Ace Design & Construction v. MAA Palm Desert Hospitality CA4/1

CourtCalifornia Court of Appeal
DecidedMarch 30, 2026
DocketD085989
StatusUnpublished

This text of Ace Design & Construction v. MAA Palm Desert Hospitality CA4/1 (Ace Design & Construction v. MAA Palm Desert Hospitality CA4/1) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ace Design & Construction v. MAA Palm Desert Hospitality CA4/1, (Cal. Ct. App. 2026).

Opinion

Filed 3/30/26 Ace Design & Construction v. MAA Palm Desert Hospitality CA4/1 NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

COURT OF APPEAL, FOURTH APPELLATE DISTRICT

DIVISION ONE

STATE OF CALIFORNIA

ACE DESIGN & CONSTRUCTION, D085989 INC.,

Plaintiff and Respondent, (Super. Ct. No. PSC1908271) v.

MAA PALM DESERT HOSPITALITY, INC.,

Defendant and Appellant.

APPEAL from a judgment of the Superior Court of Riverside County, Kira L. Klatchko, Judge. Affirmed. Artiano Shinoff, Daniel R. Shinoff and Maurice A. Bumbu for Defendant and Appellant. Braun & Melucci and Kerri M. Melucci for Plaintiff and Respondent. I. INTRODUCTION The trial court confirmed an arbitration award in favor of Ace Design & Construction, Inc. (Ace) and against MAA Palm Desert Hospitality, Inc. (MAA). MAA appealed from the ensuing judgment, arguing the arbitrator misinterpreted the parties’ contract and failed to analyze offsetting damages. Finding these claims insufficient to vacate the arbitration award, we affirm. II. BACKGROUND MAA owns the Springhill Suites by Marriott in Palm Desert. After a fire damaged the hotel in 2014, MAA hired Ace to reconstruct the property. MAA and Ace executed an American Institute of Architects’ form titled “Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price” (Contract). The terms of the Contract spanned several documents, including an additional American Institute of Architects’ form called “General Conditions of the Contract for Construction” (General Conditions). The guaranteed maximum price under the Contract was $5,159,503, “subject to additions and deductions by Change Order.” Change orders had to be in writing and signed by the parties. Exhibit F to the Contract listed the agreed upon values for different aspects of work included in the project. Some of these values were identified as “allowances.” Allowances were included in the guaranteed maximum price, and the General Conditions specified that “whenever costs are more than or less than allowances, the [guaranteed maximum price] shall be adjusted accordingly by Change Order.” The parties signed the construction contract in July 2016. During construction, disputes arose between Ace and MAA concerning the scope of the work, delay, and payment. In 2019, Ace sued MAA seeking $859,835.42 in damages for unpaid construction work. In 2022, the parties agreed to

2 submit their dispute to binding arbitration, at which the arbitrator was to

apply California law.1 The arbitration hearing occurred over eight days between July 2023 and November 2023. Ace submitted an itemized summary of damages in which it sought a total of $2,688,255.08. That figure was based on $600,000 in lost profits, several other categories of damages and prejudgment interest totaling $1,878,496.06, and $209,759.02 in attorney fees. The arbitrator issued a “Final Arbitration Award” on March 21, 2024. Finding Ace’s lost profits claim unproven, the arbitrator awarded Ace $1,375,679.11 in damages and interest and $120,285 in attorney fees. The arbitrator also determined that MAA was liable for all arbitration fees, which included $26,850 advanced by Ace. MAA filed a motion for reconsideration on various grounds, including that the arbitrator failed to consider any offset in damages. In response, on May 3, 2024, the arbitrator issued a “Final Arbitration Award (As Amended)” which did not change the award but expanded on the arbitrator’s reasoning. The amended award stated the Contract’s “maximum price was specified as $5,159,503.00 but that was subject to ‘allowances.’ ” The amended award identified “three major areas of contention,” starting with “Contract Percentage of Completion.” In that section, the arbitrator noted that MAA estimated Ace completed 50 to 60 percent of the project, while Ace asserted its completion percentage was 70 to 80 percent. The arbitrator described how he “painstakingly reviewed . . . every piece of paper that was submitted by the parties” and made a “seventy-four page[]” chronology detailing the evolution of the project. Based on this chronology

1 By that time, the dispute included Kalthia Group Hotels, Inc., and Harco National Insurance Company but they are not parties to this appeal. 3 and other evidence submitted, “the Arbitrator determined which of the [parties’] numerous estimated percentages of completion was most likely correct.” As for MAA’s claimed expenditures after Ace left the project, the arbitrator determined that MAA “did not present evidence of what work was done or how much of it could have been attributed to the scope covered by [Ace’s] contract and thereby reduced the percentage of contract work [Ace] had completed.” The next area of contention addressed in the amended award was under the heading “Change Orders.” There the arbitrator addressed “Change Orders submitted by [Ace that] were neither signed nor paid by MAA.” The arbitrator noted that the Contract “included a detailed Change Order process,” but compliance with that process was excused for several reasons: the process “was neither followed nor insisted upon,” some change orders were required by third parties, and other change orders involved matters that were not in the original plans. The arbitrator also explained that he “reviewed each item in each disputed Change Order individually, determined if an item was or was not an allowance item and, to the extent it was an allowance item, whether the change exceeded the allowed amount, either in a single Change Order or collectively in multiple Change Orders.” The final highly contested area was construction delay. The arbitrator found that the plans for the project contained inaccuracies, the work was significantly delayed by third parties, and MAA did not rebut Ace’s summary of delays that showed no fault by Ace. Shortly after the arbitrator issued the amended award, Ace sought to confirm it in the trial court. MAA opposed that petition and filed its own petition to correct or vacate the award on several grounds. As is relevant to this appeal, MAA claimed the arbitrator erred by stating the Contract’s

4 maximum guaranteed price “ ‘was subject to “allowances” ’ ” and by failing to consider a damages offset. The trial court granted Ace’s petition and rejected MAA’s claims for correcting and vacating the award with one exception. The trial court found the arbitrator improperly allocated all arbitration fees to MAA because the arbitration agreement required Ace to bear half of those costs. The trial court entered judgment in Ace’s favor, from which MAA appealed. III. DISCUSSION MAA argues the arbitrator erred on two grounds. First, MAA asserts the arbitrator committed misconduct and exceeded his powers by incorrectly stating that the Contract’s guaranteed maximum price “ ‘was subject to allowances.’ ” Based on that statement, MAA presumes the arbitrator interpreted the Contract as permitting allowance amounts to be exceeded without a change order. MAA claims this violated both California law and the Contract because allowances were included in the guaranteed maximum price and could only be altered by a signed change order. Second, MAA contends the arbitrator exceeded his powers by failing to analyze whether Ace’s damages should have been offset because Ace did not complete the project. MAA asserts this was a disputed issue requiring resolution and the arbitrator failed to address it. As we explain below, neither ground warrants vacating the arbitrator’s award. A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weeshoff Construction Co. v. Los Angeles County Flood Control District
88 Cal. App. 3d 579 (California Court of Appeal, 1979)
Taheri Law Group, APC v. Sorokurs
176 Cal. App. 4th 956 (California Court of Appeal, 2009)
Cable Connection, Inc. v. DirecTV, Inc.
190 P.3d 586 (California Supreme Court, 2008)
Emerald Aero, LLC v. Kaplan
9 Cal. App. 5th 1125 (California Court of Appeal, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Ace Design & Construction v. MAA Palm Desert Hospitality CA4/1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ace-design-construction-v-maa-palm-desert-hospitality-ca41-calctapp-2026.