Professional Building Concepts, Inc. v. City of Central Falls Housing Authority

783 F. Supp. 1558, 38 Cont. Cas. Fed. 76,381, 1992 U.S. Dist. LEXIS 2575, 1992 WL 33817
CourtDistrict Court, D. Rhode Island
DecidedFebruary 18, 1992
DocketCiv. A. 91-0263B
StatusPublished
Cited by3 cases

This text of 783 F. Supp. 1558 (Professional Building Concepts, Inc. v. City of Central Falls Housing Authority) is published on Counsel Stack Legal Research, covering District Court, D. Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Professional Building Concepts, Inc. v. City of Central Falls Housing Authority, 783 F. Supp. 1558, 38 Cont. Cas. Fed. 76,381, 1992 U.S. Dist. LEXIS 2575, 1992 WL 33817 (D.R.I. 1992).

Opinion

OPINION

FRANCIS J. BOYLE, Chief Judge.

Plaintiff Professional Building Concepts, Inc. (PBC) challenges the validity of a contract award to Marón Construction Company, Inc. (Marón) for general improvements to two elderly housing projects in the City of Central Falls. The disputed contract is funded by the United States Department of Housing and Urban Development (HUD). Professional Building Concepts filed this action after the City of Central Falls Housing Authority (Authority) had voted to award the contract to it, but the Authority subsequently rescinded that vote and awarded the contract to the next lowest bidder, Marón, because Professional Building Concepts had failed to submit a certified check with its bid. Plaintiff Inter-venor Promac, Inc. (Promac), as the third lowest bidder, argues that Maron’s bid is not for a sum certain and should be eliminated, thus, making Promac the lowest responsible bidder.

*1560 In February, 1991, the Authority issued an invitation for bids which required the submission of firm, fixed-price, sealed bids prior to 2:00 p.m. on March 19, 1991. Each bid was to be submitted as an overall bid with alternates which, if excluded, would reduce the amount of the bid. The bid invitation documents clearly required the bidders to submit a bid guarantee with each bid. The bid guarantee was to be either a “certified check or bank draft, payable to the [Authority], U.S. Government Bonds, or a satisfactory bid executed by bidder and acceptable sureties in an amount equal to five percent of the bid.” Professional Building Concepts submitted its corporate check as its bid guarantee.

At the March 19, 1991, bid opening, Authority and HUD officials recognized the deficiency in Professional Building Concepts’ bid guarantee, and after reviewing HUD’s manual and specifications, “it was determined that the Authority could allow Professional Building Concepts to submit a proper security within three days.” The next day, Professional Building Concepts substituted a certified check in the required amount, five percent of its bid, for its company check.

Present at the bid opening, were the Authority’s executive director, HUD representatives, the Authority’s Architect — Robinson, Green & Beretta, Corp. (RGB), and the three lowest bidders — Professional Building Concepts, Promac, and Marón. The minutes of the March 19, 1991, meeting indicate that the only observed variance in the bidding process was Professional Building Concepts’ submission of an uncer-tified company check as a bid guarantee.

On March 27, 1991, the Authority determined that it would exclude alternate 1 (painting), and as a result, Professional Building Concepts was the low bidder. 1 By letter dated April 4, 1991, the Authority’s architect, Robinson, Green & Beretta, Corp., recommended that the Authority award Professional Building Concepts the contract since it was the low bidder. On April 19, 1991, HUD also informed the Authority, by letter, that it could proceed to award the contract to Professional Building Concepts in the amount of $1,704,000.00 (cost of alternate 1 deducted from overall bid total of $210,000.00).

On April 4, 1991, the three lowest bidders met separately with the Authority. Promac, during its interview, gave the Authority the names of the subcontractors that it proposed to use to perform the contract. Promac asserts, and plaintiff Professional Building Concepts denies, that following the conferences it called Pro-mac’s subcontractors and adyised them that the Authority was going to delete alternate 1, and award the contract to it. Promac protested this alleged “bid shopping” to the Authority. The Authority held an informal hearing on April 19, 1991, and rejected Promac’s protest. Professional Building Concepts was neither notified of, nor did it attend this hearing. On April 23, 1991, Promac learned that the Authority had permitted Professional Building Concepts to substitute a certified check for . an uncertified company check after the bid opening. Promac immediately filed a new bid protest advising the Authority and HUD that Professional Building Concepts' bid must be rejected as nonresponsive because it failed to conform to the invitation for bid’s (IFB) guarantee requirements.

The Authority met on April 28, 1991, and unanimously voted to award the contract to Professional Building Concepts with the deletion, of alternate 1. Although the minutes of the meeting are not totally clear, it appears the Authority voted that “Notice of Award would not be signed until the Authority’s Legal Council (sic) further reviewed the situation, and issues involved.” The Authority’s legal counsel did review the situation and advised the Authority by letter dated April 30, 1991, that although a “borderline” situation, “... Professional *1561 Building Concepts’ failure to file a qualified bid guarantee, as required by the IFB, constitutes a material defect, which requires a rejection of its bid for failure to comply with a material term and condition.” Thereafter, the Authority met on May 8,1991, and rescinded its vote of April 23, 1991, and elected to award the contract to Marón.

To add to this dispute, Promac contends that Maron’s bid is also unresponsive because Marón added an extra line item to its bid document which provided for a unit price of $100.00 per square foot for concrete repair work. Promac contends that this addition rendered Maron’s bid uncertain since Marón did not include the cost of the concrete repair work in its base bid nor did it provide a basis for determining this cost. The Authority and Marón, however, agree that this addition relates to note 12 of the plans which states:

12. Inspect entire building for damaged stucco areas. Identify all areas requiring concrete repair. Repair will be accomplished under square foot unit prices, see specifications.

Additionally, section 03732, entitled “Concert Repair”, of the specification delineates how a contractor is to accomplish the required concrete repair work.

Paragraph 7 of the Authority’s Form of Bid required unit prices for “ADDITIONAL OR DEDUCTIVE WORK” from bidders with respect to “(1) the price per square foot for re-pointing additional cracks; (2) the price per square foot for repair of damaged areas of stucco finish; (3) the unit price for the removal and repair of individual bricks; and (4) the price per linear foot for the addition of new floor tile.” Of the eight bids received, only Mar-on’s bid included a fifth line item in addition to the four line items required by paragraph 7 of the IFB.

On May 8, 1991, the Authority voted to award the contract to Marón. Promac informed the Authority that it would seek judicial review of this decision. Rather than address the merits of Promac’s challenge to the responsiveness of Maron’s bid, the Authority chose to reject Promac’s challenge as being untimely filed. The Authority, however, has not adopted any formal bid protest procedures as required by the HUD regulations, nor has it provided Promac with any guidelines relating to its protest filing procedures.

Professional Building Concepts argues that the Authority improperly rejected its bid and now seeks to enjoin the award of the contract to Marón.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
783 F. Supp. 1558, 38 Cont. Cas. Fed. 76,381, 1992 U.S. Dist. LEXIS 2575, 1992 WL 33817, Counsel Stack Legal Research, https://law.counselstack.com/opinion/professional-building-concepts-inc-v-city-of-central-falls-housing-rid-1992.