Cure v. City of Jefferson

396 S.W.2d 727, 1965 Mo. LEXIS 627
CourtSupreme Court of Missouri
DecidedDecember 13, 1965
DocketNo. 51312
StatusPublished
Cited by1 cases

This text of 396 S.W.2d 727 (Cure v. City of Jefferson) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cure v. City of Jefferson, 396 S.W.2d 727, 1965 Mo. LEXIS 627 (Mo. 1965).

Opinions

WELBORN, Commissioner.

This is an action by the general contractors under a contract with the City of Jefferson for the construction of a parking facility. The petition sought $62,898.96 for removal of rock in excavation for the project. A judgment in favor of the city upon its motion for summary judgment was reversed by this court for the reason that the cause was not properly determinable under such procedure. 380 S.W.2d 305. On remand, trial before a jury was held and, at the close of plaintiffs’ case, the court sustained the city’s mo[728]*728tion for a directed verdict. After the contractors’ motion for new trial had been overruled, this appeal was taken.

As upon the prior appeal, the problem presented is whether or not, under the contract with the city, the contractors were entitled to be compensated at unit prices specified in the contract for the removal of rock or whether recovery should be denied for failure of the contractors to give notice to the city of such work in accordance with terms of the contract dealing with “changes in the work” and “claims for extra cost.”

The contract (on “(t)he Standard Form of Agreement Between Contractor and Owner for Construction of Buildings Issued by The American Institute of Architects for use when a Stipulated Sum Forms the Basis of Payment”) was for a lump sum of $301,730.64 “subject to additions and deductions provided therein.”

The specifications for excavation, incorporated by reference in the final contract, called for bidders to “include removal of 300 cubic feet of rock as a part of the base bid * * *.” The specifications further stated: “Material to be excavated is assumed to be earth and materials that can be removed by power shovel. If rock * * * is encountered, the contract amount shall be adjusted in accordance with unit prices * * *.” The bid form submitted by plaintiffs, likewise incorporated in the final contract, fixed a unit price of $2.00 per cubic foot for rock excavation of more than 300 cubic feet and $3.00 per cubic foot for less than 300 cubic feet. The contractors rely primarily on these provisions.

The city, on the other hand, contends that recovery is barred because the contractors failed to comply with the “General Conditions of the Contract” dealing with changes in the work and claims for extra cost. Article IS of the printed A. I. A. Standard Form of “General Conditions of the Contract” gave the city the right to order extra work or to make changes, but any such work involving extra cost required a written order “from the Owner signed or countersigned by the Architect, or a written order from the Architect stating that the Owner has authorized the extra work or change, and no claim for an addition to the contract sum shall be valid unless so ordered ■* *

Article IS also provided: “Should conditions encountered below the surface of the ground be at variance with the conditions indicated by the drawings and specifications the contract sum shall be equitably adjusted upon claim by either party made within [S days] after the first observance of the conditions.”

Article 16 provided: “If the Contractor claims that any instructions by drawings or otherwise involve extra cost under this contract, he shall give the Architect written notice thereof within [5 days] after the receipt of such instructions, and in any event before proceeding to execute the work, * * * and the procedure shall then be as provided for changes in the work. No claim shall be valid unless so made.”

Our reversal upon the previous appeal of the summary judgment in favor of the city was based upon the premise that the contract, considered as a whole, was not so clear and unambiguous that failure on the part of the contractors to comply with Articles 15 and 16 precluded, as a matter of law, recovery by the contractors. Our view was that whether or not the rock excavation in excess of 300 cubic yards was a “change in the work” or whether or not the contractors’ claim was a “claim for * * * extra cost” within the meaning of the contract could not be determined without resort to extrinsic evidence.

It is our conclusion that the evidence adduced by plaintiffs demonstrated the inconsistencies and ambiguities of the contract documents which we anticipated upon the prior appeal. According to plaintiff Cure, he examined the core drillings made at the construction site and incorporated [729]*729in the specifications and concluded that excavation to the levels required' by the plans would obviously involve the removal of more than 300 cubic feet of rock. Other contractors testifying on behalf of plaintiffs testified that they reached the same conclusion. Cure testified that he did not, however, before submitting his bid, endeavor to estimate the exact amount of rock which might be expected. As directed by the specifications, he accepted the arbitrary assumption that 300 cubic feet of rock were to be removed, submitted his bid on such basis and relied upon his unit price quotation to take care of rock removal in excess of 300 cubic feet. The fact that the contract was on a printed A. I. A. form for a “stipulated sum” contract would not, contrary to the contention of the city, make such an assumption on the part of the contractors contrary to the terms of the contract documents. The contract expressly provided that the contract price was “subject to the additions and deductions provided therein.” The provisions of the specifications for compensation for rock removal at unit prices certainly could reasonably be considered an addition provided by the contract.

Further evidence that the formal printed contract contemplated adjustment of the contract sum by unit price application appears from the printed language of Article 3, relating to the contract sum, and reading, in addition to the language above referred to as follows: “Where the quantities originally contemplated are so changed that application of the agreed unit price to the quantity of work performed is shown to create a hardship to the Owner or the Contractor, there shall be an equitable adjustment of the Contract to prevent such hardship.”

The specifications did state that the material to be excavated was “assumed to be earth that can be removed by power shovel.” However, plaintiffs’ testimony showed that such assumption was contrary to the facts revealed by the site drillings, a part of the specifications. The fact that inclusion of removal of 300 cubic feet of rock was directed to be made in the bid and that unit prices were required to be fixed for rock removal might well indicate that the city’s architects who prepared the specifications were aware that rock would be encountered at the site.

Plaintiff Cure testified that, when work on the project was undertaken, the overburden on the site was removed, revealing rock consistently with the drilling report, except that at one test hole, the drilling report showed rock at a level 12 inches lower than that encountered by plaintiffs. By means of a level, elevations were shot as the rock was removed and plaintiffs’ calculation of the volume of rock removal was based upon their records so compiled. Plaintiffs introduced testimony that the material removed was rock within the meaning of the specifications.

The contractors admitted that no effort was made to obtain a written order from the city authorizing removal of rock in excess of 300 cubic feet.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Klein v. Puritan Fashions, Inc.
439 S.W.2d 229 (Missouri Court of Appeals, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
396 S.W.2d 727, 1965 Mo. LEXIS 627, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cure-v-city-of-jefferson-mo-1965.