Precision Heavy Haul, Inc. v. Trail King Industries, Inc.

228 P.3d 895, 224 Ariz. 159
CourtCourt of Appeals of Arizona
DecidedJanuary 20, 2010
Docket1 CA-CV 08-0107
StatusPublished
Cited by8 cases

This text of 228 P.3d 895 (Precision Heavy Haul, Inc. v. Trail King Industries, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Precision Heavy Haul, Inc. v. Trail King Industries, Inc., 228 P.3d 895, 224 Ariz. 159 (Ark. Ct. App. 2010).

Opinion

OPINION

WEISBERG, Judge.

¶ 1 Precision Heavy Haul, Inc. (“Precision”) appeals from the trial court’s denial of prejudgment interest on a judgment in Precision’s favor following a jury trial. The trial court ruled that because the defendant, Trail King Industries, Inc. (“Trail King”), had raised comparative fault as a defense, Precision’s claim was for an unliquidated sum and not subject to prejudgment interest. In a separate unpublished memorandum decision, we address and affirm as to all issues raised in Trail King’s cross-appeal, which challenges the admission of expert testimony on Precision’s behalf as well as the process for selecting jury pools in Maricopa County superior courts. For reasons that follow, however, we reverse the ruling denying prejudgment interest and remand for further proceedings.

BACKGROUND

¶ 2 Precision filed suit against Trail King and Carlisle Companies, Inc., alleging that Trail King had manufactured and sold to Precision a trailer for transporting heavy loads, that the trailer’s negligent design and manufacture caused it to fail, and that in doing so, the trailer and the energy transformer being transported on it were damaged. Precision alleged claims of negligence, strict liability, and breach of warranty. Trail King’s answer asserted that Precision had negligently used or altered the trailer and that its damages “were caused or contributed to by [Precision’s] own comparative negligence or assumption or [sic] risk which bar[red] or reduce[d] on a comparative basis” its claims.

¶ 3 At trial, Precision’s owner testified that his company had incurred $694,550.87 in damages and offered testimony by two experts concerning the cause of the accident that damaged the transformer. The jury returned a verdict finding Trail King 100% at fault and awarding $694,550.87 in damages to Precision. The sole issue raised by Precision’s appeal is the court’s denial of prejudgment interest. We have jurisdiction of the appeal pursuant to Arizona Revised Statutes (“A.R.S.”) section 12-2101(B) (2003).

DISCUSSION

Denial of Prejudgment Interest

¶ 4 A party’s entitlement to prejudgment interest presents a question of law for our de novo review. Gemstar Ltd. v. Ernst & Young, 185 Ariz. 493, 508, 917 P.2d 222, 237 (1996); Alta Vista Plaza, Ltd. v. Insul. Specs. Co., Inc., 186 Ariz. 81, 82, 919 P.2d 176, 177 (App.1995); Employer’s Mut. Cas. Co. v. McKeon, 170 Ariz. 75, 77, 821 P.2d 766, 768 (App.1991). In addition, a party with a liquidated claim is entitled to prejudgment interest as a matter of right and is so entitled whether “the claim sounds in contract or in tort.” Employer’s Mut. Ins. Co., 170 Ariz. at 78, 821 P.2d at 769 (citation omitted).

¶ 5 An exhibit summarizing Precision’s damages was admitted at trial. The listed damages were: rigging and crew expenses in the amount of $28,590.00; crane and salvage crew expenses in the amount of $14,768.02; payment to Precision’s customer for damages to the energy transformer in the amount of $495,000.00; and funds owed to Precision but set off by its customer in the amount of $156,192.85. These requested damages totaled $694,550.87. At trial, Trail King ultimately did not challenge the accuracy of the total damages. Instead, it denied any negligence but asked, if found negligent, that the jury attribute a percentage of comparative fault to Precision, thereby reducing its own liability.

¶ 6 Rejecting any attribution of fault to Precision, the jury returned a verdict finding Trail King 100% at fault and awarding Precision damages in the exact amount requested. Precision then moved for a determination of its right to prejudgment interest. It argued that a claim is liquidated “if the evidence furnishes data which, if believed, makes it possible to compute the amount with exactness, without reliance upon opinion or discretion.” Employers Mut. Cas. Co., 170 Ariz. at 78, 821 P.2d at 769. Because its damages could be precisely calculated by “simple com *161 putation,” Precision sought prejudgment interest from the date of the accident, i.e., when it became obligated to pay its customer for the damaged transformer. Precision also asserted that although the expenses for crews, hotels, meals, and equipment rental occurred over time, the final expenses had been incurred by January 22, 2001 and thus that these damages, which totaled $43,358.02, should accrue interest as of that date. It requested a total of $365,936.97 in prejudgment interest.

¶ 7 Trail King objected, arguing that when a jury must exercise its discretion to apportion fault, the claim is not liquidated. Without Arizona precedent on point, it cited a South Dakota case in which the supreme court there upheld the denial of prejudgment interest in a construction defect ease in which the plaintiff was found to be thirty percent at fault. 1 S. Dakota Bldg. Auth. v. Geiger-Berger Assoc., 414 N.W.2d 15, 17, 20 (S.D.1987). That court held that although the plaintiffs “loss became liquidated upon receiving the billing for the repairs, and upon paying for such repairs,” id. at 20, prejudgment interest could not accrue because the defendants could not know what portion of the damages they would have to pay until the jury had allocated fault among the parties. Id. at 22.

¶ 8 Trail King also relied upon Wisper Corp. N.V. v. California Commerce Bank, 49 Cal.App.4th 948, 57 Cal.Rptr.2d 141 (1996), which interpreted a statute identical to that of South Dakota. Because the jury had found the plaintiff to be seventy-five percent at fault and therefore had awarded “a mere 25 percent of its claimed damages,” id. at 149, the court reasoned that the “large discrepancy” between the amount sought and the amount awarded militated against finding that the plaintiffs damages were sufficiently “certain” for purposes of prejudgment interest. 2 Id. at 148.

¶ 9 Trail King also argued that because Precision’s damages included a number of “estimated and indefinite” items subject to jury scrutiny for reasonableness and causation, the damages were unliquidated. Precision, of course, disagreed and replied that any uncertainty over liability for the accident should not bar prejudgment interest if the amount of damages was certain, citing Banner Realty, Inc. v. Turek, 113 Ariz. 62, 64, 546 P.2d 798, 800 (1976). It argued that at the very least its damages were liquidated on the day it paid the transformer’s owner for the damages to the transformer.

¶ 10 The tidal court acknowledged differing approaches taken by our sister states in cases involving comparative fault but found Wisper persuasive

Related

JH Kelly, LLC v. Quality Plus Services, Inc.
472 P.3d 280 (Court of Appeals of Oregon, 2020)
Sirrah Enterprises, LLC v. Wunderlich
377 P.3d 360 (Court of Appeals of Arizona, 2016)
Custom Homes by Via, LLC v. Bank of Oklahoma, Na
637 F. App'x 356 (Ninth Circuit, 2016)
monroe/pirtle v. Gagan
Court of Appeals of Arizona, 2015
Charles W. Stenz v. City of Tucson and Pinnacle Risk Management Services
336 P.3d 737 (Court of Appeals of Arizona, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
228 P.3d 895, 224 Ariz. 159, Counsel Stack Legal Research, https://law.counselstack.com/opinion/precision-heavy-haul-inc-v-trail-king-industries-inc-arizctapp-2010.