Aetna Casualty & Surety Co. v. Board of Trustees

223 Cal. App. 2d 337, 35 Cal. Rptr. 765, 1963 Cal. App. LEXIS 1535
CourtCalifornia Court of Appeal
DecidedDecember 16, 1963
DocketCiv. 20849
StatusPublished
Cited by8 cases

This text of 223 Cal. App. 2d 337 (Aetna Casualty & Surety Co. v. Board of Trustees) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aetna Casualty & Surety Co. v. Board of Trustees, 223 Cal. App. 2d 337, 35 Cal. Rptr. 765, 1963 Cal. App. LEXIS 1535 (Cal. Ct. App. 1963).

Opinion

TAYLOR, J.

Appellants, the Rincon Valley Union School District of Sonoma County and its Board of Trustees (hereinafter referred to as the District), contracted with Frank S. Glover, doing business as Glover Construction Company (hereinafter referred to as the contractor), for the construction of the Spring Creek Elementary School. The agreement established August 29, 1958, as the completion date and contained a clause stipulating $50 liquidated damages for each day the project remained incomplete. The architect granted an extension to October 3, 1958. The work was not completed within the extended time. In fact, the certificate of completion was not filed until February 5, 1959. The District withheld as liquidated damages $6,250 ($50 a day for 125 days) and the contractor brought this action to recover this sum plus interest. Subsequently, the parties stipulated to an amendment of the complaint to substitute as the real party in interest The Aetna Casualty & Surety Company, subrogee on the contractor’s faithful performance bond.

The contract provided that changes could be made only after formal change orders had been executed as provided under the rules and regulations of the State Division of Architecture. 1 On September 3, 1958, the contractor was advised by the architect of change order 3B in connection with a redwood drop inlet and was instructed not to proceed until notice of approval of the change was processed through the Department of Finance. On September 29, 1958, the contract- or was notified of change order 30 relating to the installation of a rip-rap retaining wall on the bank of Spring Creek. Both *339 of these change orders, as well as No. 4A 2 concerning certain street improvements requested by the City of Santa Rosa, were approved by the Department of Finance on December 26, 1958, and the contractor notified thereof on January 6, 1959.

One of the District’s architects testified that had he known of the time the contractor required to finish the rip-rap retaining wall, he would have granted a further extension. Another of the District’s architects testified that none of the change orders would have justified a further extension of time “Because ... the scope and nature of the work would have permitted the work to have continued concurrently with the original contract without increasing the overall length of time required.” The court found and there was testimony that much of the work of the building remained undone by the extended completion date. There was also testimony that with due diligence, the architects could have gotten the information on the drop inlet to the contractor before September 29, 1958, and submitted the change order to the Department of Finance before November 18, 1959. District architect Feleiano admitted that had he used diligence, he would have gotten the information to the contractor in time for him to have put the inlet in prior to October 3, 1958, the extended completion date. There was testimony that the drop inlet was an integral part of the project, that completion of the contract could not have been certified until this work had been completed and that as a result of the timing of change order 3B, the contractor would have been unable to complete the project by October 3, 1958, through no fault of his own.

The trial court concluded in its memorandum opinion that while the contractor was dilatory and had not substantially performed on the extended completion date (October 3, 1958), the District’s conduct made it impossible for the contractor to perform the terms of the agreement and thus complete the project until January 6, 1959, when the change *340 orders were finally processed. The court found accordingly and awarded judgment to the contractor for $4,750 3 together with interest at the rate of 7 per cent from October 3, 1958, thus allowing the District to retain liquidated damages totaling $1,500 for the 30 days between January 6, 1959, and February 5, 1959, when the project was finally completed. The District appeals from this judgment.

The issues are whether there was sufficient evidence for the trial court to find that the District rendered performance by the extended completion date impossible, and if so, whether the court could apportion liquidated damages.

The facts indicated above clearly establish that while the contractor was behind in the overall job on October 3, 1958, the District, by its own conduct in processing the change orders, rendered performance impossible within the extended time agreed upon by the parties. The District contends that since there was no evidence that it caused any delay in the ultimate completion of the entire project, it should be allowed liquidated damages. We do not agree. The crucial date is that stipulated for completion (Gogo v. Los Angeles etc. Flood Control Dist., 45 Cal.App.2d 334 [114 P.2d 65], citing Champlain Construction Co. v. O’Brien, 117 F. 271; Jefferson Hotel Co. v. Brumbaugh, 168 F. 867 [94 C.C.A. 279]; King Iron Bridge & Mfg. Co. v. City of St. Louis, 43 F. 768 [10 L.R.A. 826]). As stated in Gogo, supra: “By its own act defendant rendered performance within the time limited by the contract impossible and has therefore lost its right to claim the liquidated damages provided in the contract.” (Italics ours.) (P. 344.) Liquidated damages are a penalty not favored in equity and should be enforced only after he who seeks to enforce them has shown that he has strictly complied with the contractual requisite to such enforcement (Jefferson Hotel Co. v. Brumbaugh, supra; Civ. Code, §§ 1670, 1671).

The trial court erred in the apportionment of liquidated damages. In the first place, a proper apportionment would necessarily have to allow the contractor a reasonable time beyond the change order notification on January 6, 1959, within which to complete the work called for. However, the eases clearly hold against any apportionment of liquidat *341 ed damages. In Gogo, supra, the court said: “The correct rule is that where such delays are occasioned by the mutual fault of the parties the court will not attempt to apportion them but will refuse to enforce the provision for liquidated damages. (Jefferson Hotel Co. v. Brumbaugh, 168 F. 867 [94 C.C.A. 279]; Champlain Construction Co. v. O’Brien (Vt.) 117 F. 271.)” It is stated in the Champlain case at page 277: “There is no way for summing up the defaults of each and apportioning the damages to them, but the whole must be allowed or none; and, as all cannot be, none must be.”

The District, of course, retains its right to show actual damages sustained by the contractor’s subsequent delays. As stated in New York Continental Jewell Filtration Co. v. United States, 55 Ct. Cl.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Greg Opinski Construction, Inc. v. City of Oakdale
199 Cal. App. 4th 1107 (California Court of Appeal, 2011)
Central Steel Drum Co. v. Gold Cooperage, Inc.
491 A.2d 49 (New Jersey Superior Court App Division, 1985)
Utica Mut. Ins. Co. v. DiDonato
453 A.2d 559 (New Jersey Superior Court App Division, 1982)
Jasper Construction, Inc. v. Foothill Junior College District
91 Cal. App. 3d 1 (California Court of Appeal, 1979)
Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)
Bilardi Construction, Inc. v. Spencer
6 Cal. App. 3d 771 (California Court of Appeal, 1970)
General Insurance Co. of America v. Commerce Hyatt House
5 Cal. App. 3d 460 (California Court of Appeal, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
223 Cal. App. 2d 337, 35 Cal. Rptr. 765, 1963 Cal. App. LEXIS 1535, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aetna-casualty-surety-co-v-board-of-trustees-calctapp-1963.