Keco Industries, Inc. v. Laird

318 F. Supp. 1361, 1970 U.S. Dist. LEXIS 9652
CourtDistrict Court, District of Columbia
DecidedNovember 2, 1970
DocketCiv. A. 2979-70
StatusPublished
Cited by26 cases

This text of 318 F. Supp. 1361 (Keco Industries, Inc. v. Laird) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keco Industries, Inc. v. Laird, 318 F. Supp. 1361, 1970 U.S. Dist. LEXIS 9652 (D.D.C. 1970).

Opinion

MEMORANDUM OPINION

GASCH, District Judge.

Plaintiff, an unsuccessful bidder on two related government supply contracts, has moved for a preliminary injunction against the Government which would require it to halt all work under the disputed contracts.

The Defense Supply Agency issued two Requests for Proposals calling for delivery of air conditioning units and associated equipment to fulfill a Marine Corps requirement. Both solicitations contemplated negotiated procurement. Negotiations closed on August 7, 1970, at 2:30 P.M. Both plaintiff and The Trane Company had submitted proposals under each solicitation. All of the proposals contained price reductions conditioned on the bidder receiving waiver of first article testing as called for in the solicitations. Offers made under RFP DSA 400-70-R-7921 were as follows:

Plaintiff Trane
First Article testing $69,600 not waived *1363 First Article testing $57,600 waived $61,163

Waiver of first article testing was granted to Trane and denied to plaintiff. In this stature, based solely on price, the contract was awarded to Trane. Offers made under RFP DSA 400-70-R-7922 were as follows:

Plaintiff Trane
First Article test- $378,550 ing not waived
First Article test- $364,750 $305,713 ing waived

Subsequently plaintiff offered a price reduction of $21,550. Whether this modification was received in time for consideration is disputed. This contract was also awarded to Trane on its proposal with first article testing waived.

Plaintiff asserts three occurrences as grounds for protesting the awards made under these proposals. First, it claims that it was entitled to waiver of first article testing. If this waiver had been granted, plaintiff would have been the low 'bidder on proposal number 7921 but would still be higher than Trane on number 7922. Next plaintiff alleges that its price reduction offer on proposal 7922 was received in time to be considered a valid modification of its offer. This reduction in price does not, however, make plaintiff the low bidder on this proposal even if it is given first article waiver. Finally, plaintiff alleges that a meeting took place between Trane and government officials after the negotiations were closed but before the contract was awarded. At this meeting the Government confirmed Trane’s technical proposal but no change in price or proposal was requested or made based on information given at this meeting.

Before discussing the merits of plaintiff’s case it will be helpful to review the rights and remedies of an unsuccessful bidder for a Government contract. Scanwell Laboratories, Inc. v. Shaffer, 137 U.S.App.D.C. 371, 424 F.2d 859 (1970), established that an unsuccessful bidder has standing to bring suit in the district court. The scope of review by the Court and the remedy to be granted are not’ at this point well defined. However, Scanwell held that the Administrative Procedure Act was applicable to these situations. Thus, the Court’s function is to review final agency action. Such action may be set aside only if it is “arbitrary, capricious, an abuse of discretion or otherwise not in accordance with law.” 5 U.S.C. § 706. Determining the proper, reviewable, final action in a Government contract case is complicated by the presence of the General Accounting Office in this field. Historically the GAO has been the forum for bid protests. However, a Comptroller General opinon on the legality of a contract is not binding on the courts, United States ex rel. Brookfield Construction Co. v. Stewart, 234 F.Supp. 94 (D.D.C.1964), and the Comptroller cannot order award or termination of a contract. Thus, a protest to the GAO is not a prerequisite to judicial review of actions of the procuring agency. See Simpson Electric Co. v. Seamans, 317 F.Supp. 684 (D.D.C. September 29, 1970, Gesell, J.).

In the instant case the authority of the GAO bears not only on the scope of review but on the appropriateness of the remedy sought. Plaintiff alleges that it will be irreparably injured if the Government is not enjoined from proceeding with the contract as awarded since its appeal to the GAO will become futile if work under the contract proceeds too far since the Comptroller normally does not interfere with ongoing contracts. An injunction pending protest to the GAO is inappropriate since this Court has jurisdiction to decide the legality of the questioned contracts. Thus, the appropriateness of injunctive relief turns, in some measure on the final relief that this Court will grant.

As mentioned above, plaintiff seeks injunction pending review by the Comptroller General, however, the ultimate relief sought is award of contract 7921 to plaintiff and setting aside of award under solicitation 7922 and reissue *1364 of that solicitation. The authority of this Court to direct the award of a contract is supported by Superior Oil Co. v. Udall, 133 U.S.App.D.C. 198, 409 F.2d 1115 (1969), where the Court of Appeals affirmed an order of the District Court compelling the Secretary of the Interior to issue a lease to a bidder whom the Court held was entitled to the contract. In appropriate circumstances the Court may also exercise its injunctive powers. But injunctive relief is discretionary and its exercise should be determined according to the circumstances of the particular case in question.

It is important to note at this point that a major premise of Scanwell was that an unsuccessful bidder was in the best position to challenge government irregularities in the contract award system established under congressional guidelines. Thus, the underlying purpose of bringing bid protests into the district court is to protect the integrity of the bid process. Most of the cases so far presented to the Courts arose out of advertised procurement. By congressional direction this is the preferred method for letting Government contracts as it insures maximum price competition with the resultant benefits accruing to the Government. Deviation from this system is allowed in certain circumstances and the agency may negotiate such purchases as was done in this case, 10 U.S.C. § 2304. But the limitation of the area where negotiation is permitted and the regulations prescribing the methods of negotiation demonstrate that the integrity of the negotiated procurement procedures should be afforded similar protection. Since procurement officials are allowed wider discretion in negotiated procurement, the standard of review will differ from that used in advertised procurement. Protection may be achieved by actions less than the directed award of the contract and preliminary injunctive relief.

The contracts in question here are, although substantial, relatively small, routine military procurement contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R & W Flammann GmbH v. United States
53 Fed. Cl. 647 (Federal Claims, 2002)
Buffalo Central Terminal v. United States
886 F. Supp. 1031 (W.D. New York, 1995)
IMS Services, Inc. v. United States
40 Cont. Cas. Fed. 76,784 (Federal Claims, 1995)
Shields Enterprises, Inc. v. United States
38 Cont. Cas. Fed. 76,526 (Federal Claims, 1993)
TRW Environmental Safety Systems, Inc. v. United States
35 Cont. Cas. Fed. 75,712 (Court of Claims, 1989)
Action Manufacturing Co. v. United States
33 Cont. Cas. Fed. 74,505 (Court of Claims, 1986)
Drexel Heritage Furnishings, Inc. v. United States
32 Cont. Cas. Fed. 73,203 (Court of Claims, 1984)
DLM & A, Inc. v. United States
32 Cont. Cas. Fed. 72,941 (Court of Claims, 1984)
B.K. Instrument, Inc. v. United States
715 F.2d 713 (Second Circuit, 1983)
DeMat Air, Inc. v. United States
30 Cont. Cas. Fed. 70,980 (Court of Claims, 1983)
Peter Kiewit Sons' Co. v. U. S. Army Corps of Engineers
534 F. Supp. 1139 (District of Columbia, 1982)
Textron, Inc., Bell Helicopter Textron Div. v. Adams
493 F. Supp. 824 (District of Columbia, 1980)
Alaska Bulk Carriers, Inc. v. Kreps
595 F.2d 814 (D.C. Circuit, 1979)
North Construction Co. v. Mayo
432 F. Supp. 725 (W.D. Michigan, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
318 F. Supp. 1361, 1970 U.S. Dist. LEXIS 9652, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keco-industries-inc-v-laird-dcd-1970.