Sun Shipbuilding & Dry Dock Co. v. United States

76 Ct. Cl. 154, 1932 U.S. Ct. Cl. LEXIS 293, 1932 WL 2069
CourtUnited States Court of Claims
DecidedNovember 14, 1932
DocketNo. H-349
StatusPublished
Cited by20 cases

This text of 76 Ct. Cl. 154 (Sun Shipbuilding & Dry Dock Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sun Shipbuilding & Dry Dock Co. v. United States, 76 Ct. Cl. 154, 1932 U.S. Ct. Cl. LEXIS 293, 1932 WL 2069 (cc 1932).

Opinion

Whaley, Judge,

delivered the opinion of the court:

The plaintiff, a Pennsylvania corporation, under date of September 14, 1922, entered into a written agreement with the defendant, acting through B.. W. Crawford, major, Corps of Engineers, United States Army, therein designated the contracting officer, representing the United States, whereby it undertook to furnish, in conformity with the advertisement and specifications attached to and forming part of the contract, “ all the necessary labor, material, machinery, equipment (except as specified), erect and install the engines and equipment specified, construct, test, and deliver afloat at contractor’s yard at Chester, Pa., together with the test data, records of weights, patterns, and plans, four Diesel electric seagoing hopper dredges ” for a total consideration of $2,528,240. The plaintiff received notice of the approval of the contract by the Chief of Engineers [172]*172on September 21,1922. The first dredge was to be delivered within 16 months from the approval of the contract and one dredge each succeeding month until all were delivered. The dredges were given numbers by the plaintiff and names by the defendant as follows:

Number 58_A. MaeKenzie.
Number 59_W. L. Marshall.
Number 60_Dan O. Kingman.
Number 61_Wm. T. Kossell.

Dredges of this type had never been built by the Government before and the officers in charge of the work for the defendant had no experience in marine work. Certain engines, material, and equipment were to be provided by the defendant.

The specifications were in minute detail and the contractor was to provide detailed working plans from the specifications and these plans had to be submitted to the contracting officer for inspection and approval. In each case the working plans, prepared by the contractor from the specifications, according to which all the work was accomplished, were signed and approved by the contracting officer.

This suit is brought to recover for (a) alleged extra work performed and not paid for by the defendant; (b) delays caused by the performance of this extra work for which no allowance in remission of liquidated damages was granted; (o) extension of time in remission of delays caused by extra work ordered and paid for by the defendant; (d) unavoidable delay caused through no fault of plaintiff which was not allowed by defendant in mitigation of liquidated damages ; and (e) extra work and changes ordered by defendant and performed by plaintiff after the contract completion dates of delivery of the respective dredges and for which period liquidated damages were assessed. The plaintiff contends that the question of what was extra work and the extension of time by reason thereof; the extension of time for completion, due to delays caused by the defendant, and the remission of liquidated damages by reason thereof were not determined and decided by the officer mutually agreed upon and named in the contract.

[173]*173The plaintiff contends tbe specifications require the Assistant Chief of Engineers to be the contracting officer and that another officer lower in rank was named in the contract. Before plaintiff signed the contract its board of directors passed a resolution authorizing the proper officers to enter into a contract with R. W. Crawford, as contracting officer, and when plaintiff signed the contract it knew Crawford was named therein as contracting officer. It had a right to have the assistant to the Chief of Engineers as the contracting officer, but this right it waived by resolution of its board of directors and the signing of the contract which specifically named Crawford as the contracting officer.

Throughout the entire contract plaintiff recognized Crawford as the contracting officer. The plaintiff is bound by its own actions.

(1) Re fairing Engines

Under the specifications the Government was to furnish the main engines together “with the necessary parts for ■converting same from marine type to type suitable for ■direct connection to main generator * * *.” These engines were purchased from the Shipping Board by the ■contracting officer.

It was discovered when the engines for the MacKenzie (No. 58) and Marshall (No. 59) were assembled by the plaintiff that the bolt holes in the flanges of the engine shafts and those of the generator shafts were not aligned. It was necessary to plug and weld the old holes and to drill new holes in the correct alignment. This discovery was not riiade until the engines were in the hold of one of the vessels and •entailed much laborious work which interfered with the scheduled progress of the construction of other parts of the work. The defendant paid for this work as an extra. The plaintiff made a claim under article 5 of the contract for an extension of time because of delay caused by the defendant. The contracting officer admitted the delay was caused by the Government but declined to recommend to the Chief of Engineers extension of time. The Chief of Engineers extended the time to the completion of the contract, [174]*174in which to make a claim for deduction of liquidated damages and remission for acts of delay occasioned by the Government. There is no evidence in the record to show that the Chief of Engineers at any time thereafter definitely passed on this question of extension of time for completion. The uncontradicted evidence shows that at least 45 days’ delay was occasioned by the repairs to these engines. The completion of these two ships was delayed by the defendant but the actual extent of the delay is not determinable from the evidence. The Chief of Engineers should have decided the number of delay days caused by the Government.

The contract provided remission of damages should be decided by the Chief of Engineers upon recommendation of the contracting officer when the Government delayed the contractor. The plaintiff was entitled under the terms of the contract to a fair, impartial decision by the Chief of Engineers, and upon his failure to so decide cannot be held for liquidated damages for the period involved. Shippey et al. v. United States, 49 C.Cls. 151, 171.

(2) Hopper Door Operating Gear

Paragraph 205 of the specifications provided “ the operating mechanism shall be of the motor-driven type, operating through gears, threaded shaft, crosshead, sliding channel bars, and connecting chains and rods, essentially as shown.” The defendant decided to use a different arrangement and ordered as an extra “ electric hydraulic gear, for operating-the-water-tight doors * *

The plaintiff was paid for this change. However, when the ship listed the pump and motor of one gear failed to operate satisfactorily the other gear, and, due to friction of the entire installation, the mechanism would not overhaul with one gate.

The plaintiff installed the electric hydraulic gear according to the plans and specifications fully approved and adopted by and under the direction of the defendant. There was nothing wrong with the installation, but the arrangement was unsatisfactory. The plaintiff did not undertake-to guarantee the working of the gear to be satisfactory to the [175]*175defendant. There is no evidence that the gear failed to work due to faulty installation, but it did not combine both a pull and push ram.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amatea/Grimberg JV
Armed Services Board of Contract Appeals, 2023
Toombs & Co. v. United States
31 Cont. Cas. Fed. 72,149 (Court of Claims, 1984)
J. L. Simmons Company, Inc. v. The United States
412 F.2d 1360 (Court of Claims, 1969)
New York Shipbuilding Corporation v. The United States
385 F.2d 427 (Court of Claims, 1967)
McShain v. United States
65 F. Supp. 589 (Court of Claims, 1946)
Germain Lumber Co. v. United States
56 F. Supp. 1001 (W.D. Pennsylvania, 1944)
Needles ex rel. Needles v. United States
101 Ct. Cl. 535 (Court of Claims, 1944)
Austin Engineering Co. v. United States
97 Ct. Cl. 68 (Court of Claims, 1942)
McGlone v. United States
96 Ct. Cl. 507 (Court of Claims, 1942)
Penker Construction Co. v. United States
96 Ct. Cl. 1 (Court of Claims, 1942)
Hirsch v. United States
94 Ct. Cl. 602 (Court of Claims, 1941)
H. W. Zweig Co. v. United States
92 Ct. Cl. 472 (Court of Claims, 1941)
Goltra v. United States
91 Ct. Cl. 42 (Court of Claims, 1940)
Orleans Dredging Co. v. United States
90 Ct. Cl. 360 (Court of Claims, 1940)
Phoenix Bridge Co. v. United States
85 Ct. Cl. 603 (Court of Claims, 1937)
McShain Co. v. United States
83 Ct. Cl. 405 (Court of Claims, 1936)
Murch Bros. Construction Co. v. United States
81 Ct. Cl. 574 (Court of Claims, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
76 Ct. Cl. 154, 1932 U.S. Ct. Cl. LEXIS 293, 1932 WL 2069, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sun-shipbuilding-dry-dock-co-v-united-states-cc-1932.