Savage Industries, Inc. v. American Pulverizer Co.

103 F.3d 145, 1996 U.S. App. LEXIS 35802, 1996 WL 726889
CourtCourt of Appeals for the Tenth Circuit
DecidedDecember 18, 1996
Docket95-4159
StatusPublished

This text of 103 F.3d 145 (Savage Industries, Inc. v. American Pulverizer Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Savage Industries, Inc. v. American Pulverizer Co., 103 F.3d 145, 1996 U.S. App. LEXIS 35802, 1996 WL 726889 (10th Cir. 1996).

Opinion

103 F.3d 145

96 CJ C.A.R. 2055

NOTICE: Although citation of unpublished opinions remains unfavored, unpublished opinions may now be cited if the opinion has persuasive value on a material issue, and a copy is attached to the citing document or, if cited in oral argument, copies are furnished to the Court and all parties. See General Order of November 29, 1993, suspending 10th Cir. Rule 36.3 until December 31, 1995, or further order.

SAVAGE INDUSTRIES, INC., Plaintiff-Counter-Defendant-Appellee,
v.
AMERICAN PULVERIZER COMPANY, Defendant-Counter-Claimant-Appellant,
Chris Griesedieck, Defendant-Counter-Claimant.

No. 95-4159.

United States Court of Appeals, Tenth Circuit.

Dec. 18, 1996.

Raymond Etcheverry (William J. Stilling with him on the brief) of Parsons Behle & Latimer, Salt Lake City, Utah, for Plaintiff-Appellee.

Francis E. Pennington, III (Kenneth W. Yeates and Craig W. Dallon of Van Cott, Bagley, Cornwall & McCarthy with him on the briefs) of Dankenbring, Greiman, Osterhold & Hoffmann, P.C., St. Louis, Missouri, for Defendant-Appellant.

Before BRORBY, GODBOLD** and McWILLIAMS, Circuit Judges.

ORDER AND JUDGMENT*

BRORBY, Circuit Judge.

Savage Industries, Inc. ("Savage Industries") brought suit against American Pulverizer Company ("American Pulverizer") for negligent misrepresentation, breach of warranty, breach of contract and equitable estoppel. The district court granted summary judgment in Savage Industries' favor on the issue of American Pulverizer's liability for breach of contract, and a bench trial was held on the issue of damages. Following a two-day trial, the district court issued detailed Findings of Fact and Conclusions of Law, and entered a Judgment in favor of Savage Industries for $499,296.26. Thereafter, American Pulverizer filed a motion to amend findings and judgment, which the district court denied. American Pulverizer appeals from the district court's judgment and order denying its motion to amend findings and judgment.

I. Factual Background

In June 1991, Charles T. Main, Inc. contracted with Savage Industries for Savage Industries to build a waste coal handling system at the Sunnyside Cogeneration Project in Sunnyside, Utah. The contract required Savage Industries to provide 200 tons per hour of coal sized less than 1/4 inch to fuel the Sunnyside Cogeneration Facility.

Thereafter, American Pulverizer manufactured and sold to Savage Industries a "double roll crusher" to process waste coal as part of Savage Industries' obligation under its contract with Charles T. Main, Inc. However, the performance of the double roll crusher proved unsatisfactory when it produced a large amount of oversized material which could not be used as fuel for the Sunnyside Cogeneration Facility. In an attempt to solve the problem with the crusher, Savage Industries and American Pulverizer entered into an August 1993 agreement which contemplated installation of a newly designed system--a "Closed Loop System."1

Not long after entering the August 1993 agreement, the parties realized the Closed Loop System would not provide sufficient output to enable Savage Industries to meet its obligation to Charles T. Main, Inc. Consequently, in October 1993, Savage Industries and American Pulverizer executed a contract which provided for the installation of the "Zeigler System" instead of the Closed Loop System.2 The October 1993 contract required American Pulverizer to "[r]efurbish the Double Roll Crusher to meet OEM standards and specifications on or before November 8, 1993." It also required American Pulverizer to furnish all equipment for the Zeigler System, including the conveyor which would recirculate oversized material back into the system for crushing.3

Three days after entering the October 1993 agreement, American Pulverizer notified Savage Industries it was not financially able to perform its obligations under the contract. Although American Pulverizer's sales engineer subsequently installed newly machined roll segments on the double roll crusher, American Pulverizer never refurbished the double roll crusher as the contract required.

In order to satisfy its contractual obligation to Charles T. Main, Inc., Savage Industries searched for an economical crusher to replace the double roll crusher in the Zeigler system. Ultimately, Savage Industries purchased a Canica vertical impact crusher which met the output requirements for the Sunnyside Facility, and did so at the lowest cost possible by requiring fewer new conveyors and screens than the Zeigler System.4

From February 1994 until May 1994, while modifications were being made to accommodate the new Canica crusher, Savage Industries rented a different, temporary crusher from Canica to meet the fuel requirements at the Sunnyside Facility. Savage Industries installed the permanent Canica crusher in May 1994.

Although the Zeigler System contemplated a closed loop system, whereby oversized product would be recirculated back through the system, Savage Industries initially elected, due to cost concerns, not to install a CV-111 conveyor to "close the loop" on the Canica system. Instead, oversized material was removed by conveyor to a stockpile area for reclamation by a front-end loader. In order to handle the growing stockpile of oversized material, Savage Industries employed additional workers, operated a second front-end loader, and operated its loaders two shifts instead of one. Savage Industries had not purchased a CV-111 conveyor as of the time of trial; however, Savage Industries received capital fund approval for the conveyor in June 1995.

II. Issues Raised on Appeal

This case was tried before the district court, sitting without a jury, in June 1995. Following a two-day trial, the district court entered its Findings of Fact and Conclusions of Law, awarding Savage Industries damages in the amount of $499,296.26. Included in the district court's damages award is the sum of $62,330.00 for the CV-111 conveyor which Savage Industries had not purchased as of the date of trial.5 Also included in the court's damages award is $116,484.93 for additional operating expenses incurred by Savage Industries between November 9, 1993, and the end of May 1994. On appeal, American Pulverizer contests the damages awarded for the CV-111 conveyor and additional operating expense.

Specifically, American Pulverizer's appeal raises three issues: (1) whether the district court erroneously applied Utah law in awarding $62,330.00 to Savage Industries for the CV-111 conveyer; (2) whether the $62,330.00 award for the CV-111 conveyor is supported by sufficient evidence; and (3) whether the $116,484.93 award for additional operating expenses is supported by sufficient evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

P. L. Saddler v. United States
287 F.2d 411 (Court of Claims, 1961)
Edo Corporation v. Beech Aircraft Corporation
911 F.2d 1447 (Tenth Circuit, 1990)
Highland Construction Co. v. Union Pacific Railroad
683 P.2d 1042 (Utah Supreme Court, 1984)
Interior Elevator Co. v. Limmeroth
565 P.2d 1074 (Oregon Supreme Court, 1977)
Mann & Parker Lumber Co. v. Wel-Dri
579 F.2d 973 (Sixth Circuit, 1978)
Chaparral Resources, Inc. v. Monsanto Co.
849 F.2d 1286 (Tenth Circuit, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
103 F.3d 145, 1996 U.S. App. LEXIS 35802, 1996 WL 726889, Counsel Stack Legal Research, https://law.counselstack.com/opinion/savage-industries-inc-v-american-pulverizer-co-ca10-1996.