Savage Construction Co. v. United States

47 Ct. Cl. 298, 1912 U.S. Ct. Cl. LEXIS 99, 1911 WL 1357
CourtUnited States Court of Claims
DecidedMarch 4, 1912
DocketNo. 28682
StatusPublished

This text of 47 Ct. Cl. 298 (Savage Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Savage Construction Co. v. United States, 47 Ct. Cl. 298, 1912 U.S. Ct. Cl. LEXIS 99, 1911 WL 1357 (cc 1912).

Opinion

Peelle, Ch. J.,

delivered the opinion of the court:

This action arises out of the annulment of a contract entered into by the claimant and the Government through Capt. C. S. Riche, Corps of Engineers, United States Army, whereby the claimant company agreed “ to furnish all labor, appliances, and material, and to excavate channels for watercourses and construct foundations for abutments and piers for four aqueduct bridges along miles 31, 36, 44, and 51, western section Illinois and Mississippi Canal,” the work to be completed by September 28, 1904, which contract was approved by the Chief of Engineers October 30, 1903; buc owing to unfavorable weather work thereunder was not commenced until April following, and from that date up to September 24, 1904, the claimant had performed only about 26 per cent of the entire work, and by reason thereof it asked for an extension of the contract to July 1, 1905, which was granted with the approval of the Chief of Engineers.

Under the extended contract the claimant company continued to work up to December 31, 1904, during which time it performed about 15 per cent additional work, or in all under the contract 41 per cent, thereby earning $18,860.80 (a fraction less than 40 per cent of the contract price), which was paid, less 10 per cent deduction therefrom as stated in Finding YII. The contractor was admonished in November by the Chief of Engineers that any concrete work done in freezing weather would be at its own risk, and if found unstable in the spring would have to be done over at the contractor’s cost. The work continued, however, as before stated, until December 31, 1904, when, owing to the [305]*305severity of the weather, work was suspended. Of ail the work done, aqueduct No. o was about half finished; at No. 6, a little less than half, while at No. 7 the work was practically completed. At No. 4, the most difficult of construction, no work whatever had been done up to the date of the annulment of the contract hereinafter referred to.

From the close of work December 31, 1904, until the annulment of the contract the condition of the weather was such that no work could be done, yet the engineer in charge notified the contractor February 18, 1905, that the Government had decided under paragraph 70 of the specifications to procure the necessary appliances, materials, and labor therefor, and to construct aqueduct No. 4, leaving the claimant to complete the other aqueducts, to which the contractor responded March 15, denying the officer’s authority so to do, and informing him that all the appliances and materials necessary to complete the work had been purchased and that same would be on the ground when the season opened and the work completed within the extended period. Immediately upon receipt of this information the officer abandoned the taking over of the work at aqueduct No. 4, and in lieu thereof, notwithstanding the weather conditions were the same, he recommended the annulment of the contract.

The findings show that had the contractor been permitted to proceed with the work the same would have been completed within the extended period, but at a loss owing to the lowness of its bid, which was about 30 per cent less than each of the bids of two other persons for the same work.

The claimant’s contention is that the annulment under the conditions stated was capricious and in violation of the contract, and therefore without warrant in law. With this contention we agree.

The provision of paragraph 4 of the contract, upon which the Government grounds its right to annul the same and charge to the contractor the cost of completing the work in excess of the price agreed to be paid to the contractor, reads as follows:

“4. If, in any event, the party of the second part shall delay or fail to commence with the delivery of the material [306]*306or the performance of the work on the day specified herein, or shall, in the judgment of the engineer in charge, fail to prosecute faithfully and diligently the work in accordance with the specifications and requirements of this contract, then, in either case, the party of the first part, or his successor legally appointed, shall have power, with the sanction of the Chief of Engineers, to annul this contract by giving notice in writing to that effect to the party (or parties, or either of them) of the second part, and upon the giving of such notice all payments to the party or parties of the second part under this contract shall cease, and all money or reserved percentage due or to become due the said party or pai’ties of the second part by reason of this contract shall be retained by the party of the first part until the final completion and acceptance of the work herein stipulated to be done; and the United States shall have the right to recover from the party of the second part whatever sums may be expended by the party of the first part in completing the said contract in excess of the price herein stipulated to be paid the party of the.second part for completing the same, and also all costs of inspection and superintendence incurred by the said United States, in excess of those payable by the said United States during the period herein allowed for the completion of the contract by the party of the second part; and the party of the first part may deduct all the above-mentioned sums out of or from the money or reserved percentage retained as aforesaid; and upon the giving of the said notice the party of the first part shall be authorized to proceed to secure the performance of the work or delivery of the materials, by contract or otherwise, in accordance with law.”

By the terms of the contract the authority to annul the same depends, so far as material here, upon whether the contractor “in the judgment of the engineer officer in charge” failed “to prosecute faithfully and diligently the work” in accordance therewith.

The failure to complete the work within the original contract period, we have found, was in effect the fault of the contractor; but the contract having been extended, said failure, though the same might have been considered by the officer in determining whether a further extension of time should be granted, United States v. Gleason (175 U. S., 588, 606), could not be considered as a basis for the annulment of the contract, as all prior delinquencies in that respect [307]*307were canceled when the contract was extended. True, as held in a long line of decisions both by the Supreme Court and this court, the decision of the engineer officer in charge, in the absence of fraud or such gross error as to imply bad faith, will control in matters.wherein he is required to exercise his judgment. Kihlbery v. United States (97 U. S., 398); Sweeny v. United States (109 U. S., 618).

Paragraph 70 of the specifications, under which the engineer officer first sought to take over the work at aqueduct No. 4, provides:

“ Should any contractor, not hindered by natural causes beyond his control, fail to maintain a sufficient Avorking force of men and appliances, or if it becomes evident that the work is not being prosecuted with proper diligence to complete it within the contract time, the engineer officer in charge shall have power to employ additional labor and appliances and to procure necessary material at such cost as he may deem necessary,” etc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kihlberg v. United States
97 U.S. 398 (Supreme Court, 1878)
Sweeney v. United States
109 U.S. 618 (Supreme Court, 1884)
United States v. Behan
110 U.S. 338 (Supreme Court, 1884)
United States v. Gleason
175 U.S. 588 (Supreme Court, 1900)
United States v. Barlow
184 U.S. 123 (Supreme Court, 1902)
Barlow v. United States
35 Ct. Cl. 514 (Court of Claims, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
47 Ct. Cl. 298, 1912 U.S. Ct. Cl. LEXIS 99, 1911 WL 1357, Counsel Stack Legal Research, https://law.counselstack.com/opinion/savage-construction-co-v-united-states-cc-1912.