Northern Helex Co. v. United States

524 F.2d 707, 21 Cont. Cas. Fed. 84,304, 207 Ct. Cl. 862, 1975 U.S. Ct. Cl. LEXIS 107
CourtUnited States Court of Claims
DecidedOctober 22, 1975
DocketNo. 454-70
StatusPublished
Cited by96 cases

This text of 524 F.2d 707 (Northern Helex Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northern Helex Co. v. United States, 524 F.2d 707, 21 Cont. Cas. Fed. 84,304, 207 Ct. Cl. 862, 1975 U.S. Ct. Cl. LEXIS 107 (cc 1975).

Opinions

Skelton, Judge,

delivered the opinion of the court:

In this case Northern Helex Company (plaintiff or Northern Helex) seeks in its second amended petition to recover [868]*868$99,964,000 from the Government as damages for a breada of contract to purchase helium. The plaintiff is a ■wholly-owned subsidiary of Northern Natural Gas Company (Northern) . The liability issue in the case was decided in favor of the plaintiff by this court in Northern Helex Co. v. United States, 197 Ct. Cl. 118, 455 F. 2d 546 (1972). In that decision we held that the failure of the Government to pay for helium delivered to it by the plaintiff as required by the contract was a material breach that justified the plaintiff in terminating the contract and for which the plaintiff has a claim for damages. We held further that the plaintiff had not waived the breach of the Government by its continued production and tender of helium to the Government both before and after suit was filed. However, we did not pass upon plaintiff’s claim for damages nor upon other issues in the case that will be discussed below. We granted plaintiff’s motion for summary judgment on liability and remanded the case to the trial judge to determine the amount of recovery, if any. A trial was held on this issue, which resulted in findings of fact and a recommended decision by the trial judge in favor of the plaintiff for the recovery of $78',012,142 as damages from the Government.1 Both the plaintiff and the defendant excepted to the trial judge’s report. The facts necessary for our decision are included in this opinion. Our task is to decide the issues left undecided in our prior opinion cited above. Most of the basic facts are set forth in that opinion, and, for the sake of clarity and continuity, are repeated below with certain omissions and additions.

The plaintiff, a wholly owned subsidiary of Northern Natural Gas Company, made a contract with the United States, acting through the Department of Interior, on August 15, 1961. This agreement was authorized by the Helium Act Amendments of 1960 (50 U.S.C. § 167, et seq.), a long-range program designed to conserve helium as a natural resource for future use. A by-product of the production of natural gas, helium was wasted daily as it escaped into the atmosphere at such a rate that the helium-bearing gas resources in the southwestern states were expected to be inadequate for national [869]*869needs by 1980-1985. Because of the unique properties of helium and the slim likelihood of finding new sources as rich as the Hugoton Area, involved here, the helium conservation program was initiated. One of its components was plaintiff’s contract.

This provided for the purchase by the United States of the helium to be produced by Northern Helex which was estimated to be 13.5 billion cubic feet over a span of years. The helium was to be extracted from Hugoton gas, delivered, and paid for each month over the 22-year contract period with an annual fiscal year limitation of $9.5 million. The unit price of $11.24 per thousand cubic feet had increased to $12.41 by the date this action was filed (in December 1970) due to automatic price adjustments envisaged by the agreement. The Government also entered into similar contracts with Cities Service Helex, National Helium Corporation, and Phillips Petroleum Company. Pursuant to its contract, Northern Helex constructed facilities, extracted, and delivered helium from December 7,1962, onward.

The helium conservation program was intended to be self-liquidating, financed with borrowing authority provided by Congress and with funds lent by the Treasury Department to Interior. The borrowed funds were to be supplemented and, within 25 to 35 years, repaid with interest from helium sales proceeds. Interior was to sell some of the helium at a price high enough to pay for the entire program and still have 40-50 billion cubic feet in storage for use after 1983. The “fedex-al market” — consisting of Government agencies, their prime contractors and subcontractors — was expected to purchase its major helium requirements from Interior and provide the basic financing for the whole program.

Unfortunately this forecast did not prove itself. The difficulty was that, from the mid-1960’s, private helium plants began to operate outside the program and to sell to Government contractors. Also, other conservation contractors produced helium in excess of the amount which could be sold to Interior under their contracts and sold the excess in competition with Interior at lower prices. Northern Helex sold helium only to Interior, but over the period of 1965-1969, some $25 million (it is said) was lost to the program because helium was purchased for federal use from other private producers [870]*870rather than the Bureau of Mines. Congress did not appropriate enough funds to satisfy the payments due under the agreements of Northern Helex and its companions in the program. By letter dated November 26, 1968, Interior informed plaintiff that the Government would be unable to make payments when they became due as of January 1969. Beginning in December 1968, and continuing through 1969 the Government failed to pay the complete amount owed. Arrearages in the monthly payments ranged from a low of $664,122 to a high of $3,235,349. For deliveries from November 1969 through November 1970, the Government paid nothing at all.

In May 1970, the Interior Department convened a meeting of the four conservation contractors in which they were told that the unit price and the maximum annual payment would have to be negotiated downward. A letter of June 24, 1970 (acknowledged June 26), from Northern Helex notified the Government that its failure to make payments was a material breach which was not being waived, but that Northern Helex was willing to discuss modifications. A draft agreement which would have increased the obligations of plaintiff while the payments to it were decreased was circulated along the lines discussed in the negotiations. Meanwhile, in his request for supplemental appropriations for fiscal year 1971, the President asked only $56,100,000 in borrowing authority for obligations under the helium contracts. This amount was not sufficient to pay outstanding debts and all anticipated deliveries for the remainder of the fiscal year but only to cover five months of operation at the present contract price and seven months at the reduced price proposed by Interior. No real progress was made during the negotiations, as Northern Helex delivered 657,008,000 cubic feet of helium from November 1,1969, through November 30, 1970, plus an additional 44,647,000 through December 24, 1970, the date of filing of the petition in this court, without receiving any payment.

In its petition, plaintiff alleged that although its contractual obligation to perform had been discharged by the Government’s material breaches of contract, it would continue to tender helium to the Government in mitigation of damages and in the interest of conservation. This was done, according [871]*871to Northern Helex, because helium extraction facilities have been interrelated with its liquefied petroleum gas and petrochemical operations in such a way that the helium facilities must be continued in operation whether helium is wasted or stored.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eden Isle Marina, Inc. v. the United States 0
113 Fed. Cl. 372 (Federal Claims, 2013)
Portland General Electric Co. v. United States
107 Fed. Cl. 633 (Federal Claims, 2012)
Scott Timber Co. v. United States
97 Fed. Cl. 685 (Federal Claims, 2011)
Stovall v. United States
94 Fed. Cl. 336 (Federal Claims, 2010)
Englewood Terrace Ltd. Partnership v. United States
94 Fed. Cl. 116 (Federal Claims, 2010)
Energy Northwest v. United States
91 Fed. Cl. 531 (Federal Claims, 2010)
Dairyland Power Cooperative v. United States
90 Fed. Cl. 615 (Federal Claims, 2009)
Mactec, Inc. v. Bechtel Jacobs Company, LLC
346 F. App'x 59 (Sixth Circuit, 2009)
Boston Edison Co. v. United States
80 Fed. Cl. 468 (Federal Claims, 2008)
System Fuels, Inc. v. United States
78 Fed. Cl. 769 (Federal Claims, 2007)
Southern Nuclear Operating Co. v. United States
77 Fed. Cl. 396 (Federal Claims, 2007)
North Star Alaska Housing Corp. v. United States
76 Fed. Cl. 158 (Federal Claims, 2007)
Pacific Gas & Electric Co. v. United States
73 Fed. Cl. 333 (Federal Claims, 2006)
Yankee Atomic Electric Co. v. United States
73 Fed. Cl. 249 (Federal Claims, 2006)
Spodek v. United States
73 Fed. Cl. 1 (Federal Claims, 2006)
Slattery v. United States
69 Fed. Cl. 573 (Federal Claims, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
524 F.2d 707, 21 Cont. Cas. Fed. 84,304, 207 Ct. Cl. 862, 1975 U.S. Ct. Cl. LEXIS 107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northern-helex-co-v-united-states-cc-1975.