Cure v. City of Jefferson

380 S.W.2d 305, 1964 Mo. LEXIS 694
CourtSupreme Court of Missouri
DecidedJuly 13, 1964
Docket50305
StatusPublished
Cited by49 cases

This text of 380 S.W.2d 305 (Cure v. City of Jefferson) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cure v. City of Jefferson, 380 S.W.2d 305, 1964 Mo. LEXIS 694 (Mo. 1964).

Opinion

*306 WELBORN, Commissioner.

This is an action by the general contractors under a contract with the City of Jefferson for the contruction of a municipally owned parking facility. The petition sought recovery from the City of $62,-898.94 for the removal of rock in the excavation for the project. The architects for the facility were originally named party defendants. The trial court sustained a motion for summary judgment made by each defendant. The contractors have appealed from the judgment in favor of the City. No appeal was taken from the judgment in favor of the architects. We have jurisdiction of the appeal because of the amount in controversy.

The petition alleged that the plaintiffs, a partnership, entered into a contract, in June, 1961, with the defendant City for the construction of a parking garage for a base contract amount of $301,730.64, plus a unit price for general rock excavation and hand excavated pier rock in excess of 300 cubic feet at $2.00 per cubic foot; that the plaintiffs excavated 31,449.47 cubic feet of rock and, on October 17, 1961, submitted to the City their statement for payment in the amount of $62,989.94, which the City refused to pay. A copy of the contract between the plaintiffs and the City was incorporated by reference in the plaintiffs’ petition.

The defendant City by its answer admitted the execution of the contract, but denied generally the allegations of plaintiffs’ petition. The City also denied liability on the grounds of failure of plaintiffs to comply with provisions of the contract relating to the procedure to be followed before making a claim for extra compensation over and above the base bid and general contract sum.

After the deposition of plaintiff Cure had been taken, the City filed its motion for summary judgment, based upon the provisions of the contract as set out in the plaintiffs’ petition and statements of Cure on his deposition. The motion relied specifically upon the following provisions of the contract documents: (1) Article 3 of the basic agreement (AIA Standard Form of Agreement Between Contractor and Owner for Construction of Buildings), which read as follows:

“ARTICLE 3. THE CONTRACT SUM. The Owner shall pay the Contractor for the performance of the Contract, subject to additions and deductions provided therein, in current funds as follows: Three Hundred One Thousand Seven Hundred Thirty and 64/100 Dollars ($301,730.64), which amount has been determined as set forth in summary of costs determining the General Contract sum and attached hereto as Exhibit A; said summary being in turn determined from the bid of the General Contractor, alternates and fee for management and administration of Mechanical and Electrical Contracts, based on bid dated May 18, 1961 (attached hereto), and the following bids of Sub-Contractors, alternates, and other requirements (also attached hereto), as follows:
“Natkin & Co. — Combined bid on Bleating, Ventilating & Snow Melting and Plumbing & Drainage
“Stokes Electric Co., Inc. — Electric Work.”

(2) Section 5 of the Specifications relating to excavation, backfilling and filling (incorporated by reference as a part of the contract), which provided as follows:

“6. ITEMS OF WORK
“a) Remove existing earth, existing footings and all other items required to be removed.
“b) Do all necessary rough grading . for floors, walks, drives, etc.
*307 “c) Include removal of 300 cubic feet of rock as a part of the base bid for excavation, backfilling and filling.
“2. (e) Material to be excavated is assumed to be earth and materials that can be removed by power shovel. If rock (as defined below) is encountered, the contract amount shall be adjusted in accordance with unit prices. ROCK shall be interpreted to mean stone, boulders, or concrete that cannot be removed by a power shovel ¡J4 cu. yd. capacity, without the use of explosives or drills. No blasting shall be done without written consent of the Owner.”

(3) The following provision of the bid form submitted by plaintiffs, likewise incorporated by reference as part of the contract:

“UNIT PRICES
“1. Excavation. Backfilling, Filling & Grading — Section 5
“a) Unit price for excavation of:
“1. Common by machine $ 1.00 per cu. yd.
“2. Common by hand $10.00 per cu. yd.
“b) Unit Price for excavation of:
“1. Rock excavation of more than 300 cu. ft.
$2.00 per cu. ft.
“2. Rock excavation of less than 300 cu. ft.
$3.00 per cu. ft.”

(4) Articles IS and 16 of the General Conditions of the Contract (AIA Standard Form), which read as follows:

“ARTICLE 15. CHANGES IN WORK. The owner, without invalidating the contract, may order extra work or make changes by altering, adding to or deducting from the work, the contract sum being adjusted accordingly. All such work shall be executed under the conditions of the original contract except that any claim for extension of time caused thereby shall be adjusted at the time of ordering such change.
“In giving instructions, the architect shall have authority to malee minor changes in the work, not involving extra cost, and not inconsistent with the purposes of the building, but otherwise, except in an emergency endangering life or property, no extra work or change shall be made unless in pursuance of a written order from the owner signed or countersigned by the architect, or a written order from the architect stating that the owner has authorized the extra work or change, no claim for an addition to the contract sum shall be valid unless so ordered.
“The value of any such extra work or change shall be determined in one or more of the following ways:
“a) By estimate and acceptance in a lump sum.
“b) By unit prices named in the contract or subsequently agreed upon.
“c) By cost and percentage or by cost and a fixed fee.
“If none of the above methods is agreed upon, the contractor provided he receives an order as above, shall proceed with the work. In such case and also under case (c), he shall keep and present in such form as the architect may direct, a correct account of the cost, together with vouchers. In any case, the architect shall certify to the amount, including reasonable allow- *308 anee for overhead and profit, due to the contractor. Pending final determination of value, payments on account of changes shall be made on the architect's certificate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shocklee v. Albers Chiropractic Health Ctr., P.C.
558 S.W.3d 83 (Missouri Court of Appeals, 2018)
Good Hope Missionary Baptist Church v. St. Louis Alarm Monitoring Co.
306 S.W.3d 185 (Missouri Court of Appeals, 2010)
Osage Water Co. v. GOLDEN GLADE LAND OWNERS ASSOCIATION, INC.
270 S.W.3d 459 (Missouri Court of Appeals, 2008)
Ogg v. Mediacom, L.L.C.
142 S.W.3d 801 (Missouri Court of Appeals, 2004)
Hartzler v. Wiley
277 F. Supp. 2d 1114 (D. Kansas, 2003)
Meco Systems, Inc. v. Dancing Bear Entertainment, Inc.
948 S.W.2d 185 (Missouri Court of Appeals, 1997)
Peltzman v. Beachner
900 S.W.2d 677 (Missouri Court of Appeals, 1995)
Monsanto Co. v. International Insurance Co.
652 A.2d 36 (Supreme Court of Delaware, 1994)
ITT Commercial Finance Corp. v. Mid-America Marine Supply Corp.
854 S.W.2d 371 (Supreme Court of Missouri, 1993)
Tri-State Osteopathic Hospital Ass'n v. Blakeley
848 S.W.2d 571 (Missouri Court of Appeals, 1993)
Jake C. Byers, Inc. v. J.B.C. Investments
834 S.W.2d 806 (Missouri Court of Appeals, 1992)
Mattes v. Black & Veatch
828 S.W.2d 903 (Missouri Court of Appeals, 1992)
Schelle v. Mercantile Bancorporation, Inc.
741 S.W.2d 720 (Missouri Court of Appeals, 1987)
Koontz v. Lee
737 S.W.2d 766 (Missouri Court of Appeals, 1987)
Associated Producers Co. v. City of Independence
665 F. Supp. 755 (W.D. Missouri, 1987)
Krigel v. Federal Insurance Co.
724 S.W.2d 620 (Missouri Court of Appeals, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
380 S.W.2d 305, 1964 Mo. LEXIS 694, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cure-v-city-of-jefferson-mo-1964.