Homes & Son Construction Co., Inc. v. Bolo Corp.

526 P.2d 1258, 22 Ariz. App. 303, 1974 Ariz. App. LEXIS 471
CourtCourt of Appeals of Arizona
DecidedOctober 8, 1974
Docket1 CA-CIV 1992
StatusPublished
Cited by43 cases

This text of 526 P.2d 1258 (Homes & Son Construction Co., Inc. v. Bolo Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Homes & Son Construction Co., Inc. v. Bolo Corp., 526 P.2d 1258, 22 Ariz. App. 303, 1974 Ariz. App. LEXIS 471 (Ark. Ct. App. 1974).

Opinion

OPINION

JACOBSON, Chief Judge of Division One.

The issues raised by this appeal and cross-appeal are whether a contractor is entitled to pre-judgment interest on the amount found due under a cost-plus with a maximum construction contract and whether the trial court’s factual determinations are supported by the evidence.

This protracted litigation originated out of a contract entered into on December 27, 1963 between the plaintiff-appellant Homes & Son Construction Co. (Homes) as contractor, and defendant-cross-appellant Bolo Corporation (Bolo) as owner, whereby Homes agreed to construct a shopping center facility for Bolo. Prior to construction, Bolo had entered into leases with Skaggs Drug Center, Inc., and Mayfair Markets dba El Rancho Markets as prospective tenants of the shopping center.

The contract required that cost of the construction would not exceed a guaranteed maximum of $378,000. This guaranteed maximum was arrived at by providing that Bolo would reimburse Homes for certain costs of construction not to exceed $348,000 and in addition pay a contractor’s fee of eight percent of the total cost of the work performed or $30,000, whichever sum was the lesser.

The contract further provided that construction would be completed 180 days after receipt of a notice to proceed with a penalty clause of $100 per day for each day delay beyond the 180-day period. In addition, all change orders on work were to be in writing.

On January 8, 1964, Bolo gave notice to Homes to commence construction and Homes engaged in some site preparation immediately following this notice, although Homes did not obtain a building permit from the City of Mesa until January 15, 1964.

During the course of construction, Bolo made periodic payments to Homes totalling $299,376.00 as of July, 1964. On September 14, 1964, Homes submitted a final billing claiming reimbursable costs of $342,080.89 and a contractor’s fee of $27,366.47, together with some $18,000.00 as required by change orders. He claimed a balance due of $88,181.92. When this billing was objected to, a revised billing was made on October 5, 1964 and submitted, claiming a balance due of $87,143.50. Again, this billing was disputed and on December 15, 1964, Homes brought this action seeking the claimed balance due under the contract. Bolo filed a counterclaim in that action alleging defective construction and failure to follow specifications. Subsequently, the complaint was amended to request arbitration. The trial court ordered arbitration, an award was entered and subsequently confirmed by the trial court. The judgment confirming the arbitration award was appealed and subsequently reversed by the Arizona Supreme Court, which remanded the matter to the superior court for trial. See, Bolo Corp. v. Homes & Son Construction Co., Inc., 105 Ariz. 343, 464 P.2d 788 (1970).

On February 4, 1966, Homes again submitted a billing to Bolo, showing a balance due of $87,022.15. This billing, together with the October 5, 1964 billing, formed the basis for a stipulation by the parties that the entire cost of the job totalled $352,162.13 and left to the court the determination of whether $4,557.32 claimed by Homes were proper charges. The trial court subsequently found that $2,200.00 of this claimed sum was a proper charge and further found that had Homes completed *306 the construction timely in accordance with plans and specifications it would have due and owing $86,519.00. The trial court further found that the construction commenced on January 15, 1964 and was substantially completed on August 7, 1964; found that Bolo was entitled to damages for Homes failing to complete the work in 180 days in the sum of $2,500.00; found that Homes had failed to comply with plans and specifications and awarded damages to Bolo in the sum of $17,670.00; and entered judgment in favor of Homes in the sum of $62,892.00 after deducting Bolo’s damages, but denied Homes pre-judgment interest.

Homes has appealed the denial of prejudgment interest. Bolo has cross-appealed, contending that the construction was never successfully completed; that the trial court incorrectly determined the commencement and termination of construction dates; and that the trial court did not fully award damages for faulty construction.

PRE-JUDGMENT INTEREST

Both parties agree that a creditor is entitled to interest on its debt prior to judgment provided the sum demanded is “liquidated.” See, L. M. White Contracting Co. v. St. Joseph Structural Steel Co., 15 Ariz.App. 260, 488 P.2d 196 (1971); Arizona Eastern Railroad Co. v. Head, 26 Ariz. 259, 224 P. 1057 (1924). Where the parties disagree is whether Homes’ claim was “liquidated.” Bolo contends the claim was “unliquidated” for three reasons: (1) in a cost-plus contract over which disputes arise as to the items comprising the cost, the claim is not liquidated; (2) the existence of an unliquidated counterclaim renders the account unliquidated; and (3) where the amount of judgment differs from the amount of demand, the claim is obviously unliquidated.

We start with the definition that a claim is liquidated “if the evidence furnishes data which, if believed, makes it possible to compute the amount with exactness, without reliance upon opinion or discretion.” Arizona Title Insurance & T. Co. v. O’Malley Lbr. Co., 14 Ariz.App. 486, 496, 484 P.2d 639, 649 (1971).

We turn then to Bolo’s first contention that a cost-plus contract is incapable of being liquidated because of the existence of disputes arising out of the items comprising the account. We first note that merely because the amount due under a contract is computed on the basis of the cost of a project plus a stated percentage, does not render the amount due incapable of being computed exactly, so as to preclude pre-judgment interest. Coleman Engineering Co. v. Northern American Aviation, 65 Cal.2d 396, 55 Cal.Rptr. 1, 420 P.2d 713 (1967). However, unless the contract provides otherwise, it is the obligation of the creditor to supply to the debtor sufficient information and supporting data so as to enable the debtor to ascertain the amount owed and interest does not begin to run until such data is supplied. Conderback, Inc. v. Standard Oil of California, Western Operations, 239 Cal.App.2d 664, 48 Cal.Rptr. 901 (1966). Having once supplied such information, the creditor is entitled to such interest on the amount of money the debtor retains which he ought to pay. Mere differences of opinion as to the amount due does not preclude pre-judgment interest since disputes as to liability itself does not preclude interest. Arizona Title Insurance & T. Co. v. O’Malley Lbr. Co., supra.

Moreover, the debtor who in good faith contests the amount due may stop interest from accruing on the amount he contends is due by making and keeping good an unconditional tender of the amount he contends is owing. Laycock v. Parker, 103 Wis. 161, 79 N.W. 327 (1899).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Strategic Diversity, Inc. v. Alchemix Corp.
664 F. App'x 660 (Ninth Circuit, 2016)
monroe/pirtle v. Gagan
Court of Appeals of Arizona, 2015
Precision Heavy Haul, Inc. v. Trail King Industries, Inc.
228 P.3d 895 (Court of Appeals of Arizona, 2010)
Dixie Bell, Inc. v. Redd
656 S.E.2d 765 (Court of Appeals of South Carolina, 2007)
Gorman v. State ex rel. Owens
155 P.3d 1054 (Court of Appeals of Arizona, 2007)
Collins v. D.R. Horton, Inc.
361 F. Supp. 2d 1085 (D. Arizona, 2005)
Ry-Tan Construction, Inc. v. Washington Elementary School District No. 6
93 P.3d 1095 (Court of Appeals of Arizona, 2004)
AMHS Insurance v. Mutual Insurance
258 F.3d 1090 (Ninth Circuit, 2001)
Shoen v. Shoen (In re Shoen)
176 F.3d 1150 (Ninth Circuit, 1999)
Alta Vista Plaza, Ltd. v. Insulation Specialists Co.
919 P.2d 176 (Court of Appeals of Arizona, 1996)
Burkholder v. Cherry
607 A.2d 745 (Superior Court of Pennsylvania, 1992)
State v. BHP Petroleum Co., Inc.
804 P.2d 671 (Wyoming Supreme Court, 1991)
Wayne Smith Construction Co. v. Wolman, Duberstein, & Thompson
363 S.E.2d 115 (Court of Appeals of South Carolina, 1987)
La Paz County v. Yuma County
735 P.2d 772 (Arizona Supreme Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
526 P.2d 1258, 22 Ariz. App. 303, 1974 Ariz. App. LEXIS 471, Counsel Stack Legal Research, https://law.counselstack.com/opinion/homes-son-construction-co-inc-v-bolo-corp-arizctapp-1974.