Action Manufacturing Co. v. United States

33 Cont. Cas. Fed. 74,505, 10 Cl. Ct. 474, 1986 U.S. Claims LEXIS 835
CourtUnited States Court of Claims
DecidedJuly 16, 1986
DocketNo. 402-86C
StatusPublished
Cited by7 cases

This text of 33 Cont. Cas. Fed. 74,505 (Action Manufacturing Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Action Manufacturing Co. v. United States, 33 Cont. Cas. Fed. 74,505, 10 Cl. Ct. 474, 1986 U.S. Claims LEXIS 835 (cc 1986).

Opinion

OPINION

SETO, Judge.

In this pre-award bid protest case filed pursuant to 28 U.S.C. § 1491(a)(3), plaintiff [475]*475Action Manufacturing Company (“Action”), seeks a temporary restraining order and preliminary and permanent injunctive relief to prohibit the United States Army Armament Munitions and Chemical Command (“AAMCCOM”) from awarding a contract under Request for Proposal No. DAAA09-85-0744 (“RFP”) to anyone other than Action. The underlying issue is whether the relevant actions of AAMCCOM’s procurement officials, during the negotiation process, lacked a rational or reasonable basis.

BACKGROUND

On June 24, 1986, plaintiff filed a motion for a temporary restraining order (“TRO”) and a motion for a preliminary injunction, together with a complaint, which sought a preliminary injunction enjoining defendant from awarding a contract under RFP to any offeror other than plaintiff. Plaintiff, Action Manufacturing Company, asserts that its offer was the low, responsive, responsible one and that it is entitled to an award of a contract under the RFP. On June 25, 1986, the court held a hearing on plaintiff’s motion for a temporary restraining order, at which time defendant/inter-venor, Rexon Technology Corporation, also appeared. Pursuant to this hearing, the court issued a temporary restraining order, effective for ten days, restraining defendant, acting through the U.S. Army Armament Munitions and Chemical Command, from awarding the subject RFP to any other offeror other than plaintiff until this court rules on plaintiff’s motion for a preliminary injunction. At that hearing, defendant agreed not to award said RFP to any other offeror other than plaintiff until this court renders its decision on July 16, 1986. The court alerted all parties that it would hold a hearing on the merits on July 9, 1986; combine the motion for preliminary injunction with the motion for a permanent injunction; and hear all witnesses and evidence adduced by plaintiff, defendant, and defendant/intervenor. A full-day hearing was held on July 9, 1986. At this hearing; plaintiff adduced two witnesses and six exhibits; defendant adduced two witnesses and no exhibits; and plaintiff and defendant agreed upon ten joint exhibits.

. Action is a Pennsylvania corporation located in Philadelphia, Pennsylvania. Action is in the business of manufacturing various armament and munition related items for the United States government. Defendant is the United States acting through its agent, AAMCCOM. Defendant/intervenor is Rexon Technology Corporation (“Rexon”) located in Wayne, New Jersey. Rexon is in the business of manufacturing fuzes and safety arming devices, primarily for the United States government. On August 9, 1985, AAMCCOM issued a RFP which, as originally issued, related to the acquisition of 413,058 fuze PDM 739A MPTS (fuzes) units and 51,629 S & A mod assembly, F/155 M285 (mod assembly) units. The RFP was issued and conducted pursuant to competitive negotiation and restricted procurement to only mobilization base producers.

The delivery schedule under the contract requires the first deliveries of fuzes 360 days after the award of the contract. Deliveries are to continue on a monthly basis (approximately 30,000 per month) until 690 days after award of the contract. Delivery of one-half of the mod assemblies is required 360 days after award, completion of delivery of the remaining half is to occur 390 days after award. The contract permits 240 days for the completion of the first article testing if it is required.

Clause H-13 of the RFP permits offerors to propose the use of Government Furnished Equipment (“GFE”) in the pricing of their offers requiring offerors to state whether the offer is predicated upon the use of government furnished equipment. Where the contractor intends to use GFE, it must obtain written authorization from the procuring contracting officer with responsibility for the equipment.

Clause M-6 of the RFP sets forth a detailed evaluation formula to be used in the evaluation of offers predicated upon the use of GFE. Inasmuch as offerors using GFE have lower capital expenditures [476]*476because they possess government property, a use evaluation factor is added to the unit cost of the fuzes and mod assemblies, if GFE is to be used. The use evaluation factor is intended to equalize any potential economic advantage that an offeror using GFE has over an offeror not using GFE. The use evaluation factor discussed in Clause M-6 of the solicitation is computed based on the amount of GFE that an offer- or is planning to use in the performance of the contract. This figure, however, is not developed by the government, but rather is unique to each offeror and developed by each particular offeror.

Proposals under the RFP were due to be received by September 10, 1985. Action submitted a timely proposal on September 27, 1985, which was not based on the use of GFE. Because Action did not contemplate the use of GFE, no evaluation factor was added to Action’s unit price. Action’s initial proposal was made on an “all or none” basis, meaning that the offeror would accept only a, complete award for all the quantities solicited.

After submission of proposals in September 1985, but before an award of the contract was made, the government’s requirements for fuzes and mod assemblies changed. The quantity of fuzes was increased to 456,904, and the quantity of mod assemblies was decreased to 37,416. On January 17, 1986, the contracting officer sent telegraphic messages (“TWXs”) to each of the offerors advising them of the change in quantities required under the contract and requesting each offeror to submit best and final offers (“BAFO”). The January 17, 1986 TWX contained the following language:

Request that this office be provided a written best and final offer in accordance with the terms and conditions established in the solicitation as modified by the following quantity changes ____ (Emphasis supplied.)

Action submitted its first BAFO on January 31, 1986 and confirmed that its first BAFO was in accordance with the solicitation and the telegraphic notice of changed quantities. Action’s first BAFO was not predicated on the use of GFE as no GFE evaluation factor was included. Rexon’s first BAFO, on the other hand, was based on the use of GFE and included a revised GFE evaluation factor.

The contracting officer determined that the first BAFO submitted by Rexon, which was premised on the use of GFE, was unclear to the extent that it was impossible to accurately apply the use evaluation factor. The problem centered on whether the use evaluation factor was to be applied to both items and whether the amount of the use evaluation factor was the same for both items in the solicitation. The contracting officer determined that, because of the problem with Rexon’s first BAFO, an additional round of negotiations and a second BAFO was necessary. The contracting officer further determined that the second BAFO was necessary to confirm that Action was not planning to use GFE, despite their access to it.

Following the contracting officer’s decision to issue a request for a second BAFO, the contracting specialist handling the procurement contacted both Action and Rexon by telephone on February 25, 1986 to apprise them that AAMCCOM was requesting new BAFOs due on February 28, 1986.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
Labat-Anderson, Inc. v. United States
42 Fed. Cl. 806 (Federal Claims, 1999)
Cincom Systems, Inc. v. United States
41 Cont. Cas. Fed. 77,114 (Federal Claims, 1997)
Shields Enterprises, Inc. v. United States
38 Cont. Cas. Fed. 76,526 (Federal Claims, 1993)
Logicon, Inc. v. United States
37 Cont. Cas. Fed. 76,066 (Court of Claims, 1991)
Bellevue Bus Service, Inc. v. United States
15 Cl. Ct. 131 (Court of Claims, 1988)
CACI Field Services, Inc. v. United States
34 Cont. Cas. Fed. 75,410 (Court of Claims, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 74,505, 10 Cl. Ct. 474, 1986 U.S. Claims LEXIS 835, Counsel Stack Legal Research, https://law.counselstack.com/opinion/action-manufacturing-co-v-united-states-cc-1986.