Greg Opinski Construction, Inc. v. City of Oakdale

199 Cal. App. 4th 1107, 132 Cal. Rptr. 3d 170, 2011 Cal. App. LEXIS 1279
CourtCalifornia Court of Appeal
DecidedOctober 6, 2011
DocketNos. F060219, F060727
StatusPublished
Cited by6 cases

This text of 199 Cal. App. 4th 1107 (Greg Opinski Construction, Inc. v. City of Oakdale) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greg Opinski Construction, Inc. v. City of Oakdale, 199 Cal. App. 4th 1107, 132 Cal. Rptr. 3d 170, 2011 Cal. App. LEXIS 1279 (Cal. Ct. App. 2011).

Opinion

Opinion

WISEMAN, Acting P. J.

After a bench trial in this dispute between the City of Oakdale (city) and its general contractor on a building project, Greg Opinski Construction, Inc. (Opinski), the trial court awarded the city $54,000 in liquidated damages for late completion, $3,266 for repair of construction defects, prejudgment interest, and $97,775 in attorneys’ fees. The claims in a cross-complaint by Opinski and its performance bond surety, Fidelity and Deposit Company of Maryland, were rejected.

In its statement of decision, the trial court stated that it would not consider whether the late completion was caused by actions of the city. This was because the contract required any extension of time to be obtained through certain procedures, procedures Opinski did not use, so the question of fault for the delays did not arise. Opinski argues that, in so ruling, the trial court contravened the rule laid down by our Supreme Court in Peter Kiewit Sons’ Co. v. Pasadena City Junior College Dist. (1963) 59 Cal.2d 241 [28 Cal.Rptr. 714, 379 P.2d 18] (Peter Kiewit). There the court held that an owner is not entitled to damages for late completion if the lateness was caused by the owner’s conduct, even if the contract barred extensions of time unless requested under specified procedures and the contractor admittedly did not make a request.

In the published part of our opinion, we hold that this aspect of Peter Kiewit was superseded by a 1965 amendment to Civil Code section 1511, which allows parties to specify in a contract that a party intending to avoid the effect of its failure to perform by asserting that the other party’s act caused the failure must give written notice of this intention within a reasonable time. In this case, the contractual provisions requiring certain procedures to be followed by a party requesting an extension of time [1110]*1110amounted to the type of specification contemplated by the amendment to Civil Code section 1511. Since Opinski did not follow those procedures to claim an extension of time, it cannot rely on Peter Kiewit, and the trial court was correct to enforce the procedural requirements of the contract.

We also hold in the published part of our opinion that the court erred when it awarded prejudgment interest to the city. The city was holding retention funds in an escrow account created pursuant to Public Contract Code section 22300, in an amount that exceeded the damages upon which interest was awarded. The city was entitled to access the funds when it determined that Opinski had breached the contract. It had dominion and control of the funds from that point and therefore was not entitled to prejudgment interest.

The trial court ordered the retention funds in the escrow account to be used as a setoff against the judgment. With the interest included, the award consumed the entire escrow balance. The reversal of the interest award will mean that the escrow funds exceed the total amount awarded to the city. We remand so the trial court can modify the judgment to require the city to pay the residue to Opinski.

In the unpublished part of the opinion, we reject the remainder of Opinski’s and the surety’s arguments in these two appeals (cases Nos. F060219 & F060727).

FACTUAL AND PROCEDURAL HISTORIES

On May 3, 2004, Opinski entered into a contract with the city as the general contractor for file project. The city issued a “Notice to Proceed” effective the same day. The contract required the work to be completed within 300 calendar days and provided for liquidated damages of $250 for each day of delay. The 300th day was February 26, 2005, but, according to the architect’s certification of substantial completion, the project was not substantially complete until September 30, 2005, more than seven months late.

The litigation began when a subcontractor sued Opinski for withholding payment. The subcontractor’s claim was dismissed before trial and is not now at issue. Opinski cross-complained against the city for breach of contract. The city answered and cross-complained against Opinski and the surety, also for breach of contract.

Opinski’s claim against the city was that the city wrongfully refused to pay a balance of $164,839 of the contract price plus $24,436 in excess of the contract price for proposed change orders the city had refused to approve, [1111]*1111along with interest and contractual penalties. The $164,839 balance represented an unpaid portion of the “retention” funds. In a construction contract, a retention is a portion of the contract price that is withheld by the owner as a form of security in case of a dispute. “Authorities have noted that a retention occurs when the owner retains a percentage from each progress payment as a form of security against potential mechanics’ liens and as security that the contractor will complete the work properly and repair defects.” (Yassin v. Solis (2010) 184 Cal.App.4th 524, 534 [108 Cal.Rptr.3d 854].) The contract in this case provided for a retention of 10 percent of the contract price. As the progress payments came due, the retention funds were deposited in an escrow account the parties established for that purpose.

The city’s claim against Opinski was that Opinski owed $54,000 in liquidated damages for lateness, $10,000 for defective conditions, and interest. The city also claimed that it was withholding the balance of the contract price in escrow because it had received stop notices from three subcontractors. Stop notices are notices from subcontractors stating that the city should not pay the general contractor an amount the general contractor had failed to pay the subcontractor.

The city did not, however, argue that the stop notices ultimately meant the amount to be paid to Opinski should be reduced. In its posttrial brief, the city suggested that the court should award the city judgment against Opinski for the damages for lateness and defects, but should also direct the city to authorize the release of the funds in escrow to Opinski. Then, according to the city, Opinski should be ordered to pay the amounts at issue in the stop notices to the subcontractors.

The key provisions of the contract for purposes of these appeals concerned the means by which the contract price and the contract time (i.e., the time by which the project was to be completed) could be changed. The parties could only be bound by changes in the completion time or the price that were made in writing through specified procedures. These procedures were included in a lengthy set of provisions called the “General Conditions of the Contract.” Paragraphs 11.2 and 12.1 of the general conditions provided that the completion time and the contract price could be changed only by means of a change order. A change order was defined as a document signed by the contractor and the city that authorized a change in the price, time, or other provision of the contract.

Paragraph 11.2 provided that “[n]o claim for an adjustment in the Contract Price will be valid if not submitted in accordance with this paragraph 11.2.” Paragraph 12.1 included a similar provision about claims for adjustment to the contract time.

[1112]*1112A change order altering the time or price could be executed by either of two routes. First, under paragraph 10.4.2, the parties could execute the order by mutual agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nelson v. Offield CA1/2
California Court of Appeal, 2024
Barham Construction v. City of Riverbank CA5
California Court of Appeal, 2015
Pittsburg Unified School District v. S.J. Amoroso Construction Co.
232 Cal. App. 4th 808 (California Court of Appeal, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
199 Cal. App. 4th 1107, 132 Cal. Rptr. 3d 170, 2011 Cal. App. LEXIS 1279, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greg-opinski-construction-inc-v-city-of-oakdale-calctapp-2011.