Bellevue Bus Service, Inc. v. United States

15 Cl. Ct. 131, 1988 U.S. Claims LEXIS 114, 1988 WL 68793
CourtUnited States Court of Claims
DecidedJuly 6, 1988
DocketNo. 661-86C
StatusPublished
Cited by10 cases

This text of 15 Cl. Ct. 131 (Bellevue Bus Service, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bellevue Bus Service, Inc. v. United States, 15 Cl. Ct. 131, 1988 U.S. Claims LEXIS 114, 1988 WL 68793 (cc 1988).

Opinion

OPINION

BRUGGINK, Judge.

This is an action brought by an unsuccessful bidder to recover bid preparation costs. For the reasons that follow, defendant’s pending motion for summary judgment is granted and the action is dismissed.

BACKGROUND1

The claim has its genesis in a solicitation issued by the Department of the Air Force on May 3, 1985, for school bus services at Offutt Air Force Base in Nebraska. An amendment to the solicitation was issued the same day. It related to the number of buses needed and the aisle dimension of the buses. It also fixed the bid opening date as June 6, 1985. A second amendment was issued on May 20. It moved the opening date to June 19, and added a requirement for a preaward inspection:

Prior to award of this solicitation, a pre-award inspection of the apparent low bidder’s school transportation vehicles will be conducted. The inspection will be performed by officials from Offutt AFB, NE. The purpose of this inspection is to establish that the prospective contractor for school transportation service complies with or exceeds the state of Nebraska’s minimum standards governing school transportation vehicles. In the event that the preaward inspection reveals that the apparent low bidder cannot meet the established State of Nebraska criteria for the school transportation, the bidder will be declared not responsible and the bid will be rejected.

Bellevue Bus Service, Inc. (“Bellevue”) submitted a bid. At the opening, the apparent low bidder was Pony Express Cab & Bus, Inc. (“Pony Express”). Bellevue was the second low bidder. In accordance with the second amendment, Pony Express’ equipment was inspected on June 17. A report dated June 19 and prepared by the Quality Assurance Evaluator found a number of “discrepancies” that prevented the buses from meeting solicitation specifications. Pony Express was notified by letter the following day that its bid was “rejected as non-responsive.”2

With Pony Express apparently out of consideration, Bellevue became the low bidder. Its buses were inspected on June 24. Although minor discrepancies were found, they were correctible, and the overall condition of the vehicles was found to be satisfactory.

Also on June 24, however, Pony Express lodged a complaint with the Contracting Officer (“CO”). It states, in substance, that Pony Express had effectively less than one day to get ready for the inspection, that some of the alleged discrepancies were not appropriately chargeable under Nebraska law, and that remaining discrepancies could be cured. In response to the protest, the CO rescinded the decision of June 20, and notified Pony Express on July 1 that a new inspection was scheduled for July 11. On July 1, Bellevue sent a letter to defendant protesting the rescission and insisting that it should be awarded the contract.

Despite Bellevue’s protest, the reinspection of July 11 took place and resulted in [133]*133the notation of four relatively minor discrepancies. Overall, the Government found that the Pony Express buses met solicitation requirements, assuming that the discrepancies would be corrected. On July 23, 1985, Bellevue’s protest of July 1 was denied on the grounds that Pony Express had been improperly denied sufficient notice to prepare for the first inspection and that the reinspection was thus proper.

Bellevue protested the decision to permit reinspection to the General Accounting Office (“GAO”) on August 5, 1985. The protest was denied ten days later. The GAO held that the determination of Pony Express’ ability to perform concerned the bidder’s responsibility and, because evidence of a firm’s responsibility may be furnished any time prior to award, the CO could properly exercise his discretion to permit a second preaward inspection. Bellevue Bus Serv., Inc., B-219814, Aug. 15, 1985, 85-2 CPD ¶ 176, aff'd, on reconsideration, B-219814.2, Sept. 27, 1985, 85-2 CPD 11349.

The contract was awarded to Pony Express on August 20, 1985. Apparently, the Air Force was less than pleased with Pony Express’ performance. On August 23, it issued a cure notice to Pony Express referring to a “failure to provide school bus service.” It listed several discrepancies and warned that failure to cure within ten days would result in termination for default. On September 11, 1985, Pony Express was default terminated.

Because transportation had to be provided immediately for the school children, an emergency solicitation was issued. Bidders on the previous solicitation were contacted and allowed to make oral bids. One of those contacted was Bellevue. It was once again the second low bidder, however, and was thus unsuccessful. It filed another protest with the GAO. This protest was dismissed as being untimely filed. Bellevue Bus Serv., Inc., B-219814.3, Oct. 11, 1985, 85-2 CPD ¶407.

On November 11, 1986, subsequent to a transfer from the U.S. District Court for the District of Nebraska, Bellevue filed its amended complaint in this court. Defendant filed its motion for summary judgment on May 9, 1988. Plaintiff has responded and the motion is ready for disposition.

DISCUSSION

The First Award to Pony Express

Based on the circumstances described above, plaintiff asserts two claims against defendant. First, it contends that the decision to set aside the first rejection of Pony Express and to permit reinspection violated Bellevue’s rights in three respects: (1) section 303B(a) of the Competition in Contracting Act (“CICA”), 41 U.S.C. § 253b(a) (1982), mandates evaluation of bids solely on the basis of factors specified in the solicitation; (2) the reinspection violated the terms of the solicitation; and (3) defendant’s actions were arbitrary and capricious.

As this court has frequently stated, contracting officers are given wide discretion in their evaluation of bids and their application of procurement regulations. See, e.g., CACI Field Servs., Inc. v. United States, 13 Cl.Ct. 718, 725 (1987); Action. Mfg. Co. v. United States, 10 Cl.Ct. 474, 478 (1986); Electro-Methods, Inc. v. United States, 7 Cl.Ct. 755, 762 (1985). This includes the determination of a bidder’s responsibility. Venice Maid Co. v. United States, 225 Ct.Cl. 418, 431, 639 F.2d 690, 698 (1980); Keco Indus., Inc. v. United States, 203 Ct.Cl. 566, 576, 492 F.2d 1200, 1205 (1974). It is incumbent on Bellevue either to demonstrate that the decision to reinspect was irrational or unreasonable, or to show a clear and prejudicial violation of applicable statutes or regulations. Kentron Hawaii, Ltd. v. Warner, 480 F.2d 1166, 1169 (D.C.Cir.1973); Baird Corp. v. United States, 1 Cl.Ct. 662, 664 (1983).

Insofar as is relevant here, section 303B(a) was violated only if the evaluation of Pony Express’ bid was based on factors not specified in the solicitation. Clearly it was not. The evaluation was based on the minimum requirements for school buses set out in the solicitation. Furthermore, the decision to reinspect was not precluded by the terms of the solicitation. As the Comp[134]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Grunley Walsh International, LLC v. United States
78 Fed. Cl. 35 (Federal Claims, 2007)
Filtration Development Co. v. United States
60 Fed. Cl. 371 (Federal Claims, 2004)
Cybertech Group, Inc. v. United States
48 Fed. Cl. 638 (Federal Claims, 2001)
Bean Stuyvesant, L.L.C. v. United States
48 Fed. Cl. 303 (Federal Claims, 2000)
Cubic Defense Systems, Inc. v. United States
45 Fed. Cl. 239 (Federal Claims, 1999)
Metric Systems Corp. v. United States
42 Cont. Cas. Fed. 77,400 (Federal Claims, 1998)
CRC Marine Services, Inc. v. United States
42 Cont. Cas. Fed. 77,310 (Federal Claims, 1998)
Analytical & Research Technology, Inc. v. United States
42 Cont. Cas. Fed. 77,228 (Federal Claims, 1997)
Cincom Systems, Inc. v. United States
41 Cont. Cas. Fed. 77,114 (Federal Claims, 1997)
Cubic Applications, Inc. v. United States
41 Cont. Cas. Fed. 77,044 (Federal Claims, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
15 Cl. Ct. 131, 1988 U.S. Claims LEXIS 114, 1988 WL 68793, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bellevue-bus-service-inc-v-united-states-cc-1988.