REM Construction v. Wheatland Union High School Dist. CA3

CourtCalifornia Court of Appeal
DecidedMarch 24, 2026
DocketC100232
StatusUnpublished

This text of REM Construction v. Wheatland Union High School Dist. CA3 (REM Construction v. Wheatland Union High School Dist. CA3) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
REM Construction v. Wheatland Union High School Dist. CA3, (Cal. Ct. App. 2026).

Opinion

Filed 3/24/26 REM Construction v. Wheatland Union High School Dist. CA3 NOT TO BE PUBLISHED California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA THIRD APPELLATE DISTRICT (Yuba) ----

REM CONSTRUCTION, INC., C100232

Plaintiff and Respondent, (Super. Ct. No. CVCV21- 00847) v.

WHEATLAND UNION HIGH SCHOOL DISTRICT,

Defendant and Appellant.

REM Construction, Inc. (REM), sued Wheatland Union High School District (the District) for breach of a public works contract to modernize a high school. REM alleged it performed all work required under the contract, but the District failed to pay it the full contract price. Following a week-long bench trial, the trial court entered judgment in favor of REM. The District appeals, arguing that REM’s lawsuit is barred because it failed to comply with all steps of the contract’s claim resolution process, and compliance with that process is a condition precedent to litigation. In particular, the District argues (1) REM’s claim was untimely, and (2) even if it was timely, REM did not complete the

1 final step of the claim resolution process, namely, mediation. The trial court rejected the District’s arguments, finding the claim was timely and that any failure to mediate was the District’s fault. We agree and thus affirm. THE RELEVANT CONTRACT PROVISIONS Because it is the focus of this appeal, we begin with a description of the relevant contract provisions—specifically, section 25 of the contract governing “Claims.”1 A “Claim” is defined as a “separate demand by Contractor . . . for one or more of the following”: (1) “A time extension, including . . . for relief from damages or penalties for delay assessed by District under this Agreement”; (2) “Payment by the District of money . . . arising from work done by . . . Contractor pursuant to the Agreement and payment for

1 Many of the relevant contract provisions are identical to provisions in Public Contract Code section 9204, which creates a claim resolution process for public works projects in order to ensure that contractors are “paid in full and in a timely manner” for work “that is complete and not in dispute.” (Pub. Contract Code, § 9204, subd. (a).) Section 9204 provides “a public entity may prescribe reasonable . . . claim[] and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth in this section.” (Id., subd. (f).) As potentially relevant here, sections 25.4, 25.7.2, and 25.9 of the parties’ contract contain “procedures and requirements in addition to the provisions of” Public Contract Code section 9204. The District cites section 9204 but fails to demonstrate that it affects any of our conclusions in this case. We note that whether we are interpreting the parties’ contract or the identical provisions of section 9204, our review is de novo. (See Filtzer v. Ernst (2022) 79 Cal.App.5th 579, 583 [“de novo standard of review” applies where no extrinsic evidence was admitted concerning the contract’s meaning]; Michaels v. State Personnel Bd. (2022) 76 Cal.App.5th 560, 567 [“questions of statutory interpretation are subject to the de novo standard of review”].) We also note the District drafted the contract, and any contract provisions that do not appear in section 9204 are subject to the “ ‘ “well established rule of construction” that any ambiguities must be construed against’ the drafter, where the uncertainty cannot be resolved by other rules of contract interpretation.” (Breathe Southern California v. American Lung Assn. (2023) 88 Cal.App.5th 1172, 1182.)

2 which is not otherwise expressly provided or to which the claimant is not otherwise entitled”; and (3) “Payment of an amount that is disputed by the District.” The contract provides, “Compliance with . . . the claim submission procedures described in this Claims section is an express condition precedent to Contractor’s right to commence litigation . . . . The Contractor cannot . . . assert or bring any Claim in any . . . subsequent legal action until that Claim has gone through the Claims Resolution Process herein.” It also provides, “The procedures and provisions of this Claims section shall not apply to [¶] . . . District’s determination of . . . whether the Work complies with the Contract Documents for purposes of accepting the Work.” The claim resolution process begins with the contractor’s submission or presentation of a written claim, which must be done “within ten (10) calendar days from the date Contractor discovers or reasonably should discover, that an act, error, or omission of District, its agents or employees, or action, condition or other situation has occurred that may entitle Contractor to file a Claim.” Upon receipt of a claim, the District shall review it and provide a written response within 45 days (or longer in certain circumstances) identifying what portion of the claim is disputed and what portion is undisputed, and it shall pay any undisputed portion of the claim within 60 days. If the contactor disputes the District’s response to the claim, it “may demand in writing an informal conference to meet and confer for settlement of the issues in dispute.” Upon receipt of such a demand, the District “shall schedule a meet and confer conference within 30 days for settlement of the dispute.” “Within 10 business days following the conclusion of the meet and confer conference, if the Claim or any portion of the Claim remains in dispute, the District shall provide the Contractor a written statement identifying the portion of the Claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the Claim shall be processed and made within 60 days after the District issues its written statement.”

3 Finally, “Any disputed portion of the Claim, as identified by the contractor in writing, shall be submitted to nonbinding mediation . . . . If mediation is unsuccessful, the parts of the Claim remaining in dispute shall be subject to applicable procedures outside this section.” The District acknowledges that “applicable procedures outside this section” includes litigation. The contract also provides, “Failure by the District to . . . meet the time requirements” of the claim resolution process “shall result in the Claim being deemed rejected in its entirety.” FACTUAL AND PROCEDURAL BACKGROUND As the sole issue on appeal is whether REM’s lawsuit is barred by its failure to comply with the contract’s claim resolution process, our description of the factual and procedural background focuses on things that are relevant to that issue.2 Additional facts and evidence are described in the relevant discussion section, below. Background Relevant to the District’s Arguments on Appeal REM entered into a written contract with the District to modernize 40 classrooms at a high school for a total price of approximately $2.98 million. REM completed the bulk of the work during the summer of 2019, and the District took possession of the classrooms in August and classes began as scheduled. However, REM continued to work on “punch list” items for several months. A punch list is a list of items that remain to be completed or corrected, and it is prepared by the project’s architect as the project nears completion. As found by the trial court, “The contractor fixes items on the punch list, there is re-inspection, possibly a new punch list, more fixing and so on until the District determines all items are complete.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mainieri v. Magnuson
272 P.2d 557 (California Court of Appeal, 1954)
Platt Pacific, Inc. v. Andelson
862 P.2d 158 (California Supreme Court, 1993)
Weeshoff Construction Co. v. Los Angeles County Flood Control District
88 Cal. App. 3d 579 (California Court of Appeal, 1979)
Sosin v. Richardson
210 Cal. App. 2d 258 (California Court of Appeal, 1962)
Segal v. Silberstein
67 Cal. Rptr. 3d 426 (California Court of Appeal, 2007)
Roth v. Parker
57 Cal. App. 4th 542 (California Court of Appeal, 1997)
Pedro v. City of Los Angeles
229 Cal. App. 4th 87 (California Court of Appeal, 2014)
Alki Partners, LP v. DB Fund Services, LLC
4 Cal. App. 5th 574 (California Court of Appeal, 2016)
Powell v. Tagami
236 Cal. Rptr. 3d 765 (California Court of Appeals, 5th District, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
REM Construction v. Wheatland Union High School Dist. CA3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rem-construction-v-wheatland-union-high-school-dist-ca3-calctapp-2026.