F. Alderete General Contractors Inc. v. United States

31 Cont. Cas. Fed. 72,054, 4 Cl. Ct. 482, 1984 U.S. Claims LEXIS 1505
CourtUnited States Court of Claims
DecidedJanuary 30, 1984
DocketNo. 142-83C
StatusPublished
Cited by7 cases

This text of 31 Cont. Cas. Fed. 72,054 (F. Alderete General Contractors Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
F. Alderete General Contractors Inc. v. United States, 31 Cont. Cas. Fed. 72,054, 4 Cl. Ct. 482, 1984 U.S. Claims LEXIS 1505 (cc 1984).

Opinion

OPINION

MEROW, Judge:

In this litigation plaintiff seeks to enjoin the performance by another company of a contract ^awarded by the U.S. Army Corps of Engineers in March of 1983 for the construction of the Keystone Outlet Conduit project located in El Paso, Texas. The pri- or dismissal of this case for lack of jurisdiction, 2 Cl.Ct. 184 (1983), was reversed and the matter remanded “with instructions to hear and determine Alderete’s claim for equitable relief on the merits.” F. Alderete General Contractors, Inc. v. United States, 715 F.2d 1476 (Fed.Cir.1983).

Accordingly, in compliance with the mandate of the Court of Appeals for the Federal Circuit, a trial was held in this matter in El Paso, Texas, at which time substantial documentary evidence was introduced, together with testimony from 15 witnesses comprising over 1,000 pages of transcript.

Upon the evidence of record it is concluded that plaintiff has not established a valid basis for the relief sought.

FACTS

The Keystone Outlet Conduit contract is one segment of a flood control project for the city of El Paso, Texas and vicinity. The contract requires the underground placement of 9,400 linear feet of 96" diameter concrete pipe designed to transmit water from a dam, to be constructed under another contract, to the Rio Grande River.

As originally contemplated in 1981 the Outlet Conduit contract was the initial project, to be followed by the contract for the dam. Because the Corps of Engineers then concluded that the size and complexity of the Outlet Conduit project and the specialized work involved precluded a set-aside of the procurement for a small business, in the spring of 1981 specifications were prepared for an unrestricted advertised contract. Bid opening for the conduit contract was originally scheduled for September 15, 1981.

Alderete, at all times relevant to this litigation, has been a so-called “8(a) contractor,” a corporation designated by the Small Business Administration (SBA) as a “socially and economically disadvantaged small business concern.” 15 U.S.C. § 637(a)(4), (5), (6) (section 8(a) of the Small Business Act); 13 C.F.R. § 124.1-l(c). Under the 8(a) contract program, 15 U.S.C. § 637(a)(1)(A), a federal agency contracts with SBA for the performance of required work. SBA locates a qualified small busi[484]*484ness and the terms and conditions of the contract are then negotiated. 15 U.S.C. § 637(a)(1)(C). See Ray Baillie Trash Hauling, Ine. v. Kleppe, 477 F.2d 696 (5th Cir. 1973).

Alderete had, prior to September of 1981, contacted a number of SBA and Corps of Engineers officials in an unsuccessful attempt to have the Outlet Conduit project awarded to it as an 8(a) contractor. On September 1, 1981 Alderete filed suit in the United States District Court for the Western District of Texas to enjoin the September 15, 1981 opening of bids on the Outlet Conduit project. A delay of the bid opening was ordered by agreement of the parties. The court determined that it had subject matter jurisdiction under 28 U.S.C. § 1331. On December 15, 1981, after a trial, the court entered a judgment setting aside the Corps’ decision to let the Keystone Dam Outlet Conduit project on an unrestricted basis without consideration as to whether any individual 8(a) contractor was capable of performing the work. The court also enjoined the previously scheduled bid opening and ordered that the Corps of Engineers offer the project to SBA under the 8(a) program. The judgment further provided that “the Army Corps of Engineers, its officers, agents, servants, and/or employees be, and they are hereby, ORDERED to determine the acceptability of any 8(a) contractor(s) that the Small Business Administration may propose to the Corps as qualified to perform the work required on the Keystone Dam Outlet Conduit project.”

On April 26, 1982 the Albuquerque district Corps of Engineers requested by letter that the Dallas region, Small Business Administration, advise “if you can nominate a potential 8(a) contractor for this project [Keystone Dam Outlet Conduit].” In June of 1982 F. Alderete General Contractors, Inc., after a selection evaluation, was so nominated by SBA.

Because the Outlet Conduit contract was to be negotiated, as opposed to an award on the basis of advertised bids, and was subject to the Truth in Negotiations Act, 10 U.S.C. § 2306(f), it was necessary for Alderete to prepare detailed cost and pricing data and submit a contract pricing proposal (DD Form 633). The Corps of Engineers also was required to prepare a detailed estimate of the contract cost for use by the government negotiators in reaching a fair and reasonable price in the ensuing negotiation process. Under the applicable procedures, the Corps of Engineers’ estimate was not to be disclosed to the prospective contractor. A copy of the government estimate was furnished by the Corps to SBA to assist that agency in carrying out its function of providing guidance to the nominated 8(a) contractor. SBA was, however, also precluded from disclosing the government estimate to the contractor.

Alderete’s proposal for the Outlet Conduit contract was submitted on August 31, 1982 and the government estimate was completed at the same time. Alderete’s proposal price was $5,267,557, whereas the government estimate, including profit, was $4,200,000. Alderete’s proposal was premised upon laying 6 lengths of pipe per 10-hour day, while the Corps of Engineers’ estimate was premised upon laying 8 lengths of pipe per 8-hour day. The specifications for the contract, as prepared by the Corps, allowed 500 days to perform the work and Alderete’s proposed rate of progress encompassed this period. The government estimate contemplated a somewhat shorter period of actual work time with a resulting cost savings in items such as labor, equipment rental, dewatering the site and overhead. The 500 day performance time had been carried over from the specifications for the enjoined 1981 advertised contract and, in that prior procurement, this period of time had been set forth on the assumption that funding problems and weather could extend the time needed to complete the project.

After receipt of Alderete’s proposal the Corps of Engineers prepared a technical analysis dated October 4, 1982 which concluded, in part:

[T]he Contractor’s costs appear high on judgmental items. He has used low pro[485]*485duction rates on most of the items thereby increasing all the time related costs.
* * * * * *
The contractor has proposed a production rate of 6 joints per 10-hour day. This is not considered reasonable.
* * * * * *
Therefore, the one joint per hour rate used in the Government estimate is considered reasonable and should not be reduced.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
IMS Services, Inc. v. United States
40 Cont. Cas. Fed. 76,784 (Federal Claims, 1995)
Action Manufacturing Co. v. United States
33 Cont. Cas. Fed. 74,505 (Court of Claims, 1986)
Aviation Enterprises, Inc. v. United States
32 Cont. Cas. Fed. 73,403 (Court of Claims, 1985)
Gracon Corp. v. United States
32 Cont. Cas. Fed. 73,038 (Court of Claims, 1984)
Kinetic Structures Corp. v. United States
32 Cont. Cas. Fed. 73,015 (Court of Claims, 1984)
Harris Systems International, Inc. v. United States
32 Cont. Cas. Fed. 72,486 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cont. Cas. Fed. 72,054, 4 Cl. Ct. 482, 1984 U.S. Claims LEXIS 1505, Counsel Stack Legal Research, https://law.counselstack.com/opinion/f-alderete-general-contractors-inc-v-united-states-cc-1984.