H. v. Collins Company v. Tarro, 96-6585 (1997)

CourtSuperior Court of Rhode Island
DecidedJanuary 16, 1997
DocketC.A. No. 96-6585
StatusPublished

This text of H. v. Collins Company v. Tarro, 96-6585 (1997) (H. v. Collins Company v. Tarro, 96-6585 (1997)) is published on Counsel Stack Legal Research, covering Superior Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H. v. Collins Company v. Tarro, 96-6585 (1997), (R.I. Ct. App. 1997).

Opinion

DECISION
This is an action for declaratory relief arising out of the award of a municipal contract by the Barrington School Committee for the services of a construction manager for renovations and additions to the Barrington High School.

In the spring of 1996, the Barrington School Committee organized a High School Building Committee to plan an expansion and renovation of the town's high school. According to the Superintendent of Schools, Ralph A. Malafronte, deficiencies in the facilities were identified in 1990 by the New England Association of Secondary Schools and Colleges, which resulted in the school being placed on warning. Malafronte testified that unless there is "a commitment to address these facilities then Barrington could be placed in a position where we would need to show cause as to why we would not go on probation." (Malafronte depo. at 51)

Patrick A. Guida, an attorney and town resident, was elected chairperson of the seventeen-member committee. The architectural firm of Robinson, Green and Beretta was selected as the architect for the project. Numerous meetings were held with the architect to define the scope of the project. Thomas Zito, the project architect, urged the building committee to engage the services of a construction manager as opposed to retaining a contractor.

The competitive bid that forms the basis of this action was issued on October 7, 1996, in the form of a "Request for Proposal" (RFP) for Construction Management Services. This RFP was drafted by defendant Guida with input from defendant Malafronte and Mr. John Gray, the high school principal.

A preproposal conference was conducted on October 11, 1996, a tour of the facility was undertaken, and bids were due on October 23, 1996. Four prospective bidders attended the conference and subsequently submitted proposals. Those bidders were: H.V. Collins Company (Collins), the plaintiff, which submitted the lowest bid price — $654,893; Dimeo Construction Company (Dimeo), plaintiff intervenor, which submitted the second lowest bid price — $671,950; Gilbane Building Company, a defendant intervenor whose bid price was third highest — $714,750; and 0. Ahlborg, the highest bidder — $850,000 — and not a party to this action. The range in price between Collins, the lowest, and Gilbane and between Dimeo and Gilbane is considerable. Due to deficiencies in the Gilbane bid, the defendants adjusted the other bids downward, resulting in a significant percentage spread from the lowest to the highest bid.

The RFP required a submittal for "The Basic Fees to be Charged to the Various Categories for Services." Gilbane Building Company failed to submit a bid including the cost of the performance and payment bonds, liability insurance, and building permit. Plaintiffs allege this renders the bid nonresponsive and invalid. (See Infra.)

The Barrington School Committee backed out the costs submitted by Collins and Dimeo for the items omitted by Gilbane as follows:

H.V. Collins Dimeo Gilbane

Basic fee to be charged 654,893 671,950 714,750 for the services

Adjustment for Performance (79,495) (71,000) 0 Bond and Builder's Risk 575,398 600,950 714,750

After this calculation is performed, the Collins bid is 24 percent lower than Gilbane, and the Dimeo bid is 19 percent lower than Gilbane. The parties have agreed the cost of the building permit, also omitted by Gilbane, is $32,500. When this figure is subtracted from Collins and Dimeo's bid, the range is even greater:

Gilbane Collins Dimeo

714,750 542,898 568,450 32% 26%

Thus, after this calculation is complete, Gilbane's bid is almost one-third higher than the low bid, Collins, and 26 percent higher than the next lowest bid, Dimeo.

On December 19, 1996, the defendant School Committee awarded the contract to Gilbane. Neither the High School Building Committee nor the School Committee voted to reject the lower bids nor found the lower bidders to be not qualified or not responsible to perform the work. Indeed, the evidence in this case clearly discloses the lower bidders were found to be qualified, but the defendants felt that Gilbane was "superior" or "better" or "more likely" to perform well for the Town.

On December 20, 1996, Collins instituted suit. On December 23, 1996, this Court temporarily restrained the School Committee from awarding the contract. By agreement of the parties, the matter was assigned for a hearing on a preliminary injunction and, by agreement, the matter was consolidated for a hearing on the merits. Plaintiff Dimeo Construction Company, the second-lowest bidder, has intervened without objection.

At trial plaintiff Collins agreed to the dissolution of the restraining order and is now seeking a declaratory judgment declaring that the Gilbane bid was fatally defective and nonresponsive in several material respects. Collins also seeks a declaration that it is the lowest competent and lowest responsive bidder and should be awarded the contract. Finally, Collins and Dimeo allege that the RFP and the action of the Barrington School Committee in its selection of Gilbane violate section 16-2-9 of the Barrington Town Charter and the Municipal Bidding Act §45-55-1, et. seq. "Award of Municipal Contracts."

The evidence in this case consists of the testimony of defendants Guida and Malafronte and Thomas Zito, the architect. Over thirty documentary exhibits, including the depositions of these witnesses, the bid proposal (RFP), the bids of Collins, Dimeo, and Gilbane, a video tape of the December 19, 1996 meeting of the School Committee where the award was made, minutes of the meetings of the Building Committee and the School Committee were introduced and considered by the Court. The parties undertook lengthy and detailed final arguments and have provided the Court with comprehensive pretrial, posttrial and supplementary posttrial memoranda.

The Court has carefully and conscientiously reviewed this evidence and has considered the arguments of counsel in light of the existing statutes and relevant case law. The Court is well aware of the Supreme Court's "ringing admonition" in Truk Away ofRhode Island, Inc. v. Macera Brothers of Cranston, Inc.,643 A.2d 811, 816 (1994), that all Superior Court justices "exercise great care" before vacating an award of either a state or municipal contract. The Court acknowledges the heavy burden of proof imposed upon an unsuccessful bidder that "(t)he judiciary will interfere with an award only when it is shown that an officer or officers charged with the duty of making a decision has acted corruptly or in bad faith, or so unreasonably or so arbitrarily as to be guilty of a palpable abuse of discretion." GilbaneBuilding Co. v Board of Trustees of State Colleges, 107 R.I. 295,267 A.2d 396 (1970; Hajian Associates v. Board of LibraryTrustees/Building Committee, Town of Cumberland, 685 A.2d 283 (R.I. 1996).

For the reasons which follow, the Court finds that plaintiffs have sustained their burden of proof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carpet City, Inc. v. Stillwater Municipal Hospital Authority
1975 OK 75 (Supreme Court of Oklahoma, 1975)
Funderburg Builders, Inc. v. Abbeville County Memorial Hospital
467 F. Supp. 821 (D. South Carolina, 1979)
Terminal Construction Corp. v. Atlantic County Sewerage Authority
341 A.2d 327 (Supreme Court of New Jersey, 1975)
EM Watkins & Co., Inc. v. Bd. of Regents
414 So. 2d 583 (District Court of Appeal of Florida, 1982)
Bodies by Lembo v. Middlesex Cty.
669 A.2d 254 (New Jersey Superior Court App Division, 1996)
Accent Store Design, Inc. v. Marathon House, Inc.
674 A.2d 1223 (Supreme Court of Rhode Island, 1996)
In Re Award Contract Constr. of Bayonne Park
401 A.2d 705 (New Jersey Superior Court App Division, 1979)
Boydston v. Napa Sanitation District
222 Cal. App. 3d 1362 (California Court of Appeal, 1990)
ACE-MANZO v. Neptune Tp.
609 A.2d 112 (New Jersey Superior Court App Division, 1992)
Gilbane Building Co. v. Board of Trustees of State Colleges
267 A.2d 396 (Supreme Court of Rhode Island, 1970)
Truk Away of Rhode Island, Inc. v. MacEra Bros. of Cranston, Inc.
643 A.2d 811 (Supreme Court of Rhode Island, 1994)
Tp. of River Vale v. RJ Longo Const. Co.
316 A.2d 737 (New Jersey Superior Court App Division, 1974)
Kenneth E. Curran, Inc. v. Auclair Transportation, Inc.
431 A.2d 124 (Supreme Court of New Hampshire, 1981)
State, Ex Rel. Coleman v. Munger
83 N.E.2d 809 (Ohio Court of Appeals, 1948)
Nelson's Bus, Inc. v. Town of Burrillville
639 A.2d 63 (Supreme Court of Rhode Island, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
H. v. Collins Company v. Tarro, 96-6585 (1997), Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-v-collins-company-v-tarro-96-6585-1997-risuperct-1997.