997)). Judicial review of this defense focuses on both “the actual merits of the government’s litigating position,” id. (citing United States v. Hallmark Constr. Co., 200 F.3d 1076, 1079-80 (7th Cir.2000)), and the actions or inaction of the government agency in its consideration of the claim giving rise to the litigation in this court, 28 U.S.C. § 2412(d)(1)(B), (d)(2)(D).

II. Timeliness, Corporate Eligibility, and Prevailing Party Status

The court issued its judgment on January 10, 2008, and Metric filed its EAJA application on March 31, 2008. Metric’s application is timely pursuant to 28 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Metric Construction Co. v. United States, 83 Fed. Cl. 446, 2008 U.S. Claims LEXIS 252, 2008 WL 4165342 (uscfc 2008).

83 Fed. Cl. 446 (Metric Construction Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Small v. United States
130 Fed. Cl. 88 (Federal Claims, 2016)
Metropolitan Van & Storage, Inc. v. United States
101 Fed. Cl. 173 (Federal Claims, 2011)