Gearing v. United States

48 Ct. Cl. 12, 1912 U.S. Ct. Cl. LEXIS 5, 1912 WL 1165
CourtUnited States Court of Claims
DecidedDecember 2, 1912
DocketNo. 22550
StatusPublished
Cited by4 cases

This text of 48 Ct. Cl. 12 (Gearing v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gearing v. United States, 48 Ct. Cl. 12, 1912 U.S. Ct. Cl. LEXIS 5, 1912 WL 1165 (cc 1912).

Opinion

Peelee, Ch. J.,

The claimant on August 11,1894, entered into the contract made part of the petition, wherein for the consideration of $117,527 he agreed to furnish the materials, labor, and appliances and to do all the work therein specified in the construction of the power house ,and office building for the 800-foot lock, St. Marys Falls Canal, Mich., and to complete the same' in all respects by December 31, 1895.

The claimant entered upon the performance of the contract, and after expending all his available money — about $16,000 — he was unable to proceed further with the work, and his bondsmen thereafter furnished the residue of the money, and the work was completed and in the main under the claimant’s supervision; was accepted by the Government, and the' [22]*22full contract price therefor w,as paid less $579.55, deducted as expenses of inspection and supervision during the period of extension after December 31, 1896, as shown in finding VII.

The claim herein is for extra and additional labor and materials and for expenses during periods of delay caused by the Government and for deductions for inspection, for profits and for superintendence by the claimant, as set forth in the findings.

The .contract is a rigid one, but it was of the claimant’s making, with full knowledge and information of all the facts, and the duty of the court is simply to construe the contract as thus entered into and to determine what work and materials were or were not within the terms of the contract.

• Eespecting generally the claims for extra work and materials, paragraph 46 of the specifications, as well as the eighth paragraph of the contract, provide in substance that no claim whatever shall at any time be made by the contractor on account of any extra work or materials performed or furnished unless the same shall first be expressly required and an agreement therefor entered into in writing, wherein the prices and quantities shall be agreed upon by the parties and approved by the Chief of Engineers. The paragraph of the specifications referred to also includes claims arising from delays of any kind.

No extra or additional work was required in writing, nor was any agreement therefor entered into in writing or otherwise. On the contrary, the officer in charge insisted at the time that the work performed was only such as that required by the terms of the contract, and no bad faith is shown. A like contention was upheld in the case of United States v. Gleason (175 U. S., 588, 607), the court saying: “We are permitted, and indeed required, in the absence of evidence of bad faith on his part, to presume that he acted with due regard to his duties as between the Government and the contractors.”

By paragraph 439 of the specifications it was provided that “ The object of the foregoing specifications is to secure the complete construction of the building, using the best mate[23]*23rials and workmanship of the several kinds specified, and the contractor will be held to this object, although some minor matters may have been overlooked ”; while paragraph 32 of the specifications provides that “ Should any doubt arise as to the quality of the work required by the plans and specifications, it shall be decided by using the best class of work that any interpretation will admit of.”

Here again the contractor was bound to know that he would be held to “the best materials and workmanship * * * although some minor matters may have been overlooked,” and in case of doubt as to the quality of the work the officer in charge was therein authorized to decide the matter “ by using the best class of work that any interpretation will admit of.”

The claimant contends that he was put to extra expense by reason of the delays of the Government in the completion of the excavation and wall foundations. But conceding this to be true, paragraph 41 of the specifications provides that Should there be any delay in the completion of the excavation and wall foundations, the time set for the completion of the contract shall be extended an amount equal to such delay.”

Such extension was granted for all the delays of the Government, as set forth in Finding VII, and this court in the case of Merchants’ Loan & Trust Co. (40 C. Cls., 117, 132) held a like provision as valid and binding as any other part of the contract.

The contract further provides that “All materials furnished and work done under this contract shall, before being accepted, be subject to a rigid inspection by an inspector appointed on the part of the Government, and such as do not conform to the specifications set forth in this contract shall be rejected. The decision of the engineer officer in charge as to quality and quantity shall be final.”

Referring to the authority of the engineer in charge to determine the quantity and quality of materials to be- furnished, the court in the case of Barlow v. United States (35 C. Cls., 514, 546) said: “ Some one must pass upon the fitness of the material, the sufficiency of the workmanship, the [24]*24amount of work performed, etc. These are matters which can not be left until a building is completed; it is for the interest of both parties that they be settled as the work proceeds. The architect or engineer in charge being the person most familiar with the work, and professionally fitted to pass upon such questions, is ordinarily designated as the referee or arbitrator to determine them. Such agreements for such arbitraments must be upheld.”

This being true it was incumbent upon' the Government to provide some person competent to make such inspection, and this it appears to have done. Finding XVI recites in substance that the engineers and inspectors in charge of the work were honest and capable officials, being graduates in their profession of civil engineering from reputable schools and, though lackingi in experience in the construction of a like building, had practical experience in masonry and brickwork, which constituted two-thirds of the work under the contract; and though they erred in requiring certain work to be done outside of the contract they appear to have performed their duties in good faith; and other than as shown in Finding VII as to delays and extensions of time under paragraph 41 of the specifications they were not responsible for any delays in the performance of the work. Therefore, in the absence of any evidence of bad faith, or such gross error as to imply bad faith, on the part of the officers their acts must be upheld. United States v. Gleason, supra, and many other cases which need not be cited.

Whenever the contractor was aggrieved at the rulings or requirements of the .local engineer or inspector he was at liberty to formally protest and appeal therefrom to the enginéer in charge. This he appears to have done in three instances. First, as set forth in item 4 of Finding X respecting the additional claim for cornices in the side halls. The claimant protested against doing the work and appealed to the engineer officer in charge who decided to leave the matter to the local engineer, who required the claimant.to perform the work, which he did, and for which we have allowed. Two other appeals were taken as set forth in Finding XIII, wherein, as shown by-his. petition, he claimed $1,100 expense [25]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
Schmoll v. United States
86 Ct. Cl. 632 (Court of Claims, 1938)
Weller Construction Co. v. United States
61 Ct. Cl. 261 (Court of Claims, 1925)
Poole Engineering & Machine Co. v. United States
57 Ct. Cl. 232 (Court of Claims, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
48 Ct. Cl. 12, 1912 U.S. Ct. Cl. LEXIS 5, 1912 WL 1165, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gearing-v-united-states-cc-1912.