Smith v. Empire Sanitary District

273 P.2d 37, 127 Cal. App. 2d 63, 1954 Cal. App. LEXIS 1301
CourtCalifornia Court of Appeal
DecidedAugust 4, 1954
DocketCiv. 8335
StatusPublished
Cited by8 cases

This text of 273 P.2d 37 (Smith v. Empire Sanitary District) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Empire Sanitary District, 273 P.2d 37, 127 Cal. App. 2d 63, 1954 Cal. App. LEXIS 1301 (Cal. Ct. App. 1954).

Opinion

VAN DYKE, P. J.

This is an appeal from a money judgment against appellant in the sum of $11,587. The judgment also denied relief sought by appellant by cross-complaint. The action arouse out of a construction contract entered into between appellant district, as owner, and respondent, as contractor. Respondent, Manual Smith, filed action, alleging that the district had breached its contract with him. The subject matter of the contract was the construction of a sanitary sewer in the town of Empire. It was admitted in the pleadings that a contract had been executed; that respondent had commenced the performance thereof in May of 1949 and had continued such performance through May, June and into July. Respondent alleged that he had performed services and supplied labor and furnished material in the sum of $49,281.94; that he had not been paid that portion of the amounts earned as fixed by the terms of the contract and that for such breach he was compelled to and rightfully did cease work. The contract contained the following provision:

“ (a) Not later than the 15th day of each calendar month the Owner will make a partial payment to the Contractor on the basis of a duly certified and approved estimate of the work performed during the preceding calendar month under this Contract, but to insure the proper performance of this Contract, the Owner will retain ten (10) percent of the amount of each estimate until final completion and acceptance of all work covered by this Contract: . . .
*65 “(b) In preparing estimates, the material delivered on the site and preparatory work done may be taken into consideration.”

The controversy revolves around charges by the contractor that the owner through its engineer arbitrarily withheld progress payments due and that this withholding was motivated by bad faith of the district and its engineer, both of whom the respondent claimed embarked at once upon a course of conduct designed to run the contractor off the job.

The court found that while he was on the job the contractor furnished materials and rendered services to the district of the reasonable value of $28,969.55; that he had received payments totaling $17,382.18, and that the balance of $11,587.37 was owing and unpaid; that the district’s engineer prepared estimates of the work performed while it was going forward and was fully cognizant of the reasonable value thereof; that by the 15th of July, 1949, the sum of $23,175.65 was due, owing and payable from the district to the contractor and that this sum amounted to 90 per cent of the labor and materials which had been furnished by respondent on the job during May and June; that the appellant, acting through its engineer, had arbitrarily neglected and refused to certify the proper amounts for payment as provided by the contract and that appellant had knowingly withheld from the respondent greater amounts than authorized by the contract; that these excessive withholdings were made because the appellant had been without adequate funds to pay respondent the sums which were justly due him; that on June 22d respondent was paid $7,998.90 on account of work done during May; that on July 13th respondent was paid $9,883.28 on account of work done during June; that during those two months respondent performed work and furnished materials to the value of $25,493.21 and was entitled to be paid on account thereof $23,175,65, whereas he received in fact only $17,382.18, leaving a deficit of $5,793.47 due him at the end of those two months, after the making of just allowance for rightful withholdings; that on or about July 15th respondent had properly demanded payment of the sums so due and unpaid and that payment thereof had been refused; that by reason of such breach respondent had been prevented from continuing his work or completing the job and was now entitled to all sums withheld from the total earned; that respondent had given notice to appellant that unless the sums justly due were paid he would consider the contract breached and cease work; that he did *66 cease work during July and that on September 1st he demanded the payment of all sums earned. The court made findings adverse to appellant’s claims that it had paid to respondent all sums justly due and that it was he who had breached the contract by leaving the job. The court specifically found that appellant and its engineer and other authorized representatives had been guilty of acts of carelessness, negligence, arbitrary decisions and unreasonableness which forced the respondent to leave the work; that appellant had arbitrarily withheld amounts in excess of those which the contract permitted to be withheld and so breached the agree.ment and justified respondent ceasing his performance. Judgment was rendered as hereinabove stated and from the judgment this appeal is taken.

Primarily, this appeal presents the question of substantial support for the court’s factual findings above recited. The trial was lengthy, the documentary evidence received was voluminous, the testimony of the witnesses was grossly conflicting and the situation was shown to be one where from the very beginning the parties became antagonistic. In his first certificate, dated June 22d and covering the work of May, the engineer stated that labor and materials had been furnished to the total value of $13,331.50. He authorized payment of $7,998.90, which was 60 per cent of the stated value and his explanation was “Retention of 40% is recommended in lieu of incomplete work and clean-up not being made.” Respondent considered that this retention of 40 per cent was unjustified. He said, however, he considered the estimates of work done to be sufficiently accurate for progress payment purposes and made no formal protest, expecting the matter would be adjusted when the next payment was made. On July 13th the engineer made his second certificate, stating that the value of work and materials furnished during June amounted to $15,638.05 and he recommended payment of 60 per cent thereof amounting to $9,383.28, with the explanation that “Retention of 40% is recommended in lieu of incomplete work and clean-up not being made.” We have said that the engineer stated the values for the work of May and June. Neither certificate specifically states what period is covered, but the court found they did cover the work of May and June, respectively, and the record supports that finding, which is in harmony with the provisions of the contract. This time respondent objected violently to what he claimed were excessive and wholly unjustified withholdings. He stated the necessity *67 which compelled him to insist that the payment provisions of the contract be kept and informed the appellant that if the excess of withheld money was not paid within 48 hours he would consider the contract breached and cease work. Somewhere during this period of stress the following things were shown to have happened: The engineer, in response to a complaint about excessive withholdings, said to respondent’s foreman that he was in a frame of mind that he did not give a “damn” whether they got any money at all or not; that a representative of the district under similar circumstances stated in effect that the withholdings were compelled because the district had no money to pay more.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schellinger Brothers v. Cotter
2 Cal. App. 5th 984 (California Court of Appeal, 2016)
Hartman v. Comm'r
2008 T.C. Memo. 124 (U.S. Tax Court, 2008)
Superior Motels, Inc. v. Rinn Motor Hotels, Inc.
195 Cal. App. 3d 1032 (California Court of Appeal, 1987)
Whitney Investment Co. v. Westview Development Co.
273 Cal. App. 2d 594 (California Court of Appeal, 1969)
Integrated, Inc. v. Alec Fergusson Electrical Contractor
250 Cal. App. 2d 287 (California Court of Appeal, 1967)
Tsarnas v. Bailey
179 Cal. App. 2d 332 (California Court of Appeal, 1960)
Vowels v. Witt
308 P.2d 415 (California Court of Appeal, 1957)
Associated Lathing & Plastering Co. v. Louis C. Dunn, Inc.
286 P.2d 825 (California Court of Appeal, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
273 P.2d 37, 127 Cal. App. 2d 63, 1954 Cal. App. LEXIS 1301, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-empire-sanitary-district-calctapp-1954.