Professional Building Concepts, Inc. v. The City of Central Falls, Professional Building Concepts, Inc. v. The City of Central Falls, Promac, Inc., Plaintiff-Intervenor

974 F.2d 1, 38 Cont. Cas. Fed. 76,395, 1992 U.S. App. LEXIS 18768
CourtCourt of Appeals for the First Circuit
DecidedAugust 14, 1992
Docket92-1313
StatusPublished

This text of 974 F.2d 1 (Professional Building Concepts, Inc. v. The City of Central Falls, Professional Building Concepts, Inc. v. The City of Central Falls, Promac, Inc., Plaintiff-Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Professional Building Concepts, Inc. v. The City of Central Falls, Professional Building Concepts, Inc. v. The City of Central Falls, Promac, Inc., Plaintiff-Intervenor, 974 F.2d 1, 38 Cont. Cas. Fed. 76,395, 1992 U.S. App. LEXIS 18768 (1st Cir. 1992).

Opinion

974 F.2d 1

38 Cont.Cas.Fed. (CCH) P 76,395

PROFESSIONAL BUILDING CONCEPTS, INC., Plaintiff, Appellant,
v.
The CITY OF CENTRAL FALLS, et al., Defendants, Appellees.
PROFESSIONAL BUILDING CONCEPTS, INC., Plaintiff, Appellee,
v.
The CITY OF CENTRAL FALLS, et al., Defendants, Appellees,
Promac, Inc., Plaintiff-Intervenor, Appellant.

Nos. 92-1313, 92-1314.

United States Court of Appeals, First Circuit.

Heard June 2, 1992.
Decided Aug. 14, 1992.

David M. Campbell with whom Girard R. Visconti and Visconti & Petrocelli Ltd., Providence, R.I., were on brief, for Professional Bldg. Concepts, Inc.

Charles S. Kirwan with whom Lovett, Schefrin, Gallogly, Harnett, Providence, R.I., was on brief, for Promac, Inc.

Michael F. Horan, Pawtucket, R.I., Everett C. Sammartino, Sr., Asst. U.S. Atty., Providence, R.I., was on brief, for City of Central Falls Housing Authority and U.S. Dept. of Housing and Urban Development.

Albert A. DiFiore with whom Beals & DiFiore, Providence, R.I., was on brief, for Maron Const. Co., Inc.

Before SELYA, Circuit Judge, RONEY,* Senior Circuit Judge, and PIERAS,** District Judge.

PER CURIAM:

Two disappointed bidders sought an injunction against the award by a public housing authority of a construction contract on two housing projects. The lowest bid was rejected because no certified check or other guarantee was submitted with the bid. Contrary to the arguments of that bidder, the district court held this was not arbitrary, capricious or in violation of law. The third lowest bidder argues the district court erred in approving the contract award on a bid that it contends was unresponsive because it contained an additional line item of cost not contemplated by the invitation to bid. We affirm.

At dispute is a contract funded by the United States Department of Housing and Urban Development (HUD) for general improvements to two housing projects in Central Falls, Rhode Island. In February 1991, the City of Central Falls Housing Authority (the Authority) issued an invitation for bids, requiring the submission of firm, fixed-price, sealed bids prior to 2:00 p.m. on March 19, 1991.

PBC's Bid

The bid invitation required submission of a bid guarantee with each bid. The bid guarantee was to be either

[a] certified check or bank draft, payable to the Central Falls Housing Authority, U.S. Government Bonds, or a satisfactory bid bond executed by the bidder and acceptable sureties in an amount equal to five percent of the bid ...

Professional Building Concepts, Inc. (PBC) submitted a non-certified corporate check. At the March 19, 1991 bid opening, the Authority and HUD officials recognized the deficiency in PBC's guarantee. After a review of HUD's manual and specifications, it was determined that the Authority could allow PBC to submit a proper security within three days. The next day, PBC substituted a certified check in the required amount for its company check. Present at the bid opening were the three lowest bidders, PBC, Maron Construction Company, Inc. (Maron), and Promac, Inc. (Promac). The minutes of the meeting indicate that no other variance in the bidding process was observed.

On March 27, the Authority determined that PBC was the low bidder. On April 4, the three lowest bidders met separately with the Authority. Following the conferences, Promac asserted that PBC had improperly contacted its subcontractors and engaged in "bid shopping." Promac's protest was subsequently rejected in an informal hearing held by the Authority on April 19.

By letter dated April 4, the Authority's architect recommended that the Authority award PBC the contract. On April 19, HUD informed the Authority by letter that it could award the contract to PBC. On April 23, Promac learned that the Authority had permitted PBC to substitute a certified check for its company check after the bid opening. Promac filed a new bid protest, contending that PBC's bid must be rejected as nonresponsive.

The Authority met on April 23 and unanimously voted to award the contract to PBC. Although the minutes of the meeting are not completely clear, it appears that the Authority voted that notice of award would not be signed until the Authority's legal counsel further reviewed the situation and issues involved.

The Authority's legal counsel later advised the Authority that, although the situation was borderline, PBC's failure to file a qualified bid guarantee was a material defect requiring rejection of its bid. The Authority rescinded its April 23 vote and elected to award the contract to Maron.

PBC brought suit challenging the award of the contract to Maron and seeking an injunction. The district court rejected PBC's claim for injunctive relief, holding that the Authority's decision to reject PBC's bid was correct and, therefore, PBC has no basis for injunctive relief 783 F.Supp. 1558.

The question in PBC's appeal is whether the submission of a corporate check, rather than a certified check as required by the invitation of bids, constitutes a material noncompliance in the bidding process.

The materiality of a bid guarantee requirement is governed by HUD procurement regulations which must be read in conjunction with the Federal Acquisition Regulations System. See 48 C.F.R. § 1.101 (1991). The Federal Acquisition Regulation (FAR) provides that, in sealed bidding, noncompliance with a solicitation requirement for a bid guarantee requires rejection of a bid, except in certain limited situations which are not applicable to this case. See RADVA Corp. v. United States, 17 Cl.Ct. 812 (1989) (quoting 48 C.F.R. § 28.101-4), aff'd, 914 F.2d 271 (Fed.Cir.1990).

No controlling cases have been called to our attention, and we have not located any interpreting FAR or HUD regulations with respect to the significance of a bid guarantee. Decisions of the Comptroller General, although not controlling, are instructive on this issue. See Keco Industries, Inc. v. Laird, 318 F.Supp. 1361, 1363 (D.D.C.1970). Beginning in 1959, the approach of the Comptroller General has been that "where an invitation for bids requires a bid to be supported by a bid guarantee and noncompliance occurs, the bid shall be rejected." To the Heads of Departments, Independent Establishments, Agencies, & Others Concerned, 38 Comp.Gen. 532 (1959); see In re Castle Floor Covering, 70 Comp.Gen. 530 (1991); In re Hudgins & Co., Inc., 56 Comp.Gen. 43 (1976). The Comptroller reasons that "the submission of a binding bid guarantee is a material condition of responsiveness with which a bid must comply at the time of bid opening." In re Castle Floor Covering, 70 Comp.Gen. 530 (1991).

The Authority could reasonably hold PBC's noncompliance was not a minor informality which could be sufficiently corrected after opening. PBC could have chosen not to comply with the bid guarantee requirement after the bid opening by stopping payment on its corporate check.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Keco Industries, Inc. v. Laird
318 F. Supp. 1361 (District of Columbia, 1970)
Radva Corp. v. United States
35 Cont. Cas. Fed. 75,706 (Court of Claims, 1989)
Excavation Construction, Inc. v. United States
494 F.2d 1289 (Court of Claims, 1974)
Wesson v. United States
782 F.2d 1074 (First Circuit, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
974 F.2d 1, 38 Cont. Cas. Fed. 76,395, 1992 U.S. App. LEXIS 18768, Counsel Stack Legal Research, https://law.counselstack.com/opinion/professional-building-concepts-inc-v-the-city-of-central-falls-ca1-1992.